摘 要:过去工程造价控制的重点一直在项目的实施阶段,而实践证明工程建设的不同阶段对投资的影响程度有很大的差异。据统计,投资决策和初步设计阶段对投资的影响程度最大,其次为技术设计阶段对投资的影响,而过去所著重的施工阶段对投资的影响只有10%左右。
关键词:投资决策阶段设计阶段投资控制改进意见
中图分类号:TU723.3 文献标识码:A文章编号:
Abstract: The key of engineering cost control in the past has been in the implementation stage of the project, and proved the different phases of the project construction of the influence degree of the investment there is a big difference. According to the statistics, the investment decision-making and preliminary design stage to the influence degree of the biggest investment, followed by technology design stages of investment, while the effect of the past with heavy construction stage to the influence of the investment only about 10%.
Key Words: investment decision stage; design stage; investment control; improvements
一个建设项目,往往需要数百万、上千万、甚至上亿元的资金。项目建成以后能否盈利,能否达到预期效果,这是每个业主非常关心的问题。这就要求工程造价管理人员对项目从立项、可行性研究、初步设计、施工图设计直至竣工验收进行全过程跟踪,使项目投资控制贯穿于项目建设全过程投资决策、项目设计、招标、施工及竣工决算审计等五个阶段。投资决策阶段即可行性研究阶段,包括投资估算、策划;建设项目设计阶段包括方案估算、概算、施工图预算;招标阶段包括标书、标底编制、评标、定标;施工阶段包括中期进度款审核、跟踪动态控制等。
过去工程造价控制的重点一直在项目的实施阶段,而实践证明工程建设的不同阶段对投资的影响程度有很大的差异。据统计,投资决策和初步设计阶段对投资的影响程度最大,其次为技术设计阶段对投资的影响,而过去所著重的施工阶段对投资的影响只有10%左右。由此可见,工程建设的决策阶段和设计阶段是决定工程造价的关键阶段,工艺、流程、方案一经确定,工程造价基本上确定了。
1项目投资决策阶段的投资控制
1.1项目投资决策阶段目前存在的问题
目前在项目建议书阶段,通常由建设单位向公司投资计划部提出投资估算,内容相当简单往往造成漏项。在可行性研究阶段,建设单位委托设计单位、勘察设计单位编制可行性研究报告,并编制投资估算,该投资估算经审批后将作为此项目工程造价的最高限额。但由于本阶段以经济分析和方案为主,工程量不明确,所以设计院本阶段的投资估算,准确性较差,同时由于建设单位通常不是投资估算和造价控制的内行,而且对工艺流程和方案缺乏认真研究;有时建设单位为了所报项目能被批准,要求设计单位在投资估算时有意低估,搞“钓鱼工程”,增加了估算的不准确性。
1.2投资决策阶段的工程造价控制
1.2.1在投资决策阶段做好基础资料的收集,保证详实、准确
要做好项目的投资预测,需要很多资料,如工程所在地的水电路状况、地质情况、主要材料设备的价格资料、大宗材料的采购地以及现有已建类似工程资料,对于做经济评价的项目还要收集更多资料。造价人员要对资料的准确性、可靠性认真分析,保证投资预测、经济分析的准确。
1.2.2認真做好市场研究,是论证项目建设必要性的关键
市场研究就是指对拟建项目所提供的产品或服务的市场占有可能性分析。包括国内外市场在项目计算期内对拟建产品的需求状况;类似项目的建设情况;国家对该产业的政策和今后发展趋势等。要做好市场研究,技术经济人员就需要掌握大量的统计数据和信息资料,并进行综合分析和处理,项目建设的必要性。
1.2.3做好方案优化是控制工程造价的关键
据国外统计资料表明,在项目前期方案优化过程中节约投资的可能性为80%左右,所以,要真正有效地控制工程造价,就应该把工作重点放在前期工作上,在完成市场研究以后,结合项目的实际情况,在满足生产的前提下,遵循"效益至上"的原则,进行多方案比选。这就要求设计人员必须牢固树立经济意识,克服重技术,轻经济,设计保守浪费的倾向,明确今天的投资就是企业明天的成本,技术经济人员应有专业知识,了解设计意图,熟悉工艺技术方案,和设计人员密切配合,用动态分析方法进行多方案技术经济比较,要在降低工程造价上下功夫。通过方案优化,使工艺流程尽量简单,设备选型更加合理,从而节约大量资金。
1.2.4合理确定评价价格和基准参数是做好经济效益的基础
财务评价是在国家现行财税制度和价格体系下,计算项目范围内的效益和费用,分析项目的盈利能力、清偿能力,以考察项目在财务上的可行性。在财务评价中,评价价格的选用是项目经济评价的关键,直接影响评价的质量。目前在经济评价报告中,产品销售价格按市场价格计算,不考虑计算期内价格相对变动,这样,若产品销售价格逐年下降,那么就夸大了项目的效益,如果产品的价格是逐年上升的,就缩小了项目的效益。显然,经济评价仅用当时的市场价格来编制是不够的,这就要求评价人员针对不同项目的特点,结合市场分析、竞争力分析、不确定性分析等因素选取多种价格方案并加以分析,以使投资者对项目未来的效益有充分的了解和减少项目投资风险。
强化项目前期工作,规范项目投资决策,是提高投资运行质量的基础,在项目取舍上实行效益否决制,没有经济效益或经济效益差的项目,不安排建设,列入建设计划的项目,必须做可行性研究,可行性研究必须有经济效益评价,没有经济效益评价的可行性研究报告或方案不予评审,达不到经济效益标准的项目不予立项,突出项目前期工作的超前性。通过投资科学管理,提高投资经济运行质量,以保证公司全局经济效益的提高。
2项目设计阶段
2.1项目设计阶段目前存在的问题
当前推行限额设计尚有一定难度。一方面,长期以来人们只注重技术创新,设计人员在控制工程造价上的创新却很少得到表彰和奖励,反而要承担更多的风险,这样势必挫伤设计人员主动控制工程造价的积极性。另一方面,现行设计费收费偏低和计算方法不利于开展限额设计。实行限额设计,设计单位和设计人员势必付出更多的劳动和时间,低费率的设计收费与其所付出的劳动并不匹配;设计收费按工程投资额及相应费率计算更是与实行限额设计相矛盾。经济利益会驱使设计单位和设计人员提高工程造价,而不会主动控制和降低工程造价,设计单位只注意设计产值的完成量,而忽略设计产品的经济性。鉴于此,以行政和经济手段促使设计人员主动实行限额设计,控制工程造价是今后必然趋势。
2.1.1技术和经济的结合不够
长期以来,在工程建设领域,工程设计和投资控制工作联系不够紧密是一种普遍现象。一提到设计,大家必然想到那是设计人员的责任;一提到造价控制,想当然的是造价人员的职责。在实际工作中,一般都是设计人员根据设计委托进行现场调查,选择方案,进行设计,不同阶段向造价人员提供条件,进行估价或预算。造价人员对工程概况、现场情况了解很少,无法将各种影响因素考虑全面。所以工作中既要克服片面强调节约、忽视技术,又要反对重技术、轻经济、设计保守浪费的现象。所以造价人员应该及时对项目投资进行分析比较,反馈造价信息,能动地指导设计,使设计方案在满足生产要求的前提下,节约投资。
2.1.2设计中成本控制认识不足,影响竞争能力
设计人员在设计中一般都比较注重设计产品安全实用,技术先进,强调设计的产值,而对设计产品的经济性不够重视,不抓设计中的经济指标和成本控制工作。另外,现行的设计收费标准是以工程造价为取费基数,对设计中造成的浪费缺乏明确标准和控制措施,不带任何经济责任,具有较明显的计划经济色彩。2001年国家建设部对设计费重新调整,但随着与国际接轨,工程设计收费方法将引入限额按比例提成的机制,使得设计单位增强为业主控制投资成本的意识。
2.1.3造价控制环节脱节
目前基本建设项目投资管理部门都采取分段式的管理方法,与之相适应的估算、概算、预算和结算也是分段编制的。设计单位一般负责初步设计概算和施工图预算,但结算一般都不参与,造成投资控制的脱节。现在新材料、新设备不断更新,价格不断变化,定额调整滞后,对工程造价的约束力降低,预算和结算差距不断增大,如果设计单位没有机会了解实际发生的工程成本,做不到评价前阶段造价控制质量如何,缺乏信息反馈,无法进行事后分析,积累经验,在以后的工作中遇到同样的问题也就不能有所突破,不能进一步提高造价工作的质量。
2.2项目设计阶段的工程造价控制
2.2.1设计阶段没有引起足够重视,造成失误和浪费
设计阶段包括初步设计和施工图设计两个阶段,设计阶段应是全过程造价控制的重点。据相关统计,初步设计影响造价可能性75%~95%,技术阶段设计为35%~75%,设计费用一般只相当于建设工程全过程费用的1%以下,而这小于1%的费用对工程造价的影响程度占75%以上。然而,长期以来,建设单位普遍忽视设计阶段的造价控制,给予设计过程的时间紧迫,给予设计需要建设单位提供的资料不够完善和准确,而把管理的主要精力放在工程的实施阶段,在审核施工图预算、工程造价款结算上算细帐。这样做,尽管有一定的效果,但毕竟是“亡羊补牢”,事倍功半。
(1)违反基本建设程序和经济规律。基本建设程序是基本建设活动的客观规律。随着市场投资主体的多元化,许多业主为使项目尽快上马,不按基本建设程序和经济规律办事,任意简化和减少基本建设的程序和环节,压缩设计时间,不做项目可行性研究和初步设计,或项目可行性研究和初步设计与施工图设计一起做,甚至直接从施工图设计做起,边设计,边施工,造成投资决策失误,设计深度不深、设计质量低劣、设计更改频繁,致使工程造价无法得到控制。这些违反基本建设程序和经济规律的建设项目明显存在先天不足,使得以后阶段的工程造价很难得到控制。例如2007年的老爷庙联合站建设工程,在可研没有批复的情况下就开始了原油储罐区的设计和施工,设计时间紧迫,为满足施工要求,要求设计单位边设计边施工,设计单位只能采用临时白图作为现场施工依据。在施工图设计的同时,本工程正在进行可研的审查。当可研批复时,油田产能数据超出可研规模,在此基础上进行初步设计,此可研不能完全作为初步设计的依据,同时,各类设备已开始招标,中标厂家在规定时间内不能提供尺寸全面的图纸,设计单位根据主要尺寸进行基础设计并提供施工草图,常常造成没有设备正规图纸就将设备基础草图送到施工现场,施工单位不等设备到位进行基础核实就开始施工,造成大部分到货设备尺寸和提供的基础尺寸不吻合,使工程施工过程中现场存在很多调整。造成该工程共发生设计变更和现场签证2760多万元,增加投资占总建设投资的4.6%。
(2)重技术轻经济,技术与经济相脱节。在项目可行性研究和初步设计阶段,往往只注重对技术方案的论证,对经济因素考虑的较少,缺乏多方案比较和技术经济分析,造成工程投资的极大浪费。在施工图设计阶段,设计人员缺乏经济观念,设计只管技术,不管经济,甚至追求新、奇、异,造成投资失控。
2.2.2切实推行限额设计,推广标准设计
限额设计是以项目可行性研究报告的批复所确定的建设规模、建设内容、建设标准为依据,在投资估算限额范围内进行工程设计,以提高投资的经济效益。另外,从业主的角度讲,业主的资金是有限的,他的目的是通过项目建设实现经济效益,设计的任务就是利用业主的有限资金,合理确定工程标准、规模,确保项目的實施完成,保护业主的经济利益。从这个意义上讲限额设计更是业主所关心的。
设计过程中要积极推行限额设计,按照设计程序分阶段层层控制总投资,使其贯穿于可行性研究、初步设计、技术设计直到施工图设计的各个阶段,形成纵向控制;各设计阶段,按各专业进行投资分解,分块限额,具体分配到单元和专业,形成横向控制和纵向控制相结合。但提倡限额设计并不是单纯的追求降低造价,应该坚持科学,采用优化设计使技术和经济紧密结合,通过技术比较,经济分析和效果评价,力求以最少的投入,创造最大的效益。
做好限额设计,对造价人员提出了更高的要求。技术经济人员要对概算严格控制。实现了对投资限额的控制,也就同时实现了设计规模、设计标准、工程数量等各方面的控制。
标准设计是根据共同的条件按照通用的原则编制的,是经过一定程序批准的,可供设计单位重复使用,既优质又经济。标准设计能较好地贯彻执行国家的技术经济政策,合理利用能源、资源、材料和设备,并能够缩短设计周期,加快施工进度。因此,采用标准设计一般都能使工程造价低于非标设计的工程造价。
概算超估算、预算超概算、决算超预算,造成这种"三超"现象的主要原因之一就是没有实行限额设计。限额设计是控制工程造价的重要手段。由上述含义可知,限额设计是按上一阶段批准的投资(或造价)控制下一阶段的设计,而且在设计中以控制工程量为主要内容,抓住控制工程造价的核心,从而达到克服"三超"的目的。
加强设计变更管理也是限额设计的一个重要内容。在工程各实施阶段,设计变更更应尽量提前,变更发生得越早,损失越小,反之就越大。如在设计阶段变更,则只需修改图纸,其他费用尚未发生,损失有限;如在采购阶段变更,不仅仅需要修改图纸,而且设备、材料还须重新采购;若在施工阶段变更,除以上费用外,已施工的工程可能要拆除,势必造成重大变更损失。为此,必须加强设计变更管理,尽可能把设计变更控制在设计阶段初期,尤其对影响工程造价的重大设计变更,使工程造价得到有效控制。
现在我国的造价控制管理还是静态滞后的,不利于动态的控制投资,这就要求造价管理人员规范、系统地做好造价资料的积累,以适应造价工作新的要求,作为造价人员,个人专业素质,知识结构,技能水平非常重要,在拥有良好的职业道德同时,本着为业主负责的精神,必须加强专业知识学习和技能熟练操作,掌握计价规范和各地区相关概预算定额,不断积累工程经验,才能把握自身主动权,最大限度地减少失误。在方案阶段甚至可行性研究阶段密切配合设计人员,主动沟通、交流,做好事前控制,方能未雨绸缪,特别基本建设可研,是基本建设前期的重要内容,也是基本建设程序办事的重要阶段,其目的就是使建设项目决策正确,避免或减少决策失误而造成浪费,投资估算将对初步设计概算起控制作用,认真熟悉设计文件,了解设计意图,广泛收集市场信息及时分析研究,明确工程造价控制目标,使成本分析建立在真实、准确地基础上。只有对工程项目的全面了解,定额熟悉、计价熟练程度高,加大计算机应用技术力度,严把质量关,才能编制出水平高,质量好,速度高,让业主满意的精品来,确保编制阶段能较好的反映出工程实际造价,避免事倍功半,为项目决策提供科学的依据,提高企业竞争能力。
总之,工程造价投资控制涉及到工程建设的诸多方面,它与工程建设的全过程中每个环节紧密相连,控制工程造价不仅是领导者和工程技术人员的职责,而且是每一位工程建设参与者份内之事。提高造价人员的素质,提高技术经济分析论证能力,提高设计产品的经济性能,增强企业市场竞争力,为企业的长远发展奠定基础。
参考文献:冯俊杰、王兆军、张总翎,浅议项目管理知识在设计阶段应用
徐大图建设项目投资控制
肖笃姓工程经济投资分析
关键词:投资决策阶段设计阶段投资控制改进意见
中图分类号:TU723.3 文献标识码:A文章编号:
Abstract: The key of engineering cost control in the past has been in the implementation stage of the project, and proved the different phases of the project construction of the influence degree of the investment there is a big difference. According to the statistics, the investment decision-making and preliminary design stage to the influence degree of the biggest investment, followed by technology design stages of investment, while the effect of the past with heavy construction stage to the influence of the investment only about 10%.
Key Words: investment decision stage; design stage; investment control; improvements
一个建设项目,往往需要数百万、上千万、甚至上亿元的资金。项目建成以后能否盈利,能否达到预期效果,这是每个业主非常关心的问题。这就要求工程造价管理人员对项目从立项、可行性研究、初步设计、施工图设计直至竣工验收进行全过程跟踪,使项目投资控制贯穿于项目建设全过程投资决策、项目设计、招标、施工及竣工决算审计等五个阶段。投资决策阶段即可行性研究阶段,包括投资估算、策划;建设项目设计阶段包括方案估算、概算、施工图预算;招标阶段包括标书、标底编制、评标、定标;施工阶段包括中期进度款审核、跟踪动态控制等。
过去工程造价控制的重点一直在项目的实施阶段,而实践证明工程建设的不同阶段对投资的影响程度有很大的差异。据统计,投资决策和初步设计阶段对投资的影响程度最大,其次为技术设计阶段对投资的影响,而过去所著重的施工阶段对投资的影响只有10%左右。由此可见,工程建设的决策阶段和设计阶段是决定工程造价的关键阶段,工艺、流程、方案一经确定,工程造价基本上确定了。
1项目投资决策阶段的投资控制
1.1项目投资决策阶段目前存在的问题
目前在项目建议书阶段,通常由建设单位向公司投资计划部提出投资估算,内容相当简单往往造成漏项。在可行性研究阶段,建设单位委托设计单位、勘察设计单位编制可行性研究报告,并编制投资估算,该投资估算经审批后将作为此项目工程造价的最高限额。但由于本阶段以经济分析和方案为主,工程量不明确,所以设计院本阶段的投资估算,准确性较差,同时由于建设单位通常不是投资估算和造价控制的内行,而且对工艺流程和方案缺乏认真研究;有时建设单位为了所报项目能被批准,要求设计单位在投资估算时有意低估,搞“钓鱼工程”,增加了估算的不准确性。
1.2投资决策阶段的工程造价控制
1.2.1在投资决策阶段做好基础资料的收集,保证详实、准确
要做好项目的投资预测,需要很多资料,如工程所在地的水电路状况、地质情况、主要材料设备的价格资料、大宗材料的采购地以及现有已建类似工程资料,对于做经济评价的项目还要收集更多资料。造价人员要对资料的准确性、可靠性认真分析,保证投资预测、经济分析的准确。
1.2.2認真做好市场研究,是论证项目建设必要性的关键
市场研究就是指对拟建项目所提供的产品或服务的市场占有可能性分析。包括国内外市场在项目计算期内对拟建产品的需求状况;类似项目的建设情况;国家对该产业的政策和今后发展趋势等。要做好市场研究,技术经济人员就需要掌握大量的统计数据和信息资料,并进行综合分析和处理,项目建设的必要性。
1.2.3做好方案优化是控制工程造价的关键
据国外统计资料表明,在项目前期方案优化过程中节约投资的可能性为80%左右,所以,要真正有效地控制工程造价,就应该把工作重点放在前期工作上,在完成市场研究以后,结合项目的实际情况,在满足生产的前提下,遵循"效益至上"的原则,进行多方案比选。这就要求设计人员必须牢固树立经济意识,克服重技术,轻经济,设计保守浪费的倾向,明确今天的投资就是企业明天的成本,技术经济人员应有专业知识,了解设计意图,熟悉工艺技术方案,和设计人员密切配合,用动态分析方法进行多方案技术经济比较,要在降低工程造价上下功夫。通过方案优化,使工艺流程尽量简单,设备选型更加合理,从而节约大量资金。
1.2.4合理确定评价价格和基准参数是做好经济效益的基础
财务评价是在国家现行财税制度和价格体系下,计算项目范围内的效益和费用,分析项目的盈利能力、清偿能力,以考察项目在财务上的可行性。在财务评价中,评价价格的选用是项目经济评价的关键,直接影响评价的质量。目前在经济评价报告中,产品销售价格按市场价格计算,不考虑计算期内价格相对变动,这样,若产品销售价格逐年下降,那么就夸大了项目的效益,如果产品的价格是逐年上升的,就缩小了项目的效益。显然,经济评价仅用当时的市场价格来编制是不够的,这就要求评价人员针对不同项目的特点,结合市场分析、竞争力分析、不确定性分析等因素选取多种价格方案并加以分析,以使投资者对项目未来的效益有充分的了解和减少项目投资风险。
强化项目前期工作,规范项目投资决策,是提高投资运行质量的基础,在项目取舍上实行效益否决制,没有经济效益或经济效益差的项目,不安排建设,列入建设计划的项目,必须做可行性研究,可行性研究必须有经济效益评价,没有经济效益评价的可行性研究报告或方案不予评审,达不到经济效益标准的项目不予立项,突出项目前期工作的超前性。通过投资科学管理,提高投资经济运行质量,以保证公司全局经济效益的提高。
2项目设计阶段
2.1项目设计阶段目前存在的问题
当前推行限额设计尚有一定难度。一方面,长期以来人们只注重技术创新,设计人员在控制工程造价上的创新却很少得到表彰和奖励,反而要承担更多的风险,这样势必挫伤设计人员主动控制工程造价的积极性。另一方面,现行设计费收费偏低和计算方法不利于开展限额设计。实行限额设计,设计单位和设计人员势必付出更多的劳动和时间,低费率的设计收费与其所付出的劳动并不匹配;设计收费按工程投资额及相应费率计算更是与实行限额设计相矛盾。经济利益会驱使设计单位和设计人员提高工程造价,而不会主动控制和降低工程造价,设计单位只注意设计产值的完成量,而忽略设计产品的经济性。鉴于此,以行政和经济手段促使设计人员主动实行限额设计,控制工程造价是今后必然趋势。
2.1.1技术和经济的结合不够
长期以来,在工程建设领域,工程设计和投资控制工作联系不够紧密是一种普遍现象。一提到设计,大家必然想到那是设计人员的责任;一提到造价控制,想当然的是造价人员的职责。在实际工作中,一般都是设计人员根据设计委托进行现场调查,选择方案,进行设计,不同阶段向造价人员提供条件,进行估价或预算。造价人员对工程概况、现场情况了解很少,无法将各种影响因素考虑全面。所以工作中既要克服片面强调节约、忽视技术,又要反对重技术、轻经济、设计保守浪费的现象。所以造价人员应该及时对项目投资进行分析比较,反馈造价信息,能动地指导设计,使设计方案在满足生产要求的前提下,节约投资。
2.1.2设计中成本控制认识不足,影响竞争能力
设计人员在设计中一般都比较注重设计产品安全实用,技术先进,强调设计的产值,而对设计产品的经济性不够重视,不抓设计中的经济指标和成本控制工作。另外,现行的设计收费标准是以工程造价为取费基数,对设计中造成的浪费缺乏明确标准和控制措施,不带任何经济责任,具有较明显的计划经济色彩。2001年国家建设部对设计费重新调整,但随着与国际接轨,工程设计收费方法将引入限额按比例提成的机制,使得设计单位增强为业主控制投资成本的意识。
2.1.3造价控制环节脱节
目前基本建设项目投资管理部门都采取分段式的管理方法,与之相适应的估算、概算、预算和结算也是分段编制的。设计单位一般负责初步设计概算和施工图预算,但结算一般都不参与,造成投资控制的脱节。现在新材料、新设备不断更新,价格不断变化,定额调整滞后,对工程造价的约束力降低,预算和结算差距不断增大,如果设计单位没有机会了解实际发生的工程成本,做不到评价前阶段造价控制质量如何,缺乏信息反馈,无法进行事后分析,积累经验,在以后的工作中遇到同样的问题也就不能有所突破,不能进一步提高造价工作的质量。
2.2项目设计阶段的工程造价控制
2.2.1设计阶段没有引起足够重视,造成失误和浪费
设计阶段包括初步设计和施工图设计两个阶段,设计阶段应是全过程造价控制的重点。据相关统计,初步设计影响造价可能性75%~95%,技术阶段设计为35%~75%,设计费用一般只相当于建设工程全过程费用的1%以下,而这小于1%的费用对工程造价的影响程度占75%以上。然而,长期以来,建设单位普遍忽视设计阶段的造价控制,给予设计过程的时间紧迫,给予设计需要建设单位提供的资料不够完善和准确,而把管理的主要精力放在工程的实施阶段,在审核施工图预算、工程造价款结算上算细帐。这样做,尽管有一定的效果,但毕竟是“亡羊补牢”,事倍功半。
(1)违反基本建设程序和经济规律。基本建设程序是基本建设活动的客观规律。随着市场投资主体的多元化,许多业主为使项目尽快上马,不按基本建设程序和经济规律办事,任意简化和减少基本建设的程序和环节,压缩设计时间,不做项目可行性研究和初步设计,或项目可行性研究和初步设计与施工图设计一起做,甚至直接从施工图设计做起,边设计,边施工,造成投资决策失误,设计深度不深、设计质量低劣、设计更改频繁,致使工程造价无法得到控制。这些违反基本建设程序和经济规律的建设项目明显存在先天不足,使得以后阶段的工程造价很难得到控制。例如2007年的老爷庙联合站建设工程,在可研没有批复的情况下就开始了原油储罐区的设计和施工,设计时间紧迫,为满足施工要求,要求设计单位边设计边施工,设计单位只能采用临时白图作为现场施工依据。在施工图设计的同时,本工程正在进行可研的审查。当可研批复时,油田产能数据超出可研规模,在此基础上进行初步设计,此可研不能完全作为初步设计的依据,同时,各类设备已开始招标,中标厂家在规定时间内不能提供尺寸全面的图纸,设计单位根据主要尺寸进行基础设计并提供施工草图,常常造成没有设备正规图纸就将设备基础草图送到施工现场,施工单位不等设备到位进行基础核实就开始施工,造成大部分到货设备尺寸和提供的基础尺寸不吻合,使工程施工过程中现场存在很多调整。造成该工程共发生设计变更和现场签证2760多万元,增加投资占总建设投资的4.6%。
(2)重技术轻经济,技术与经济相脱节。在项目可行性研究和初步设计阶段,往往只注重对技术方案的论证,对经济因素考虑的较少,缺乏多方案比较和技术经济分析,造成工程投资的极大浪费。在施工图设计阶段,设计人员缺乏经济观念,设计只管技术,不管经济,甚至追求新、奇、异,造成投资失控。
2.2.2切实推行限额设计,推广标准设计
限额设计是以项目可行性研究报告的批复所确定的建设规模、建设内容、建设标准为依据,在投资估算限额范围内进行工程设计,以提高投资的经济效益。另外,从业主的角度讲,业主的资金是有限的,他的目的是通过项目建设实现经济效益,设计的任务就是利用业主的有限资金,合理确定工程标准、规模,确保项目的實施完成,保护业主的经济利益。从这个意义上讲限额设计更是业主所关心的。
设计过程中要积极推行限额设计,按照设计程序分阶段层层控制总投资,使其贯穿于可行性研究、初步设计、技术设计直到施工图设计的各个阶段,形成纵向控制;各设计阶段,按各专业进行投资分解,分块限额,具体分配到单元和专业,形成横向控制和纵向控制相结合。但提倡限额设计并不是单纯的追求降低造价,应该坚持科学,采用优化设计使技术和经济紧密结合,通过技术比较,经济分析和效果评价,力求以最少的投入,创造最大的效益。
做好限额设计,对造价人员提出了更高的要求。技术经济人员要对概算严格控制。实现了对投资限额的控制,也就同时实现了设计规模、设计标准、工程数量等各方面的控制。
标准设计是根据共同的条件按照通用的原则编制的,是经过一定程序批准的,可供设计单位重复使用,既优质又经济。标准设计能较好地贯彻执行国家的技术经济政策,合理利用能源、资源、材料和设备,并能够缩短设计周期,加快施工进度。因此,采用标准设计一般都能使工程造价低于非标设计的工程造价。
概算超估算、预算超概算、决算超预算,造成这种"三超"现象的主要原因之一就是没有实行限额设计。限额设计是控制工程造价的重要手段。由上述含义可知,限额设计是按上一阶段批准的投资(或造价)控制下一阶段的设计,而且在设计中以控制工程量为主要内容,抓住控制工程造价的核心,从而达到克服"三超"的目的。
加强设计变更管理也是限额设计的一个重要内容。在工程各实施阶段,设计变更更应尽量提前,变更发生得越早,损失越小,反之就越大。如在设计阶段变更,则只需修改图纸,其他费用尚未发生,损失有限;如在采购阶段变更,不仅仅需要修改图纸,而且设备、材料还须重新采购;若在施工阶段变更,除以上费用外,已施工的工程可能要拆除,势必造成重大变更损失。为此,必须加强设计变更管理,尽可能把设计变更控制在设计阶段初期,尤其对影响工程造价的重大设计变更,使工程造价得到有效控制。
现在我国的造价控制管理还是静态滞后的,不利于动态的控制投资,这就要求造价管理人员规范、系统地做好造价资料的积累,以适应造价工作新的要求,作为造价人员,个人专业素质,知识结构,技能水平非常重要,在拥有良好的职业道德同时,本着为业主负责的精神,必须加强专业知识学习和技能熟练操作,掌握计价规范和各地区相关概预算定额,不断积累工程经验,才能把握自身主动权,最大限度地减少失误。在方案阶段甚至可行性研究阶段密切配合设计人员,主动沟通、交流,做好事前控制,方能未雨绸缪,特别基本建设可研,是基本建设前期的重要内容,也是基本建设程序办事的重要阶段,其目的就是使建设项目决策正确,避免或减少决策失误而造成浪费,投资估算将对初步设计概算起控制作用,认真熟悉设计文件,了解设计意图,广泛收集市场信息及时分析研究,明确工程造价控制目标,使成本分析建立在真实、准确地基础上。只有对工程项目的全面了解,定额熟悉、计价熟练程度高,加大计算机应用技术力度,严把质量关,才能编制出水平高,质量好,速度高,让业主满意的精品来,确保编制阶段能较好的反映出工程实际造价,避免事倍功半,为项目决策提供科学的依据,提高企业竞争能力。
总之,工程造价投资控制涉及到工程建设的诸多方面,它与工程建设的全过程中每个环节紧密相连,控制工程造价不仅是领导者和工程技术人员的职责,而且是每一位工程建设参与者份内之事。提高造价人员的素质,提高技术经济分析论证能力,提高设计产品的经济性能,增强企业市场竞争力,为企业的长远发展奠定基础。
参考文献:冯俊杰、王兆军、张总翎,浅议项目管理知识在设计阶段应用
徐大图建设项目投资控制
肖笃姓工程经济投资分析