根据郑州机务南段的统计,1983年第一季度,东风3型内燃机车因膨胀水箱出现虚水位所造成的计划外修理128件,因此,带来一系列严重的问题: 1.第一季度垫用蒸汽机车牵引客车79列; 2.更换气缸套175个,其中因穴蚀损坏的130个,占74.29%;因气缸裂损45个,占25.71%。3.停修时间7512.3小时,计313天,平均每天3.5台机车在段修理或待修; 4.此修程工作量大,劳动强度大。
According to the statistics of Zhengzhou South Branch, in the first quarter of 1983, a total of 128 unplanned repairs were caused to the Dongfeng-3 diesel locomotive due to the virtual water level in the expansion tank. As a result, a series of serious problems were caused: 1. The first quarter pad With steam locomotive towing 79 buses; 2. Change cylinder liner 175, of which 130 due to cavitation damage, accounting for 74.29%; 45 due to cylinder crack, accounting for 25.71%. 3. The repair time 7512.3 hours, total 313 days, an average of 3.5 locomotives in the segment repair or repair; 4. The repair work load, labor-intensive.