摘要:随着我国建筑物的服务水平不断提高,现代建筑朝着智能化,电气化方向发展,这对我国建筑工程电气安装施工技术提出了更高的要求,为了确保建筑电气安装施工能够顺利完成,我们应该不断改进和完善施工技术及施工工艺。本文给合工程实例,对电气工程中主要施工技术进行了详细的探讨。
关键词:电气工程;安装;施工方法
Abstract: along with our country the structure of the service level continuously improve, modern building, towards intelligent electrification direction, this for our country construction project electrical installation construction technology put forward higher request, in order to ensure that building electrical installation is complete, we should continue to improve and perfect the construction technology and construction technology. Give us engineering examples, this paper mainly in the electrical engineering construction technology has carried on the detailed discussion.
Keywords: electrical engineering; Installation; The construction method
中图分类号:TU855 文献标识码:A文章编号:2095-2104(2013)
1 工程概念
该工程以某厂为例,建筑面积22450平方米,工期74天,给排水、消防、空调、电气、土建、装修同时施工,为了做好这个工程我们是按以下步骤进行。
2 电气施工前应完成的前期工作准备
施工前应依据工程进度确定进场的工作人员。实地施工的人员要认真熟悉国家关于具体施工的规范、准则、熟悉该项目的施工图纸,同时准备好相关的施工标准图纸进行对比审核。同时要求编制好合理科学的施工预算方案,对施工人员进行施工前期的培训和内部控制学习,按照工程的工艺流程进行工程施工。
3 建筑电气工程施工的主要内容
3.1 关于配电箱、配件柜的安装操作
(1)建筑工程配电箱具体由两部分组成明箱和暗箱,配电箱应根据具体要求实行定制。暗箱周围要求用砂浆填充实在,根据已经预留好的尺寸确定相应的水平垂直标高。明箱在量好尺寸之后用膨胀螺丝等紧固件固定好,在固定过程中保持箱体的水平垂直,同时尽量保证箱体表面完整。
(2)验收配电箱应注意相应的铭牌,确定厂家名称以及配电箱所附属的配件的完整,在开箱进行验收时必须有监理,厂商在场,同时做好记录并各方签字确认。
(3)配电箱的安装要求:
在建筑电气工程施工过程中配电箱的底部距离地面有一定的设计和规范要求。首先,导线的剥削应细心,不能损伤导线线芯,同时线压头要牢固可靠、出现多股导线与端子排相互连接的,要求加装压线端子,二者同时涮锡,再压接在端子排上,多股导线压线连接要注意导线的具体股数。引出面板的导线要平整,光滑,同时金属面板要铺设绝缘材料。箱体内部各开关闸应标明线路回路情况与各
自支线相对应。同时要保证仪表在状态,保持表面整洁,安全,各零配件使用灵活、齐全。
(4)安装基础型钢时,首先要进行调直,然后按照图纸上的具体要求进行操作最后刷防锈漆,预留铁件上架设时应确定其位置并进行固定,同时注意扁钢和基础型钢的焊接长度。
(5)配件柜安装应注意每台配电柜应单独与接地干线的连接,同时找正固定的位置严格执行图纸设计。
(6)安装桥架和线槽时首先应验收质量,吊顶内桥架安装时应提前进行。安装完成后要进行相应的测试。
3.2 电气工程管路的铺设
(1)根据图纸要求或其他具体要求,施工人员要熟悉图纸关于管路的设计,包括管线的规格,铺设方式,具体型号等等
(2)在施工过程中要严格按照项目设计的图纸进行管线的连接,铺设,同时严格执行关于保护层,管道口等相关设计,要及时检查,相互监督,保证施工质量。
(3)吊顶内管路铺设及楼板,地板、墙内的管线铺设应根据各自不同的要求进行相应处理,要防止水泥等堵塞管道,同时要注意管道的折损和变形。
3.3 关于管道、金属线槽内部的配线
土建结构施工完毕后,我们应先将管道及线槽内进行清理,同时做好相应的防缘层的处理,穿线过程中要注意采用具体规定的三色线。穿线管内绝对不能出现导线接头,要进行相应的电阻绝缘测试。根据不同的测试标准确定其是否合格。
3.4 电缆铺设
(1)经检验合格的电缆,在电气设备,配电箱,配电柜等安装,测试之后就可以进行铺设。
(2)根据已经画好的电缆铺设,排列图表,选择相应的电缆进行铺设,测试,在电缆铺设过程中应在适当的位置悬挂电缆的具体特性,例如型号,电压等级或其他编号等。电缆铺设拐弯时应根据具体的要求进行合理科学的铺设。
(3)遇到其他具体情况的要进行技术交底,并作相应的记录。
3.5 灯具在安装过程中的操作工艺要求
(1)在安装灯具之前,首先要对灯具的外观,结构等进行检验,根据安装的具体环境,选择相应适合的灯具,同时要检查灯具内部的配线是不是达到相应的设计要求和工藝水准。如果是指示灯则要确定指示方向和灯光是否一致,应急灯要求反映灵敏快速,较大型的灯具安装要检查是否有预埋件,或预埋件是否牢固,安全。灯具外壳是否绝缘等。安装灯具时位置要准确,同时一定要坚固、安全。
(2)安装灯座时要注意灯座和螺丝台的固定,相线要与接线柱触点,要防止连接线路时出现螺丝松动的情况,导致发生电路短路故障等。
(3)在使用接线盒安装壁灯的过程中,在安装之前应该根据灯具具体的外型构造选择适合的全盘的塑料台,再把需要安装的灯具摆放在塑料台上面,注意灯具摆放的位置要适中,周围空余的地方要均匀。然后在在木台上用电钻等专业工具开出相应的线孔和相应的安装孔,同时在相应的灯具底板上开安装孔,之后将由木台出线孔中甩出的灯具灯头线,在接线盒式内接头,并进行绝缘处理,严密包扎。之后将包扎好的接头放入盒式内,将塑料台正对着接线盒,紧贴墙面,用螺丝等固定件将调整好尺寸,位置的塑料台直接固定在盒子上,最后配好相应数量的灯泡、灯伞或灯罩等其他配件。
(4)关于荧光灯的具体安装:
安装组合链式荧光灯时要首先在相应的顶棚上安装好适合尺寸的塑料台,然后将吊盒、法兰等固定在塑料台的中心。将灯具导线与其他吊线盒内的电源线进行相互连接,应注意的是当进行法兰盘内连接时,要用绝缘胶带严密包扎梳理线头后固定相应的法兰盘,将所安装灯具的反光板用螺丝等固定件固定在灯箱上,观察调整好合适的灯角,最后装上灯管。
安装荧光吸顶灯时应该根据已经处理好的预埋灯盒的位置来确定荧光灯的安装位置,直接将荧光灯安装在建筑物表面,安装时为了美观,因此灯头盒应被荧光灯的灯箱完全遮盖,在灯箱的底板上与灯位盒相应的位置进行电钻打孔。用螺丝等紧固件进行紧固安装即可。
(5) 经过吊顶的建筑物来说嵌入式灯具一般安装在顶棚中。在安装时我们要注意龙骨的承重等因素。同时灯具在挖孔时要使用相应的工具。对于大型嵌入式灯具的安装要采用相应的支架,铁架等相互连接的方法。
3.6 电气工程施工的工艺流程
(1)前期清理工作:清理线盒里面残存的灰尘,水泥、灰块等建筑残留,同时用干净的布块将线盒内部全面擦拭。
(2)接线的具体规定和操做流程
关于开关接线的具体规定:开关控制着所有电器、灯具的相线。在开关接線之前,应先将盒内的导线进行理顺,依次接线后,将盒内较长的导线盘整齐,压放于开关盒内。
关于各个插座接线具体规定:按照常规规定,单相两孔插座的右极和左极分别接相线和接零线,而单相三孔、三相四孔的在接线时相对于单相两孔而言地线或零线都在最上方。
关于接线的具体要求:在处理导线维修长度削去绝缘皮时一定要注意不能碰伤线芯、否则这段线会被损坏。如果进行接线处理的开关或插座是接线柱,应该把导线按照顺时针的方向缠绕在开关或插座相对应的接线柱上,最后旋紧压头。
(3)开关、插座的安装
所安装的开关、插座其具体的规格、型号要符合设计的要求,不能使用不合格产品。开关、插座安装的位置高低应该一致,应该根据相应的要求进行确定,不能违规开孔安装。相同建筑物内的开关的方向应该一致,高度要求符合设计要
求,同时要求插座有保护盖板,而且开关、插座要使用灵活、接触方便可靠。
开关、插座,固定时一定要平整,端正,与墙面齐平,同时表面有装饰的一定要将装饰安装整齐。开关插座要用螺丝进行固定。
3.7 开关、插座进行通电测试
已经安装好的开关、插座进行通电测试,测试过程中应按照单元每户测试线路的绝缘电阻等情况,同时要求做好相应的测试记录。单个支线的绝缘电阻测试验收合格后再进行通电试运行、施工人员应该在通电后仔细检查和巡视、确定漏电开关是否出现掉闸、跳闸等现象。注意插座接线是否正确,插座、开关的面板是否平整干净等。
3.8 建筑防雷工程
任何建筑设计都应该有其相应的防雷工程:具体由下面几方面的内容:
(1)接地体的安装:在建筑设计中我们经常用桩基和承台钢筋来作为建筑接地体。把相应数量,相应位置的桩基钢筋进行焊接与主筋进行焊好,做好相应的清除防腐、防锈处理后,做好标识便于以后引出检查。
(2)接地体按照规定完成之后,要进行相应的核实,在核实过程中应注意其位置,材料,焊接工艺均应达到设计施工的具体要求和防雷验收规范方可填埋。回填土内不能有石块或建筑垃圾。同时要进行遥测并做好相应的电阻测试记录。
(3)接地体在安装过程中有着严格的规定,在处理过程中应严格按照规定设计进行安装,配置及防腐处理。同时接地体的间距和距离建筑物的距离也有着具体的规定,例如接地体埋设位置应距离建筑物3 米以上,环形接地体除外等等。
(4)接地干线首先要进行调值,侧位,等之后才能进行安装,铺设时首先要根据相应的设计要求开挖相应尺寸的沟槽,将扁钢侧方入内。压实填回土。为方便接引地线要注意接地干线末端露出地面部分应小于50 厘米。
4 关于接地干线的安装规定
应在接地干线穿过墙壁、楼板和地坪的地方加装钢管或其它坚固的保护套:同时进行相应的防腐措施。在跨越建筑物变形缝处,还应设补偿器或用接地线身弯成弧状代替。
4.1 接地干线支架的安装,接地干线安装时应尽量适用施工结构的要求预埋相应的支架或铁件。应根据相应的设计要求进行不同的划分和定位。在进行凿空时,洞口的大小应该保持一致。埋设支架时应进行调值,找平等。
4.2 避雷、防雷扁管的铺设
在进行铺设之前要将所需要的扁钢调直。调直之后的扁钢作为的引下线被运到各具体的安装地点,根据具体的设计要求在建筑物上处理好,之后将其下端与接地体进行焊接,也可以与断接卡进行连接,随着建筑物的逐步增高,将引下线铺设于建筑物内屋顶并出屋面一定长度,以备与避雷网连接。如需接头则应进行焊接,焊接后应敲掉药皮并刷防锈漆,最后由相关的施工人员进行验收,同时做好相应的记录。
4.3 避雷网和避雷针的安装操作
避雷网和避雷针在安装前首先要进行调直。根据相应的操作程序将避雷网和避雷针焊接在相应的位置,完成之后要进行表面处理,涂刷银粉、防锈漆等。
4.4 其他应注意的事项
检查施工实际安装是否与当初的具体设计图纸相符,检测电阻的具体情况,若出现实际电阻值较大时应进行及时的补救措施以达到设计要求等等。
结束语
通过以上内容,大家可以了解到建筑工程中电气工程中的部分的施工内容,在工程施工实践中不断的总结经验,同时注重质量。 当然不同的在实际施工过程中,不同工程,不同设计方案,电气工程施工的方式方法也是不尽相同的,我们要在实践中不断的发现问题解决问题,不断的发展前进。使得建筑电气工程施工技术更加成熟,完善。
关键词:电气工程;安装;施工方法
Abstract: along with our country the structure of the service level continuously improve, modern building, towards intelligent electrification direction, this for our country construction project electrical installation construction technology put forward higher request, in order to ensure that building electrical installation is complete, we should continue to improve and perfect the construction technology and construction technology. Give us engineering examples, this paper mainly in the electrical engineering construction technology has carried on the detailed discussion.
Keywords: electrical engineering; Installation; The construction method
中图分类号:TU855 文献标识码:A文章编号:2095-2104(2013)
1 工程概念
该工程以某厂为例,建筑面积22450平方米,工期74天,给排水、消防、空调、电气、土建、装修同时施工,为了做好这个工程我们是按以下步骤进行。
2 电气施工前应完成的前期工作准备
施工前应依据工程进度确定进场的工作人员。实地施工的人员要认真熟悉国家关于具体施工的规范、准则、熟悉该项目的施工图纸,同时准备好相关的施工标准图纸进行对比审核。同时要求编制好合理科学的施工预算方案,对施工人员进行施工前期的培训和内部控制学习,按照工程的工艺流程进行工程施工。
3 建筑电气工程施工的主要内容
3.1 关于配电箱、配件柜的安装操作
(1)建筑工程配电箱具体由两部分组成明箱和暗箱,配电箱应根据具体要求实行定制。暗箱周围要求用砂浆填充实在,根据已经预留好的尺寸确定相应的水平垂直标高。明箱在量好尺寸之后用膨胀螺丝等紧固件固定好,在固定过程中保持箱体的水平垂直,同时尽量保证箱体表面完整。
(2)验收配电箱应注意相应的铭牌,确定厂家名称以及配电箱所附属的配件的完整,在开箱进行验收时必须有监理,厂商在场,同时做好记录并各方签字确认。
(3)配电箱的安装要求:
在建筑电气工程施工过程中配电箱的底部距离地面有一定的设计和规范要求。首先,导线的剥削应细心,不能损伤导线线芯,同时线压头要牢固可靠、出现多股导线与端子排相互连接的,要求加装压线端子,二者同时涮锡,再压接在端子排上,多股导线压线连接要注意导线的具体股数。引出面板的导线要平整,光滑,同时金属面板要铺设绝缘材料。箱体内部各开关闸应标明线路回路情况与各
自支线相对应。同时要保证仪表在状态,保持表面整洁,安全,各零配件使用灵活、齐全。
(4)安装基础型钢时,首先要进行调直,然后按照图纸上的具体要求进行操作最后刷防锈漆,预留铁件上架设时应确定其位置并进行固定,同时注意扁钢和基础型钢的焊接长度。
(5)配件柜安装应注意每台配电柜应单独与接地干线的连接,同时找正固定的位置严格执行图纸设计。
(6)安装桥架和线槽时首先应验收质量,吊顶内桥架安装时应提前进行。安装完成后要进行相应的测试。
3.2 电气工程管路的铺设
(1)根据图纸要求或其他具体要求,施工人员要熟悉图纸关于管路的设计,包括管线的规格,铺设方式,具体型号等等
(2)在施工过程中要严格按照项目设计的图纸进行管线的连接,铺设,同时严格执行关于保护层,管道口等相关设计,要及时检查,相互监督,保证施工质量。
(3)吊顶内管路铺设及楼板,地板、墙内的管线铺设应根据各自不同的要求进行相应处理,要防止水泥等堵塞管道,同时要注意管道的折损和变形。
3.3 关于管道、金属线槽内部的配线
土建结构施工完毕后,我们应先将管道及线槽内进行清理,同时做好相应的防缘层的处理,穿线过程中要注意采用具体规定的三色线。穿线管内绝对不能出现导线接头,要进行相应的电阻绝缘测试。根据不同的测试标准确定其是否合格。
3.4 电缆铺设
(1)经检验合格的电缆,在电气设备,配电箱,配电柜等安装,测试之后就可以进行铺设。
(2)根据已经画好的电缆铺设,排列图表,选择相应的电缆进行铺设,测试,在电缆铺设过程中应在适当的位置悬挂电缆的具体特性,例如型号,电压等级或其他编号等。电缆铺设拐弯时应根据具体的要求进行合理科学的铺设。
(3)遇到其他具体情况的要进行技术交底,并作相应的记录。
3.5 灯具在安装过程中的操作工艺要求
(1)在安装灯具之前,首先要对灯具的外观,结构等进行检验,根据安装的具体环境,选择相应适合的灯具,同时要检查灯具内部的配线是不是达到相应的设计要求和工藝水准。如果是指示灯则要确定指示方向和灯光是否一致,应急灯要求反映灵敏快速,较大型的灯具安装要检查是否有预埋件,或预埋件是否牢固,安全。灯具外壳是否绝缘等。安装灯具时位置要准确,同时一定要坚固、安全。
(2)安装灯座时要注意灯座和螺丝台的固定,相线要与接线柱触点,要防止连接线路时出现螺丝松动的情况,导致发生电路短路故障等。
(3)在使用接线盒安装壁灯的过程中,在安装之前应该根据灯具具体的外型构造选择适合的全盘的塑料台,再把需要安装的灯具摆放在塑料台上面,注意灯具摆放的位置要适中,周围空余的地方要均匀。然后在在木台上用电钻等专业工具开出相应的线孔和相应的安装孔,同时在相应的灯具底板上开安装孔,之后将由木台出线孔中甩出的灯具灯头线,在接线盒式内接头,并进行绝缘处理,严密包扎。之后将包扎好的接头放入盒式内,将塑料台正对着接线盒,紧贴墙面,用螺丝等固定件将调整好尺寸,位置的塑料台直接固定在盒子上,最后配好相应数量的灯泡、灯伞或灯罩等其他配件。
(4)关于荧光灯的具体安装:
安装组合链式荧光灯时要首先在相应的顶棚上安装好适合尺寸的塑料台,然后将吊盒、法兰等固定在塑料台的中心。将灯具导线与其他吊线盒内的电源线进行相互连接,应注意的是当进行法兰盘内连接时,要用绝缘胶带严密包扎梳理线头后固定相应的法兰盘,将所安装灯具的反光板用螺丝等固定件固定在灯箱上,观察调整好合适的灯角,最后装上灯管。
安装荧光吸顶灯时应该根据已经处理好的预埋灯盒的位置来确定荧光灯的安装位置,直接将荧光灯安装在建筑物表面,安装时为了美观,因此灯头盒应被荧光灯的灯箱完全遮盖,在灯箱的底板上与灯位盒相应的位置进行电钻打孔。用螺丝等紧固件进行紧固安装即可。
(5) 经过吊顶的建筑物来说嵌入式灯具一般安装在顶棚中。在安装时我们要注意龙骨的承重等因素。同时灯具在挖孔时要使用相应的工具。对于大型嵌入式灯具的安装要采用相应的支架,铁架等相互连接的方法。
3.6 电气工程施工的工艺流程
(1)前期清理工作:清理线盒里面残存的灰尘,水泥、灰块等建筑残留,同时用干净的布块将线盒内部全面擦拭。
(2)接线的具体规定和操做流程
关于开关接线的具体规定:开关控制着所有电器、灯具的相线。在开关接線之前,应先将盒内的导线进行理顺,依次接线后,将盒内较长的导线盘整齐,压放于开关盒内。
关于各个插座接线具体规定:按照常规规定,单相两孔插座的右极和左极分别接相线和接零线,而单相三孔、三相四孔的在接线时相对于单相两孔而言地线或零线都在最上方。
关于接线的具体要求:在处理导线维修长度削去绝缘皮时一定要注意不能碰伤线芯、否则这段线会被损坏。如果进行接线处理的开关或插座是接线柱,应该把导线按照顺时针的方向缠绕在开关或插座相对应的接线柱上,最后旋紧压头。
(3)开关、插座的安装
所安装的开关、插座其具体的规格、型号要符合设计的要求,不能使用不合格产品。开关、插座安装的位置高低应该一致,应该根据相应的要求进行确定,不能违规开孔安装。相同建筑物内的开关的方向应该一致,高度要求符合设计要
求,同时要求插座有保护盖板,而且开关、插座要使用灵活、接触方便可靠。
开关、插座,固定时一定要平整,端正,与墙面齐平,同时表面有装饰的一定要将装饰安装整齐。开关插座要用螺丝进行固定。
3.7 开关、插座进行通电测试
已经安装好的开关、插座进行通电测试,测试过程中应按照单元每户测试线路的绝缘电阻等情况,同时要求做好相应的测试记录。单个支线的绝缘电阻测试验收合格后再进行通电试运行、施工人员应该在通电后仔细检查和巡视、确定漏电开关是否出现掉闸、跳闸等现象。注意插座接线是否正确,插座、开关的面板是否平整干净等。
3.8 建筑防雷工程
任何建筑设计都应该有其相应的防雷工程:具体由下面几方面的内容:
(1)接地体的安装:在建筑设计中我们经常用桩基和承台钢筋来作为建筑接地体。把相应数量,相应位置的桩基钢筋进行焊接与主筋进行焊好,做好相应的清除防腐、防锈处理后,做好标识便于以后引出检查。
(2)接地体按照规定完成之后,要进行相应的核实,在核实过程中应注意其位置,材料,焊接工艺均应达到设计施工的具体要求和防雷验收规范方可填埋。回填土内不能有石块或建筑垃圾。同时要进行遥测并做好相应的电阻测试记录。
(3)接地体在安装过程中有着严格的规定,在处理过程中应严格按照规定设计进行安装,配置及防腐处理。同时接地体的间距和距离建筑物的距离也有着具体的规定,例如接地体埋设位置应距离建筑物3 米以上,环形接地体除外等等。
(4)接地干线首先要进行调值,侧位,等之后才能进行安装,铺设时首先要根据相应的设计要求开挖相应尺寸的沟槽,将扁钢侧方入内。压实填回土。为方便接引地线要注意接地干线末端露出地面部分应小于50 厘米。
4 关于接地干线的安装规定
应在接地干线穿过墙壁、楼板和地坪的地方加装钢管或其它坚固的保护套:同时进行相应的防腐措施。在跨越建筑物变形缝处,还应设补偿器或用接地线身弯成弧状代替。
4.1 接地干线支架的安装,接地干线安装时应尽量适用施工结构的要求预埋相应的支架或铁件。应根据相应的设计要求进行不同的划分和定位。在进行凿空时,洞口的大小应该保持一致。埋设支架时应进行调值,找平等。
4.2 避雷、防雷扁管的铺设
在进行铺设之前要将所需要的扁钢调直。调直之后的扁钢作为的引下线被运到各具体的安装地点,根据具体的设计要求在建筑物上处理好,之后将其下端与接地体进行焊接,也可以与断接卡进行连接,随着建筑物的逐步增高,将引下线铺设于建筑物内屋顶并出屋面一定长度,以备与避雷网连接。如需接头则应进行焊接,焊接后应敲掉药皮并刷防锈漆,最后由相关的施工人员进行验收,同时做好相应的记录。
4.3 避雷网和避雷针的安装操作
避雷网和避雷针在安装前首先要进行调直。根据相应的操作程序将避雷网和避雷针焊接在相应的位置,完成之后要进行表面处理,涂刷银粉、防锈漆等。
4.4 其他应注意的事项
检查施工实际安装是否与当初的具体设计图纸相符,检测电阻的具体情况,若出现实际电阻值较大时应进行及时的补救措施以达到设计要求等等。
结束语
通过以上内容,大家可以了解到建筑工程中电气工程中的部分的施工内容,在工程施工实践中不断的总结经验,同时注重质量。 当然不同的在实际施工过程中,不同工程,不同设计方案,电气工程施工的方式方法也是不尽相同的,我们要在实践中不断的发现问题解决问题,不断的发展前进。使得建筑电气工程施工技术更加成熟,完善。