攀成钢10 m2竖炉大水梁原设计采用常温冷却系统,由于其中的冷却水存在涡流现象,影响冷却效果,导致水梁寿命短,而且余热无法利用。鉴于此,该厂于2011年对大水梁冷却系统进行了改造,采用了汽化冷却和常温冷却并存的双系统结构,并对汽包参数和管网布置进行了优化。改造后,大水梁使用寿命从原来的3~6个月延长到24个月以上,大大提高了竖炉作业率和产量,同时还能回收余热生产蒸汽,实现了节能,年创经济效益500多万元。
Pan-steel 10 m2 shaft furnace Danshun Liang original design using room temperature cooling system, due to the presence of eddy current cooling water, affecting the cooling effect, resulting in short beam life, and the waste heat can not be used. In view of this, the factory in 2011 to transform the large beam cooling system, the use of both evaporative cooling and room temperature cooling coexistence of dual-system structure, and the steam drum parameters and pipe network layout has been optimized. After the transformation, the service life of the large beam has been extended from the original 3 to 6 months to over 24 months, greatly improving the operation rate and output of the shaft furnace, and also recovering the waste heat to produce steam and achieving energy saving and annual economic benefit of 500 More million.