对常州客运中心预留地铁站房工程中施工缝的施工处理措施进行研究,介绍了所使用的膨胀密封胶和全断面注浆管防水技术。工程完成后发现局部存在渗水现象,对渗水原因进行分析。同时指出对于多雨地区,地面施工环境复杂的项目,以及施工单位缺乏相应施工管理经验的工程,应针对实际工况调整施工方案,设计中也可以考虑采用膨胀密封胶和止水钢板相结合的方法。
The construction measures of construction joints in the subway station building reserved for Changzhou Passenger Transport Center are studied, and the waterproofing technology of the expansion sealant and full-face grouting pipe used is introduced. After the completion of the project found that there is partial water seepage phenomenon, the cause of water seepage analysis. At the same time, it is pointed out that in the rainy area, the project with complex ground construction environment and the construction unit lacking the corresponding construction management experience should adjust the construction plan according to the actual working conditions. In the design, the combination of the expansion sealant and the water stop plate can also be considered .