随着3条导流洞全线贯通,小浪底工程施工重点最近已由土石方开挖转向混凝土浇筑。已累计完成土石方工程开挖2336万 m~3,是截流目标计划的90%,其中1月至10月完成年计划的91%。承建大坝工程标的黄河承包商(YRC),精心组织施工,顺利完成黄河右岸坝基开挖和处理工作,提前拉开坝体填筑序幕,目前已完成
With the three diversion channels across the board, Xiaolangdi project construction has recently been focused on the excavation of earth and stone to concrete pouring. It has completed a total of 23.36 million m 3 excavation of earthwork projects, which is 90% of the planned river closure goals, of which 91% of the annual plan is completed from January to October. Construction of Yellow River Contractor (YRC), the subject of dam construction, meticulously organized the construction and successfully completed the excavation and treatment of the dam foundation at the right bank of the Yellow River. The dam prefabricated construction was completed ahead of schedule and has been completed