四三峡工程已经后延,华中、华东电网缺电需要抓紧解决。根据华中、华东电网的30年电源建设规划,三峡应在1997年投产,现按1989年开工,2000年投入2台机组(136万千瓦),比规划中2000年要求投入一半容量(845万千瓦,送电华东300万千瓦)少了709万千瓦,这就迫切需要尽快安排其他水火电站补上。华东电网除将规划中应在2000年前投产的滩坑(60万千瓦)、珊溪(24万千瓦)、天荒坪蓄能(150万千瓦)、西邢冲蓄能(60万千瓦)等水电站抓紧进行工作外,还必须要增加300万千瓦火电替补。规划中到2000年原需增加火电3625万千瓦,每年共需煤1.09亿吨(其中由山西调入7050万吨),再加300万千瓦后,每年需
The Three Gorges Project has been postponed, and power shortages in Central and East China Power Grids need to be resolved. According to the 30-year power supply construction plan for the Central and East China Power Grid, the Three Gorges project should be put into production in 1997. The project is now starting in 1989. Two generating units (1.36 million kilowatts) were put into operation in 2000, which is half the capacity required in the plan for 2000 (8.45 million kilowatts). 3.7 million kilowatts of electricity was lost in East China’s 3 million kilowatts of power transmission. This urgently requires that other hydropower stations should be replaced as soon as possible. In addition to the East China Power Grid plans to put into production in 2000 before the pit (600,000 kilowatts), Shanxi (24 million kilowatts), Tianhuangping energy (1.5 million kilowatts), West Xingchong energy (600,000 kilowatts) Other hydropower stations have to step up their work, but they must also add 3 million kilowatts of thermal power substitutes. In the plan, by the year 2000, 36.25 million kilowatts of thermal power will be needed, and a total of 109 million tons of coal will be required each year (including 70.5 million tons transferred from Shanxi), plus 3 million kilowatts per year.