【摘要】随着电力建设事业的发展, 对于防电晕要求高的导线, 必须采用大型机械进行升空式展放; 为了节时、高效地满足工期紧、任务重的施工要求, 张力放线成为施工必要工序。一般适用于220 KV及以上的送电线路施工, 通常采用“一牵二”或“一牵四”的方法施工。本文笔者就张力放线法在光缆安装工程施工中的应用方法进行了分析,希望能为业界提供一定的参考价值。
【关键词】输电线路;张力放线;张力场;牵引场;牵引绳
Tension on-line method applied in the construction of cable installation
Liu Wei-heng
【Abstract】With the development of electric power construction, the high demand for anti-corona wire, large machinery must be put off type show; For when the festival and efficiently to meet tight schedules, tasks, heavy construction requirements, construction becomes necessary tension actinomycetes processes. More generally applicable to 220 KV power transmission line construction and, usually, "I take two" or "one led by four" method of construction. In this paper, the author tension stringing method application methods in the construction of the cable installation were analyzed, hoping to provide some reference value to the industry.
【Key words】Transmission line;Tension lines;Tension field;Traction field;Leash
“张力放线”是指利用人工已经展放好的导引绳,穿过选定放线流程段各塔号从牵引场牵拉过牵引绳,然后利用牵引绳带着张力牵拉过“两根”或“四根”钢芯铝铰线完成每一相导线的展放。一般要求:要在展放导线前,清除通道内的障碍物,针对性地对各等级的电力线、公路、乡村路、通讯线、光缆、果园等搭高跨越架。要选择符合要求的牵引场、张力场场地,并对其进行平整;对于进场的道路要予修补。按照“施工金具组装图”正确地悬挂绝缘子串及放线滑车;耐张塔按相应的预偏角度悬挂放线滑车。进行现场实际勘测,进行准确的导线布线。本文笔者结合多年的工作实践经验,对张力放线法在光缆安装工程施工中的应用进行了阐述。
1. 工程概况
(1)甘肃瓜州安北第二风电场B区200MW工程场址位于酒泉地区瓜州县城东北约60Km、玉门镇西北约88 Km处的戈壁荒滩,东经96°16′34.2″~96°20′10.1″,北纬40°45′40.8″~40°54′35.5″之间,其中A区占地36Km2。场址区海拔高度在1475m~1640m之间,地势开阔,地形平坦。风电场场址南部边缘紧邻兰新铁路,北部边缘紧邻安北第三风电场,西部边缘紧邻安北第一风电场,东部则与安北第三、四风电场相邻。
(2)根据风机布置情况,综合考虑各种因素后,将134台风机分为12组,每组对应一回35kv集电线路,共12回。全部输电线路总亘长426.9Km(其中LGJ-120/25线路79.3Km 、LGJ-185/30线路285.6Km、LGJ-240/30线路62Km)。线路根据发电负荷要求,按经济电流密度分别选择LGJ-185/30 和LGJ-120/20 、LGJ-240/30导线,线路全线架设 GJ-50避雷线。
(3)本工程的项目法人、委建单位、设计单位见表1。
表1
业 主 单 位 甘肃中电酒泉第三风力发电有限公司
招 标人 中电国际新能源控股有限公司
设 计 单 位 中国水电顾问集团西北勘探设计研究院
监 理 单 位 黑龙江润华电力工程项目管理有限公司
建 设 工 期 62天
2. 光缆的展放施工方法及措施
2.1ADSS常用安装方法。
ADSS常用安装架线方法推荐为张力放线法,可保证与障碍物和其他物体有足够的间隙,避免发生摩擦,且不会损伤ADSS。同时可减少青苗赔偿、减轻体力劳动并提高施工进度(ADSS安装示意图见图1)。
2.2施工准备。
2.2.1放线通道处理、障碍物清除、交叉跨越协议及防护措施。
一般与电力线路施工结合进行,按《架空送(配)电线路设计技术规程》、《电力建设施工及验收暂行技术规范》等有关规定,在施工前对线路所经过的区域作通道清理,保证运输畅通。
图1ADSS安装示意图
2.2.2牵引场和张力场的布置。
(1)张力场一般选择宽约10m,长约25m的平整场地设置,并应能方便张力机、光缆线盘等设备与材料的放置与搬运;牵引场可以参照张力场的条件进行选择。
(2)牵引场和张力场应尽量布置在被架设段两端耐张塔外侧且应布置在线路方向上。在受到地形限制时也可选在内侧。若牵张场不能布置在放线方向上,可通过大直径滑轮来导向,但注意放线时不要滑槽。
(3)张力机和牵引机到第一基杆塔的间距应至少保持3倍塔高,张力机与放线架线轴之间的距离应不小于5m。
2.2.3悬挂放线滑轮。
根据光缆线路施工技术要求,在每一个杆塔上吊挂满足尺寸要求的滑轮。
2.2.4牵引绳布放与升空。
牵引绳采用人工展放,按牵引绳盘长分段布线、展放,然后用抗弯连接器连接,连接必须有专人负责;展放完毕后,应对所有牵引绳顺线检查连接是否良好。
2.2.5牵引端头连接。
在放线过程中,ADSS内的光纤容易因ADSS的额外扭转而受到影响和损伤,因此,应按要求制作好牵引端,以
确保在放线过程中ADSS不发生扭转。
3. ADSS展放过程控制
(1)按技术部门给定的参数调整控制光缆张力,施加的张力一般控制10%RTS以内,在施工过程中施加在光缆上的任一张力,均应不超过20%RTS。牵引机的牵引力应按技术部门所给定的设定值控制。起始放线速度为5m/min,待光缆通过第一基杆塔后,可均匀加速至30m/min左右,最大放线速度应不超过40m/min。牵引时尽量匀速前进,严禁突然加速或减速,严禁放线中抖动。
(2)放线时,每个转角杆塔顶部和交叉跨越点均必须有专人看管,以便发生夹线或其它情况时及时报告处理。光缆牵引端头应在施工人员监视下通过滑轮。光缆端头及防扭鞭临近放线滑轮,尤其是转角塔放线滑轮时,应均匀放慢牵引速度,以便防扭鞭顺利通过滑轮。防扭鞭顺利通过滑轮后可均匀加速至原来的牵引速度。
(3)光缆在展放过程中不能落地,确保光缆与跨越物保持3~5m的安全距离。光缆的最小弯曲半径应确保在0.5m以上,架设过程中临时中断时,应及时通过手闸或磨杠阻止缆盘上的光缆继续绕出,否则易造成弯曲损坏,同时要避免在光缆上产生扭距。光缆展放完毕后,尾缆要留住,并且预留长度应不少于耐张接续塔的高度(或门型构架高度)再加15m,作为接头或者备用。不要使尾缆着地,不可使光缆的弯曲半径小于0.5m,严禁出现硬弯、打金钩等现象。光缆不允许两盘连放,如受地形限制,确实需要两盘连放的必须经过相关方面的确认,并制订详细的方案。
4. ADSS临时固定和尾端锚固
光缆如未能在一日内展放完毕时,应在牵引端、张力端各自对牵引绳、光缆进行临时锚固。张力端锚线点到张力机之间的光缆松弛度以解除对牵张机的拉力为宜,不能过分松弛,光缆不得拖地。光缆展放完毕后如不能立即紧、挂线,也应将光缆临时锚住。此时应在光缆尾端锚线,将光缆专用卡线工具卡在光缆尾端3~4m处。锚线时也应有相应的防扭措施,可在与卡线器相连的U型环上坠重物防扭。
5. 结语
近几年来通过 500 KV电力线路展放施工, 发现张力展放导线, 可在防护导线磨损、缩减施工工期、提高施工效益方面取得很好效果。希望今后更好地完善施工方法, 更大程度地运用于高电压等级的线路施工中。
参考文献
[1]陈小花. 关于500kV输电线路张力放线技术研究[J]. 现代经济信息,2013,11:291+308.
[2]毛哲轩. 浅谈客运专线大张力放线施工技术[J]. 铁道建筑技术,2009,06:109~112.
[3]卓可思. 500kV架空输电线路张力架线施工技术[J]. 电源技术应用,2014,01:45+49.
[文章编号]1006-7619(2014)06-26-344
【关键词】输电线路;张力放线;张力场;牵引场;牵引绳
Tension on-line method applied in the construction of cable installation
Liu Wei-heng
【Abstract】With the development of electric power construction, the high demand for anti-corona wire, large machinery must be put off type show; For when the festival and efficiently to meet tight schedules, tasks, heavy construction requirements, construction becomes necessary tension actinomycetes processes. More generally applicable to 220 KV power transmission line construction and, usually, "I take two" or "one led by four" method of construction. In this paper, the author tension stringing method application methods in the construction of the cable installation were analyzed, hoping to provide some reference value to the industry.
【Key words】Transmission line;Tension lines;Tension field;Traction field;Leash
“张力放线”是指利用人工已经展放好的导引绳,穿过选定放线流程段各塔号从牵引场牵拉过牵引绳,然后利用牵引绳带着张力牵拉过“两根”或“四根”钢芯铝铰线完成每一相导线的展放。一般要求:要在展放导线前,清除通道内的障碍物,针对性地对各等级的电力线、公路、乡村路、通讯线、光缆、果园等搭高跨越架。要选择符合要求的牵引场、张力场场地,并对其进行平整;对于进场的道路要予修补。按照“施工金具组装图”正确地悬挂绝缘子串及放线滑车;耐张塔按相应的预偏角度悬挂放线滑车。进行现场实际勘测,进行准确的导线布线。本文笔者结合多年的工作实践经验,对张力放线法在光缆安装工程施工中的应用进行了阐述。
1. 工程概况
(1)甘肃瓜州安北第二风电场B区200MW工程场址位于酒泉地区瓜州县城东北约60Km、玉门镇西北约88 Km处的戈壁荒滩,东经96°16′34.2″~96°20′10.1″,北纬40°45′40.8″~40°54′35.5″之间,其中A区占地36Km2。场址区海拔高度在1475m~1640m之间,地势开阔,地形平坦。风电场场址南部边缘紧邻兰新铁路,北部边缘紧邻安北第三风电场,西部边缘紧邻安北第一风电场,东部则与安北第三、四风电场相邻。
(2)根据风机布置情况,综合考虑各种因素后,将134台风机分为12组,每组对应一回35kv集电线路,共12回。全部输电线路总亘长426.9Km(其中LGJ-120/25线路79.3Km 、LGJ-185/30线路285.6Km、LGJ-240/30线路62Km)。线路根据发电负荷要求,按经济电流密度分别选择LGJ-185/30 和LGJ-120/20 、LGJ-240/30导线,线路全线架设 GJ-50避雷线。
(3)本工程的项目法人、委建单位、设计单位见表1。
表1
业 主 单 位 甘肃中电酒泉第三风力发电有限公司
招 标人 中电国际新能源控股有限公司
设 计 单 位 中国水电顾问集团西北勘探设计研究院
监 理 单 位 黑龙江润华电力工程项目管理有限公司
建 设 工 期 62天
2. 光缆的展放施工方法及措施
2.1ADSS常用安装方法。
ADSS常用安装架线方法推荐为张力放线法,可保证与障碍物和其他物体有足够的间隙,避免发生摩擦,且不会损伤ADSS。同时可减少青苗赔偿、减轻体力劳动并提高施工进度(ADSS安装示意图见图1)。
2.2施工准备。
2.2.1放线通道处理、障碍物清除、交叉跨越协议及防护措施。
一般与电力线路施工结合进行,按《架空送(配)电线路设计技术规程》、《电力建设施工及验收暂行技术规范》等有关规定,在施工前对线路所经过的区域作通道清理,保证运输畅通。
图1ADSS安装示意图
2.2.2牵引场和张力场的布置。
(1)张力场一般选择宽约10m,长约25m的平整场地设置,并应能方便张力机、光缆线盘等设备与材料的放置与搬运;牵引场可以参照张力场的条件进行选择。
(2)牵引场和张力场应尽量布置在被架设段两端耐张塔外侧且应布置在线路方向上。在受到地形限制时也可选在内侧。若牵张场不能布置在放线方向上,可通过大直径滑轮来导向,但注意放线时不要滑槽。
(3)张力机和牵引机到第一基杆塔的间距应至少保持3倍塔高,张力机与放线架线轴之间的距离应不小于5m。
2.2.3悬挂放线滑轮。
根据光缆线路施工技术要求,在每一个杆塔上吊挂满足尺寸要求的滑轮。
2.2.4牵引绳布放与升空。
牵引绳采用人工展放,按牵引绳盘长分段布线、展放,然后用抗弯连接器连接,连接必须有专人负责;展放完毕后,应对所有牵引绳顺线检查连接是否良好。
2.2.5牵引端头连接。
在放线过程中,ADSS内的光纤容易因ADSS的额外扭转而受到影响和损伤,因此,应按要求制作好牵引端,以
确保在放线过程中ADSS不发生扭转。
3. ADSS展放过程控制
(1)按技术部门给定的参数调整控制光缆张力,施加的张力一般控制10%RTS以内,在施工过程中施加在光缆上的任一张力,均应不超过20%RTS。牵引机的牵引力应按技术部门所给定的设定值控制。起始放线速度为5m/min,待光缆通过第一基杆塔后,可均匀加速至30m/min左右,最大放线速度应不超过40m/min。牵引时尽量匀速前进,严禁突然加速或减速,严禁放线中抖动。
(2)放线时,每个转角杆塔顶部和交叉跨越点均必须有专人看管,以便发生夹线或其它情况时及时报告处理。光缆牵引端头应在施工人员监视下通过滑轮。光缆端头及防扭鞭临近放线滑轮,尤其是转角塔放线滑轮时,应均匀放慢牵引速度,以便防扭鞭顺利通过滑轮。防扭鞭顺利通过滑轮后可均匀加速至原来的牵引速度。
(3)光缆在展放过程中不能落地,确保光缆与跨越物保持3~5m的安全距离。光缆的最小弯曲半径应确保在0.5m以上,架设过程中临时中断时,应及时通过手闸或磨杠阻止缆盘上的光缆继续绕出,否则易造成弯曲损坏,同时要避免在光缆上产生扭距。光缆展放完毕后,尾缆要留住,并且预留长度应不少于耐张接续塔的高度(或门型构架高度)再加15m,作为接头或者备用。不要使尾缆着地,不可使光缆的弯曲半径小于0.5m,严禁出现硬弯、打金钩等现象。光缆不允许两盘连放,如受地形限制,确实需要两盘连放的必须经过相关方面的确认,并制订详细的方案。
4. ADSS临时固定和尾端锚固
光缆如未能在一日内展放完毕时,应在牵引端、张力端各自对牵引绳、光缆进行临时锚固。张力端锚线点到张力机之间的光缆松弛度以解除对牵张机的拉力为宜,不能过分松弛,光缆不得拖地。光缆展放完毕后如不能立即紧、挂线,也应将光缆临时锚住。此时应在光缆尾端锚线,将光缆专用卡线工具卡在光缆尾端3~4m处。锚线时也应有相应的防扭措施,可在与卡线器相连的U型环上坠重物防扭。
5. 结语
近几年来通过 500 KV电力线路展放施工, 发现张力展放导线, 可在防护导线磨损、缩减施工工期、提高施工效益方面取得很好效果。希望今后更好地完善施工方法, 更大程度地运用于高电压等级的线路施工中。
参考文献
[1]陈小花. 关于500kV输电线路张力放线技术研究[J]. 现代经济信息,2013,11:291+308.
[2]毛哲轩. 浅谈客运专线大张力放线施工技术[J]. 铁道建筑技术,2009,06:109~112.
[3]卓可思. 500kV架空输电线路张力架线施工技术[J]. 电源技术应用,2014,01:45+49.
[文章编号]1006-7619(2014)06-26-344