登封市朝阳沟水库除险加固工程的坝体和坝基防渗均采用塑性混凝土防渗墙,结合该工程,文章主要介绍了塑性混凝土防渗墙的施工方法、质量控制、特殊情况处理等。防渗墙的实施大大提高了朝阳沟水库的防渗能力,保证了水库运行安全,减轻了防洪压力,保障了水库周边地区人民群众生命财产安全。目前大冶镇以朝阳沟水库为依托,建设了朝阳沟森林公园、朝阳沟集中供水厂,对当地社会经济发展起到了较大推动作用。
In combination with the project, the construction methods, quality control and special handling of plastic concrete cutoff walls are mainly introduced in the dam body and dam foundation seepage prevention works of Chaoyanggou Reservoir in Dengfeng City. The implementation of cutoff wall greatly enhances the anti-seepage capability of Chaoyanggou Reservoir, ensures the safe operation of reservoirs, lightens the flood control pressure and ensures the safety of people’s lives and property in the area around the reservoir. Currently Daye Town to Chaoyanggou reservoir as the basis, the construction of Chaoyanggou Forest Park, Chaoyanggou centralized water supply plant on the local social and economic development has played a greater role in promoting.