论文部分内容阅读
1提前截流方案提出缘由燕山水库工程原初步设计总工期为57个月,在工程开工第3年,即2007年汛后截流,2008年底前基本完成主体:翻呈建设。根据水利部、淮委对治淮工程2007年完成的总体要求和河南省委省政府提出的提前在2007年基本完成燕山水库主体工程施工的建设目标,河南省水利勘测设计研究院根据业主要
1 Premature Closure Proposed Causes Yanshan Reservoir original preliminary design of the total construction period of 57 months in the project started the third year, that is, after the closure of the flood in 2007, the main body completed by the end of 2008: construction turned over. According to the overall requirements of the Ministry of Water Resources and Huai River for the completion of the Huaihe River Project in 2007 and the construction target put forward by the Henan Provincial Party Committee and Government in advance to complete the construction of the main Yanshan Reservoir project in 2007, Henan Provincial Institute of Hydraulic Design and Research,