论文部分内容阅读
1投标报价风险1.1风险管理分析(1)在EPC总承包模式下,业主往往要求承包商按照招标书进行投标报价,但是招标书一般比较简单,例如,国外火电站总承包项目的招标书只是对装机容量、主机、主要附属系统的性能、执行标准、工期做出了要求,而对工程量没有说明,其次对项目所在国现场的具体情况没有具体的说明,所以EPC总承包商在投标阶段要进行大量的工作。
1 tender offer risk 1.1 Risk Management Analysis (1) In the EPC general contracting mode, the owners often require the contractor to submit a tender offer in accordance with the tender, but the tender is generally relatively simple, for example, the general tender of foreign thermal power plant project bidding only Installed capacity, host, the performance of the main ancillary system, the implementation of standards, time requirements, but did not explain the amount of the project, followed by the specific circumstances of the project country where there is no specific description, EPC general contractor in the bidding stage Do a lot of work.