论文部分内容阅读
摘要:小水电开发建设的特点是:投资规模小,后续运行维护费用低,见效快,对促进地方工业和乡镇企业的发展,有着十分重要的作用。小水电工程的建设管理跟大中型水电工程相比同样具有施工条件复杂多变、专业技术面广等特点。因现行的小水电工程建设监理收费标准偏低,要推行大中型水电工程监理模式是不切实际的。通过对贵州、云南、广西三省多个小型水电站工程建设监理实践,摸索出一套较为适合小水电开发建设的监理模式。
关键词:小水电工程;施工监理;管理体制;
Abstract: the characteristics of the development of the small hydropower development is: investment in small scale, the follow-up operation and maintenance expenses low, quick effect, to promote the local industry and the development of township enterprises, has a very important role. Small hydropower engineering construction management with large and medium-sized hydropower engineering construction conditions than also has complicated, professional technical side wide etc. Characteristics. Because of the small hydropower engineering construction supervision charges low standard, to carry large and medium-sized hydropower project supervision mode is unrealistic. Through to guizhou, yunnan, guangxi provinces more small hydropower project construction supervision practice, found out a set of suit relatively small hydropower development of construction supervision mode.
Keywords: small hydropower engineering; Construction supervision; Management system;
中图分类号:TV文献标识码:A 文章编号:
1.监理工作实践
1.1 监理机构与监理工作方法
1.1.1监理机构(见图1)
根据监理合同的要求和工程特点,在施工现场组建机构简练、高效率专业化的监理机构,是监理工作的关键。监理机构实行总监负责制,下设水工组、水机、金结组和电气组,分别进行安全、质量、进度、投资控制和信息管理。同时为了适应工程建设的全面和全过程监理的要求,必须建立健全监理机构内部管理的各项规章制度,做到监理工作制度化、规范化。
1.1.2监理基本方法
以合同、国家及部颁施工技术规范、审查批准的设计文件、建设部《建设监理试行规定》水利部《水利工程建设监理规定》为依据,根据业主授予的权限、运用监理的职责和技能,通过对施工安全、工程质量、进度和投资控制过程,使工程建设的总目标按时完成。
图1 监理机构
1.2工程安全管理
通过对工程施工各环节的控制,使工程安全生产得到全过程、全天候、全方位的监控,确保工程安全目标“确保不发生较大以上安全事故,争取安全生产事故为零”。的实现。
1.2.1安全生产监督管理原则、内容、方法
(1)安全生产监督管理原则
工程的安全文明施工是工程建设的重要组成部分,本着“安全第一、预防为主、综合治理”的方针,依据《安全生产法》、《建筑工程安全生产管理条例》、国家现行的安全生产的法律、法规,水利、建设行政主管部门的安全生产的规章制度、建设工程强制性标准、设计文件、工程建设合同等规定,通过建立有效的安全管理組织机构体系,对工程施工中各个环节的控制,确保工程安全施工,确保工程建设人员在施工过程中的安全和健康。
(2) 安全生产监督管理内容
工程建设安全生产监理的内容,就是对施工中可能产生安全隐患的各种因素进行控制,概括起来讲就是:
① 控制施工人员的不安全行为。
② 控制物料的不安全状态。
③ 控制施工设备的不安全状态。
④ 控制施工方法、施工工艺的不安全事态。
⑤ 作业环境的安全防护。
(3) 安全生产监督管理方法
对安全生产工作情况,采取日常检查、定期检查、专项检查三种方法。
① 日常检查
1)贯彻执行“安全第一、预防为主、综合治理”的方针,执行国家现行安全生产的法律、法规,建设行政主管部门的安全生产的规章和标准。
2)督促承建单位落实安全生产的组织保证体系,建立、健全安全生产责任制度。
3)督促承建单位对工人进行安全生产教育及分部工程的安全技术交底。
4)审查施工方案及安全技术措施(洞内施工要做好防尘、防噪音措施;加强洞内通风、作业人员要佩戴安全冒和防护面具)。
5)审查并督促承建单位,按照建筑物施工安全技术标准和规范要求,落实分部工程或各工序,关键部位的安全防护措施。
6)督促检查承建单位现场的消防工作、冬季防寒、夏季防暑、文明施工、卫生防疫等项工作。
7)定期组织安全生产大检查和安全生产评比表彰活动。按《建筑施工安全检查评分标准》进行评分。
8)发现违章作业的要责令其停止作业,发现隐患要责令停工整顿。
9)参加对安全事故进行的调查分析、审查承建单位的安全事故报告及安全报表、监督承建单位对安全事故的处理。
10)定期(每月)向业主报告安全生产情况,按规定编制监理工作项目安全统计报表。对重大安全事故的处理及时向安全主管部门和业主报告。
② 定期检查
定期检查为月安全检查。
③ 专项检查
定期检查为月安全检查,在重大节日前,或针对重要危险作业,组织安全专项检查。
1.3合同管理
合同管理工作较繁且责任重大,监理工程师不仅要非常熟悉合同文件,还必须了解本合同的管理特点,掌握工程实际情况,制定以安全生产为基础、工程进度为重点、施工质量作保证、投资效益为目标的合同管理原则。
1.3.1合同管理方案内容
(1)熟悉合同文件,正确解析合同。弄清合同中每项内容,明确参建各方的责、权、利,认真明确履行本工程的职责范围、任务,正确处理好各方的关系。
(2)在工程进行中的细节的文件资料包括:信件、会议纪要、业主的规定、指示、总监的决定、承建方的请示、报告、监理的指令记录信函以及各种报表资料等,有关方一旦发生争执,监理工作以此资料和记录作为协调问题的依据。
(3)考虑问题要灵活,管理工作要做在其他工作前面。审查工程变更申请,提出处理意见,经业主同意后下达工程变更令。
(4)审查承建方提出的索赔申请,进行索赔与反索赔调查,提出索赔处理意见。
(5)审查工程分包,经监理工程师审查同意并经发包人批准后,分包队伍才能进场施工。
(6)制定以文字(文件、通知、信函)代替口头指令及传达的管理方式。进行风险分析,避免投资损失。
(7)调解合同纷争,减少矛盾和纠纷,对合同中的词意表达“含糊”字句及时提出正确的解释。
(8)遇到较大的问题应组织业主和承建方一起协商,尽量求得共识和谅解,避免合同关系对抗。
1.3.2合同管理方法和制度
(1)合同管理方法
通过工程变更、索赔、违约、担保、保险、分包、合同解除、争议解决、清场和撤离等过程管理,实现合同管理的有效性。
(2)合同管理制度
对工程变更、工程延期、费用索赔、工程分包等制定制度。
合同管理制度主要有:工程变更监理实施细则、工程的计量与支付监理实施细则、工程索赔处理监理工作实施细则、工程造价控制监理实施细则等。
1.4质量控制
工程質量是工程建设的核心,是监理工作的重点,本着“百年大计、质量第一”的方针,通过对工序质量实施事前、事中、事后的全过程、全方位跟踪监督和及时解决施工中存在的质量问题,确保监理工作质量控制目标“完建的工程满足设计文件、国家强制性标准和施工合同文件规定的质量要求;在合同工程的整个施工期内不出现质量责任事故”。
1.4.1工程质量控制的依据、标准
(1)工程质量控制的依据
① 工程承建合同文件及其技术条件与技术规范。
② 国家、电力部、水利部、省级行政主管部门颁发的法律与行政法规。
③ 经监理工程师批准并签发的设计图纸与设计技术要求。
④ 国家、电力部、水利部、省级行政主管部门颁发的技术规程、规范、质量检验标准及质量检验办法。
(2)工程质量控制标准
① 工程实施过程中,国家、电力部、水利部、省级行政主管部门颁发新的技术标准替代了原技术标准,从新标准生效之日起,依据新标准执行。
② 当合同文件规定的技术标准低于国家、电力部、水利部颁发的强制性技术标准时,应按国家、电力部、水利部颁发的强制性技术标准执行。
③ 当国家、电力部、水利部颁发的技术标准(包括推荐标准和强制性标准)低于合同文件规定的技术标准时,按合同技术标准执行。
④ 监理工程师依照工程承建合同文件规定,在征得业主批准后,对工程质量控制所执行的合同技术标准与质量检验方法进行补充、修改与调整。
1.4.2 施工前质量控制
工程项目开工前,为了主动有效地控制工程质量,做到工程质量处于监理受控之中,主要做好以下几个方面工作:
(1)实行设计文件的审查、汇审、签发制度,监理工程师做好每张施工图纸的审查,及时发现、纠正施工图纸中存在的图面缺陷和差错。对于施工图纸中与招标图纸和合同技术条件有偏离,组织业主、设计方、承建单位予以汇审、分析、研究和澄清。审查后施工图纸监理工程师签发给承建单位,以便承建单位按照签发施工图纸施工。
(2)实行设计技术交底制度,监理在工程项目开工前,组织设计方进行设计技术交底,使承建单位明确设计意图、技术标准和技术要求。
(3)协助业主进行工程项目划分,划分到每一个单元工程,施工质量控制实行“以单元工程为基础,以工序控制为手段”的程序化管理。
(4)实行开工申请制度,单位工程开工要承建单位报送施工组织设计,分部工程开工报送各单项工程施工措施计划,单元工程开工填报单元工程开工申请(审批)单。监理工程师对报送的资料进行审查,重点审查施工方案、程序、施工工艺及质量安全保证体系,对承建单位报送的施工计划切实可行的方可签发开工许可文件。
(5)对进场的建筑材料实行申报签证制度。
(6)落实质量检测制度,即承建单位按有关规范要求自检,监理机构进行复验,建设单位抽检三项制度。
1.4.3施工中质量控制
在工程施工过程中,监理工程师进行质量控制的方法有巡视检验、旁站监理、平行检测、跟踪检测和现场记录和发布文件等方法。
(1) 巡视检验
巡视检验时监理工程师对所监理的工程项目进行的定期或不定期的检查、监督和管理。通过这种检验方式,监理工程师可以掌握现场施工情况,控制施工现场,是监理工程师所采取的一种经常性、最为普遍的方法。
(2) 旁站监理
监理按照监理合同约定,在施工现场对工程项目的重要部位和关键工序的施工,实施连续性的全过程检查、监督与管理。旁站是监理工程师的一种主要现场检查形式。对容易产生缺陷的部位,以及隐蔽工程,尤其应该加强旁站。
在旁站检查中,监理工程师必须检查承包商在施工中所用的设备、材料及混合料是否与已批准的配比相符,检查是否按技术规范和批准的施工方案、施工工艺进行施工,注意及时发现问题和解决问题,制止错误的施工方法和手段,尽早避免事故的发生。
(3) 平行检测
监理工程师在承建方对试样自行检测的同时,独立抽样进行检测,检验承建方的检测结果。《水利工程施工监理规范》规定:平行检测的检测数量,混凝土试样不少于承建方检测数量的3%,重要部位每种标号的混凝土最少取样1组;土方试样不应少于承包人检测数量的5%;重要部位至少取样3组。
(4) 跟踪检测
在承建方进行试样检测前,监理工程师对其检测人员、仪器设备以及拟订的检测程序和方法进行审核;在承建方对试样进行检测时,实施全过程的监督、确认其程序、方法的有效性以及检测结果的可信性,并对该结果确认。《水利工程施工监理规范》规定:跟踪检测的检测数量,混凝土试样不少于承建方检测数量的7%,土方试样不少于承包人检测数量的10%。
(5) 现场记录和发布文件
监理工程师应认真、完整记录每日施工现场的人员、设备、材料、天气、施工环境以及施工中出现的各种情况作为处理施工过程中合同问题的依据之一,并通过发布通知、指示、批复、签认等文件形式进行施工全过程的控制和管理。
1.4.4施工质量后续控制
工程项目的主体工作已完成,监理工程师的主要工作就是根据工程验收依据:工程承建合同文件、经业主或监理工程师审核签发的设计文件;国家、电力部、水利部颁发的现行设计、施工验收规程、规范;工程质量等级评定标准;质监站批准的工程项目划分,协助业主组织好工程项目的分部工程验收、单位工程验收和完(竣)工验收。
1.5进度控制
在市场经济和投资主体多元化影响下,建设单位非常重视工程项目进度的进展情况,对工期也会提出苛刻的要求。因此,进度控制是监理部门一项艰巨的工作。影响进度的因素很多,如施工条件、水文地质的变化,材料、资金、设计图纸的供应以及承建单位的施工水平等是制约进度的主要因素。我们的工作思路应该是尽量为承建单位创造良好的外部施工环境,同时加强对承建单位施工管理,让他们按进度计划施工。监理部门应按以下程序工作:
(1)总体工程开工前,首先要求承建单位报送总施工进度计划,监理部门审查其逻辑关系、施工程序和资源的均衡投入以及对工程施工质量与合同工期目标的影响。
(2)承建单位根据监理部门批准的进度计划,结合实际工程的进展,按月向监理部门报送当月实施的施工进度报告和下月的施工进度计划。
(3)工程施工进程中,监理工程师应密切注意施工进度进展情况,并且通过计算机项目管理程序进行动态跟踪,如工程出现工期延误的情况,监理部门应及时召开协调会议,查出原因,由于承建单位责任造成的发出赶工令,非承建单位责任造成的,及时与业主协商,尽快解决存在的问题。
1.6 投资控制
投资控制的目的是控制实际投资额不超过计划投资额,使资金和资源得到有效的利用,以提高投资效益;其主要任务是工程计量,工程进度款的审核、索赔处理及价差调整等。
1.6.1 工程计量
计量控制是投资控制的基础,在计量过程中首先必须遵守计量原则(合同文件中有关的计量条款),其次是按照设计图纸完成的施工质量合格的,并在工程量清单中列有的项目才予以计量。同时也要按照监理细则规定好的计量程序进行计量,如在土石方开挖完成后,监理工程师应及时到现场进行土石方开挖测量核准,计量资料完善后方可计量。
1.6.2工程进度款的审核
一般要求承建单位在每个月底(一般规定25日),将当月的施工进度款申请表按监理部的格式要求报送到监理部,监理部按三级进行校审(即监理人员的复核、项目组长的审核和总监的审定),把校审后的施工进度款审核表上报业主。
1.6.3索赔处理
工程索赔是施工中常出现的风险合理分配形式,索赔处理是合同投资控制管理中较为复杂的一个问题,监理工程师和承建合同双方在这个问题上需要花费较多的时间和精力。公正合理地处理好索赔问题必须做好以下几点:
(1)日常监理记录全面细致。
(2)吃透合同文件,尽量在合同文件中找依据,力求准确界定合同双方在索赔问题中的责任,说服双方放弃不合理的要求。
(3)遇到合同无法处理的模糊部分,应通过监理协调,创造良好气氛促使问题友好解决。
1.6.4价格调差
小水电工程建设施工期一般在三年以内,在此期间由于物价波动引起的价格调整应根据合同规定进行补差。目前业主多采用自供主要材料的办法来控制价差,即使由承建单位负责采购,且合同规定给予补差的,很少使用公式法调差,较常用的是工程结算时将工程总消耗的人工,主要材料总量直接与差额相乘求得。在这种情况下,监理工程师一方面做好材料价格资料和有关文件的收集,加一方面要做好人工和主要材料消耗量的核实工作。
1.7 信息及文件管理
1.7.1信息管理
监理信息是很重要的,它直接为工程质量、施工进度、合同支付三项合同目标控制服务,为监理决策服务,同时为合同索赔、工程验收和工程运行服务。要真正让它发挥其服务性,必须做到:
(1)信息采集时要及时、全面、准确、详尽和真实。
(2)坚持每天做监理现场记录和监理日记,并做好信息整理和技术归档工作。
(3)通过定期的监理月报发布工程信息。
1.7.2 文件管理
工程文件是参建各方之间为实現工程项目或达到合同目的相互传递的书面记录,是监理机构的日常重要工作。要做好文件管理,首先把工程文件进行分类,如分成设计、施工、监理文件和业主指标四类,然后分别对其进行管理,完善文件传递、受理、归档等管理制度。
2.认识与体会
经过近些年的摸索和实践,小水电工程建设的监理工作正处在不断完善和提高的过程中,对监理工作的认识和体会如下:
(1)要搞好监理工作的根本是要建立一支专业齐全,有实际工作能力的高素质监理队伍,内部要有一套完整的组织机构和管理制度。
(2)在实行社会监理制的现阶段,要充分发挥监理的作用,必须加强与业主的沟通和联系,使现场的监理工作得到业主的支持、理解和认可。
(3)参建各方要增强合同和法律意识。特别是有些业主的合同观念淡薄,主观意识较强,违反合同的事件时有发生,使得合同管理工作无法正常开展。
(4)要使建设合同真正起到约束、协调的作用,保证参建各方履行各自的职责,要使工程项目的总目标能顺利实现,合同的签订必须规范、详细,应按照国家现行的《水利水电工程施工项目合同和招标文件示范文本》拟签合同。
(5)目前投资失控的主要原因是设计变更引起的,要使投资得到有效控制,设计部门应按照设计规范要求进行设计,前期的现场勘查设计工作要做得全面扎实,尽量减少技施阶段的设计变更。
(6)为便于施工期的合同管理,监理工程师应介入工程招标工作,参与招标文件有关条款的拟定。
(7)监理工程师在施工现场履行职责时要树立良好的形象、必须坚持以“数据说话”的原则,以理服人。
(8)在工程项目实施过程中,监理工程师要有预控能力,及时识别和防范当前或潜在的质量和安全隐患。
(9)要使工程项目的总目标能顺利实现,选择承建单位是一个关键因数,除了正常招投标外,对承建单位的实际情况要进行全面了解。
(10)要使工程项目的总目标能顺利实现,业主的建设资金必须到位,业主必须按合同的约定支付监理费,支付承建单位工程进度款项和其它合理的费用。
(11)要使工程项目的总目标能顺利实现,业主必须按合同的约定,要求设计方提供供图计划,严格按照供图计划提供施工用图。
注:文章内所有公式及图表请以PDF形式查看。
关键词:小水电工程;施工监理;管理体制;
Abstract: the characteristics of the development of the small hydropower development is: investment in small scale, the follow-up operation and maintenance expenses low, quick effect, to promote the local industry and the development of township enterprises, has a very important role. Small hydropower engineering construction management with large and medium-sized hydropower engineering construction conditions than also has complicated, professional technical side wide etc. Characteristics. Because of the small hydropower engineering construction supervision charges low standard, to carry large and medium-sized hydropower project supervision mode is unrealistic. Through to guizhou, yunnan, guangxi provinces more small hydropower project construction supervision practice, found out a set of suit relatively small hydropower development of construction supervision mode.
Keywords: small hydropower engineering; Construction supervision; Management system;
中图分类号:TV文献标识码:A 文章编号:
1.监理工作实践
1.1 监理机构与监理工作方法
1.1.1监理机构(见图1)
根据监理合同的要求和工程特点,在施工现场组建机构简练、高效率专业化的监理机构,是监理工作的关键。监理机构实行总监负责制,下设水工组、水机、金结组和电气组,分别进行安全、质量、进度、投资控制和信息管理。同时为了适应工程建设的全面和全过程监理的要求,必须建立健全监理机构内部管理的各项规章制度,做到监理工作制度化、规范化。
1.1.2监理基本方法
以合同、国家及部颁施工技术规范、审查批准的设计文件、建设部《建设监理试行规定》水利部《水利工程建设监理规定》为依据,根据业主授予的权限、运用监理的职责和技能,通过对施工安全、工程质量、进度和投资控制过程,使工程建设的总目标按时完成。
图1 监理机构
1.2工程安全管理
通过对工程施工各环节的控制,使工程安全生产得到全过程、全天候、全方位的监控,确保工程安全目标“确保不发生较大以上安全事故,争取安全生产事故为零”。的实现。
1.2.1安全生产监督管理原则、内容、方法
(1)安全生产监督管理原则
工程的安全文明施工是工程建设的重要组成部分,本着“安全第一、预防为主、综合治理”的方针,依据《安全生产法》、《建筑工程安全生产管理条例》、国家现行的安全生产的法律、法规,水利、建设行政主管部门的安全生产的规章制度、建设工程强制性标准、设计文件、工程建设合同等规定,通过建立有效的安全管理組织机构体系,对工程施工中各个环节的控制,确保工程安全施工,确保工程建设人员在施工过程中的安全和健康。
(2) 安全生产监督管理内容
工程建设安全生产监理的内容,就是对施工中可能产生安全隐患的各种因素进行控制,概括起来讲就是:
① 控制施工人员的不安全行为。
② 控制物料的不安全状态。
③ 控制施工设备的不安全状态。
④ 控制施工方法、施工工艺的不安全事态。
⑤ 作业环境的安全防护。
(3) 安全生产监督管理方法
对安全生产工作情况,采取日常检查、定期检查、专项检查三种方法。
① 日常检查
1)贯彻执行“安全第一、预防为主、综合治理”的方针,执行国家现行安全生产的法律、法规,建设行政主管部门的安全生产的规章和标准。
2)督促承建单位落实安全生产的组织保证体系,建立、健全安全生产责任制度。
3)督促承建单位对工人进行安全生产教育及分部工程的安全技术交底。
4)审查施工方案及安全技术措施(洞内施工要做好防尘、防噪音措施;加强洞内通风、作业人员要佩戴安全冒和防护面具)。
5)审查并督促承建单位,按照建筑物施工安全技术标准和规范要求,落实分部工程或各工序,关键部位的安全防护措施。
6)督促检查承建单位现场的消防工作、冬季防寒、夏季防暑、文明施工、卫生防疫等项工作。
7)定期组织安全生产大检查和安全生产评比表彰活动。按《建筑施工安全检查评分标准》进行评分。
8)发现违章作业的要责令其停止作业,发现隐患要责令停工整顿。
9)参加对安全事故进行的调查分析、审查承建单位的安全事故报告及安全报表、监督承建单位对安全事故的处理。
10)定期(每月)向业主报告安全生产情况,按规定编制监理工作项目安全统计报表。对重大安全事故的处理及时向安全主管部门和业主报告。
② 定期检查
定期检查为月安全检查。
③ 专项检查
定期检查为月安全检查,在重大节日前,或针对重要危险作业,组织安全专项检查。
1.3合同管理
合同管理工作较繁且责任重大,监理工程师不仅要非常熟悉合同文件,还必须了解本合同的管理特点,掌握工程实际情况,制定以安全生产为基础、工程进度为重点、施工质量作保证、投资效益为目标的合同管理原则。
1.3.1合同管理方案内容
(1)熟悉合同文件,正确解析合同。弄清合同中每项内容,明确参建各方的责、权、利,认真明确履行本工程的职责范围、任务,正确处理好各方的关系。
(2)在工程进行中的细节的文件资料包括:信件、会议纪要、业主的规定、指示、总监的决定、承建方的请示、报告、监理的指令记录信函以及各种报表资料等,有关方一旦发生争执,监理工作以此资料和记录作为协调问题的依据。
(3)考虑问题要灵活,管理工作要做在其他工作前面。审查工程变更申请,提出处理意见,经业主同意后下达工程变更令。
(4)审查承建方提出的索赔申请,进行索赔与反索赔调查,提出索赔处理意见。
(5)审查工程分包,经监理工程师审查同意并经发包人批准后,分包队伍才能进场施工。
(6)制定以文字(文件、通知、信函)代替口头指令及传达的管理方式。进行风险分析,避免投资损失。
(7)调解合同纷争,减少矛盾和纠纷,对合同中的词意表达“含糊”字句及时提出正确的解释。
(8)遇到较大的问题应组织业主和承建方一起协商,尽量求得共识和谅解,避免合同关系对抗。
1.3.2合同管理方法和制度
(1)合同管理方法
通过工程变更、索赔、违约、担保、保险、分包、合同解除、争议解决、清场和撤离等过程管理,实现合同管理的有效性。
(2)合同管理制度
对工程变更、工程延期、费用索赔、工程分包等制定制度。
合同管理制度主要有:工程变更监理实施细则、工程的计量与支付监理实施细则、工程索赔处理监理工作实施细则、工程造价控制监理实施细则等。
1.4质量控制
工程質量是工程建设的核心,是监理工作的重点,本着“百年大计、质量第一”的方针,通过对工序质量实施事前、事中、事后的全过程、全方位跟踪监督和及时解决施工中存在的质量问题,确保监理工作质量控制目标“完建的工程满足设计文件、国家强制性标准和施工合同文件规定的质量要求;在合同工程的整个施工期内不出现质量责任事故”。
1.4.1工程质量控制的依据、标准
(1)工程质量控制的依据
① 工程承建合同文件及其技术条件与技术规范。
② 国家、电力部、水利部、省级行政主管部门颁发的法律与行政法规。
③ 经监理工程师批准并签发的设计图纸与设计技术要求。
④ 国家、电力部、水利部、省级行政主管部门颁发的技术规程、规范、质量检验标准及质量检验办法。
(2)工程质量控制标准
① 工程实施过程中,国家、电力部、水利部、省级行政主管部门颁发新的技术标准替代了原技术标准,从新标准生效之日起,依据新标准执行。
② 当合同文件规定的技术标准低于国家、电力部、水利部颁发的强制性技术标准时,应按国家、电力部、水利部颁发的强制性技术标准执行。
③ 当国家、电力部、水利部颁发的技术标准(包括推荐标准和强制性标准)低于合同文件规定的技术标准时,按合同技术标准执行。
④ 监理工程师依照工程承建合同文件规定,在征得业主批准后,对工程质量控制所执行的合同技术标准与质量检验方法进行补充、修改与调整。
1.4.2 施工前质量控制
工程项目开工前,为了主动有效地控制工程质量,做到工程质量处于监理受控之中,主要做好以下几个方面工作:
(1)实行设计文件的审查、汇审、签发制度,监理工程师做好每张施工图纸的审查,及时发现、纠正施工图纸中存在的图面缺陷和差错。对于施工图纸中与招标图纸和合同技术条件有偏离,组织业主、设计方、承建单位予以汇审、分析、研究和澄清。审查后施工图纸监理工程师签发给承建单位,以便承建单位按照签发施工图纸施工。
(2)实行设计技术交底制度,监理在工程项目开工前,组织设计方进行设计技术交底,使承建单位明确设计意图、技术标准和技术要求。
(3)协助业主进行工程项目划分,划分到每一个单元工程,施工质量控制实行“以单元工程为基础,以工序控制为手段”的程序化管理。
(4)实行开工申请制度,单位工程开工要承建单位报送施工组织设计,分部工程开工报送各单项工程施工措施计划,单元工程开工填报单元工程开工申请(审批)单。监理工程师对报送的资料进行审查,重点审查施工方案、程序、施工工艺及质量安全保证体系,对承建单位报送的施工计划切实可行的方可签发开工许可文件。
(5)对进场的建筑材料实行申报签证制度。
(6)落实质量检测制度,即承建单位按有关规范要求自检,监理机构进行复验,建设单位抽检三项制度。
1.4.3施工中质量控制
在工程施工过程中,监理工程师进行质量控制的方法有巡视检验、旁站监理、平行检测、跟踪检测和现场记录和发布文件等方法。
(1) 巡视检验
巡视检验时监理工程师对所监理的工程项目进行的定期或不定期的检查、监督和管理。通过这种检验方式,监理工程师可以掌握现场施工情况,控制施工现场,是监理工程师所采取的一种经常性、最为普遍的方法。
(2) 旁站监理
监理按照监理合同约定,在施工现场对工程项目的重要部位和关键工序的施工,实施连续性的全过程检查、监督与管理。旁站是监理工程师的一种主要现场检查形式。对容易产生缺陷的部位,以及隐蔽工程,尤其应该加强旁站。
在旁站检查中,监理工程师必须检查承包商在施工中所用的设备、材料及混合料是否与已批准的配比相符,检查是否按技术规范和批准的施工方案、施工工艺进行施工,注意及时发现问题和解决问题,制止错误的施工方法和手段,尽早避免事故的发生。
(3) 平行检测
监理工程师在承建方对试样自行检测的同时,独立抽样进行检测,检验承建方的检测结果。《水利工程施工监理规范》规定:平行检测的检测数量,混凝土试样不少于承建方检测数量的3%,重要部位每种标号的混凝土最少取样1组;土方试样不应少于承包人检测数量的5%;重要部位至少取样3组。
(4) 跟踪检测
在承建方进行试样检测前,监理工程师对其检测人员、仪器设备以及拟订的检测程序和方法进行审核;在承建方对试样进行检测时,实施全过程的监督、确认其程序、方法的有效性以及检测结果的可信性,并对该结果确认。《水利工程施工监理规范》规定:跟踪检测的检测数量,混凝土试样不少于承建方检测数量的7%,土方试样不少于承包人检测数量的10%。
(5) 现场记录和发布文件
监理工程师应认真、完整记录每日施工现场的人员、设备、材料、天气、施工环境以及施工中出现的各种情况作为处理施工过程中合同问题的依据之一,并通过发布通知、指示、批复、签认等文件形式进行施工全过程的控制和管理。
1.4.4施工质量后续控制
工程项目的主体工作已完成,监理工程师的主要工作就是根据工程验收依据:工程承建合同文件、经业主或监理工程师审核签发的设计文件;国家、电力部、水利部颁发的现行设计、施工验收规程、规范;工程质量等级评定标准;质监站批准的工程项目划分,协助业主组织好工程项目的分部工程验收、单位工程验收和完(竣)工验收。
1.5进度控制
在市场经济和投资主体多元化影响下,建设单位非常重视工程项目进度的进展情况,对工期也会提出苛刻的要求。因此,进度控制是监理部门一项艰巨的工作。影响进度的因素很多,如施工条件、水文地质的变化,材料、资金、设计图纸的供应以及承建单位的施工水平等是制约进度的主要因素。我们的工作思路应该是尽量为承建单位创造良好的外部施工环境,同时加强对承建单位施工管理,让他们按进度计划施工。监理部门应按以下程序工作:
(1)总体工程开工前,首先要求承建单位报送总施工进度计划,监理部门审查其逻辑关系、施工程序和资源的均衡投入以及对工程施工质量与合同工期目标的影响。
(2)承建单位根据监理部门批准的进度计划,结合实际工程的进展,按月向监理部门报送当月实施的施工进度报告和下月的施工进度计划。
(3)工程施工进程中,监理工程师应密切注意施工进度进展情况,并且通过计算机项目管理程序进行动态跟踪,如工程出现工期延误的情况,监理部门应及时召开协调会议,查出原因,由于承建单位责任造成的发出赶工令,非承建单位责任造成的,及时与业主协商,尽快解决存在的问题。
1.6 投资控制
投资控制的目的是控制实际投资额不超过计划投资额,使资金和资源得到有效的利用,以提高投资效益;其主要任务是工程计量,工程进度款的审核、索赔处理及价差调整等。
1.6.1 工程计量
计量控制是投资控制的基础,在计量过程中首先必须遵守计量原则(合同文件中有关的计量条款),其次是按照设计图纸完成的施工质量合格的,并在工程量清单中列有的项目才予以计量。同时也要按照监理细则规定好的计量程序进行计量,如在土石方开挖完成后,监理工程师应及时到现场进行土石方开挖测量核准,计量资料完善后方可计量。
1.6.2工程进度款的审核
一般要求承建单位在每个月底(一般规定25日),将当月的施工进度款申请表按监理部的格式要求报送到监理部,监理部按三级进行校审(即监理人员的复核、项目组长的审核和总监的审定),把校审后的施工进度款审核表上报业主。
1.6.3索赔处理
工程索赔是施工中常出现的风险合理分配形式,索赔处理是合同投资控制管理中较为复杂的一个问题,监理工程师和承建合同双方在这个问题上需要花费较多的时间和精力。公正合理地处理好索赔问题必须做好以下几点:
(1)日常监理记录全面细致。
(2)吃透合同文件,尽量在合同文件中找依据,力求准确界定合同双方在索赔问题中的责任,说服双方放弃不合理的要求。
(3)遇到合同无法处理的模糊部分,应通过监理协调,创造良好气氛促使问题友好解决。
1.6.4价格调差
小水电工程建设施工期一般在三年以内,在此期间由于物价波动引起的价格调整应根据合同规定进行补差。目前业主多采用自供主要材料的办法来控制价差,即使由承建单位负责采购,且合同规定给予补差的,很少使用公式法调差,较常用的是工程结算时将工程总消耗的人工,主要材料总量直接与差额相乘求得。在这种情况下,监理工程师一方面做好材料价格资料和有关文件的收集,加一方面要做好人工和主要材料消耗量的核实工作。
1.7 信息及文件管理
1.7.1信息管理
监理信息是很重要的,它直接为工程质量、施工进度、合同支付三项合同目标控制服务,为监理决策服务,同时为合同索赔、工程验收和工程运行服务。要真正让它发挥其服务性,必须做到:
(1)信息采集时要及时、全面、准确、详尽和真实。
(2)坚持每天做监理现场记录和监理日记,并做好信息整理和技术归档工作。
(3)通过定期的监理月报发布工程信息。
1.7.2 文件管理
工程文件是参建各方之间为实現工程项目或达到合同目的相互传递的书面记录,是监理机构的日常重要工作。要做好文件管理,首先把工程文件进行分类,如分成设计、施工、监理文件和业主指标四类,然后分别对其进行管理,完善文件传递、受理、归档等管理制度。
2.认识与体会
经过近些年的摸索和实践,小水电工程建设的监理工作正处在不断完善和提高的过程中,对监理工作的认识和体会如下:
(1)要搞好监理工作的根本是要建立一支专业齐全,有实际工作能力的高素质监理队伍,内部要有一套完整的组织机构和管理制度。
(2)在实行社会监理制的现阶段,要充分发挥监理的作用,必须加强与业主的沟通和联系,使现场的监理工作得到业主的支持、理解和认可。
(3)参建各方要增强合同和法律意识。特别是有些业主的合同观念淡薄,主观意识较强,违反合同的事件时有发生,使得合同管理工作无法正常开展。
(4)要使建设合同真正起到约束、协调的作用,保证参建各方履行各自的职责,要使工程项目的总目标能顺利实现,合同的签订必须规范、详细,应按照国家现行的《水利水电工程施工项目合同和招标文件示范文本》拟签合同。
(5)目前投资失控的主要原因是设计变更引起的,要使投资得到有效控制,设计部门应按照设计规范要求进行设计,前期的现场勘查设计工作要做得全面扎实,尽量减少技施阶段的设计变更。
(6)为便于施工期的合同管理,监理工程师应介入工程招标工作,参与招标文件有关条款的拟定。
(7)监理工程师在施工现场履行职责时要树立良好的形象、必须坚持以“数据说话”的原则,以理服人。
(8)在工程项目实施过程中,监理工程师要有预控能力,及时识别和防范当前或潜在的质量和安全隐患。
(9)要使工程项目的总目标能顺利实现,选择承建单位是一个关键因数,除了正常招投标外,对承建单位的实际情况要进行全面了解。
(10)要使工程项目的总目标能顺利实现,业主的建设资金必须到位,业主必须按合同的约定支付监理费,支付承建单位工程进度款项和其它合理的费用。
(11)要使工程项目的总目标能顺利实现,业主必须按合同的约定,要求设计方提供供图计划,严格按照供图计划提供施工用图。
注:文章内所有公式及图表请以PDF形式查看。