1990年初,上级决定在“海富花园 A、B 栋”工程上搞项目法施工的试点。4月份,我上任担任了该项目的项目经理。该工程建筑面积40761m~2,为两栋各为地下一层、地面以上35层的超高层高级公寓楼。我方作为主承包商,承建地下室(包括 C、D 栋)及上部结构工程、室内砌体、水电风安装工程。合同造价1794.59万元(±0.00以上建筑)合同总工期540天,其中主体325天。工程特点为工程量大,楼层高,结构复杂,施工难度大,工期紧迫。我代表项目与分公司签订了承包协议,基本内容为:土建部分按1240.83万元全额承包,实行内部独立核算;质量要求实现优良等级;安全目标无重大伤亡事故,月负伤频率不超
At the beginning of 1990, the superior decided to carry out pilot project construction on the “Haifu Garden A and B buildings” project. In April, I took up the position of project manager for this project. The project has a construction area of 40,761m2, which is a super high-rise apartment building with two floors, each with a basement level and 35 floors above the ground. As the main contractor, we have contracted to build basement (including C and D buildings) and superstructure engineering, indoor masonry, and hydropower wind installation projects. The contract cost of 17.9459 million yuan (±0.00 building) The total duration of the contract is 540 days, of which the main body is 325 days. The characteristics of the project are large quantities of work, high floors, complex structures, difficult construction, and tight schedules. On behalf of the project, I signed a contracting agreement with the branch company. The basic content is: the civil construction part is contracted at a total amount of 12.4083 million yuan, and internal independent accounting is carried out; the quality requirements achieve good grades; the safety target has no major casualties, and the frequency of monthly injuries is not excessive.