为了降低烧结矿生产成本和提高效益,5号高炉通过调整槽下装料顺序,研究小粒度烧结矿使用量和装入方式,将小粒度烧结矿准确布入炉内指定位置,消除其对料柱透气性带来的不利影响,力求炉况稳定顺行。措施实施后,5号高炉小粒度烧结矿使用比例逐步提高,达到6.5%~8.0%,吨铁小粒度烧结矿矿耗80~120kg/t,小粒度烧结矿全部回收利用。
In order to reduce the production costs and improve the efficiency of sinter, blast furnace No. 5 adjusts the sequence of charging under the trough, studies the usage and loading method of small-size sinter, and accurately distributes the small-sized sinter into the specified position in the furnace to eliminate the burden on the material Column adverse effects of air permeability, and strive to stabilize the furnace condition. After the implementation of the measures, the use proportion of No.5 blast furnace small-grained sinter gradually increases to 6.5% -8.0%, and the consumption of small-size iron ore per tonne is 80-120kg / t. The small-size sinter is all recycled.