摘要:近年来,随着城市、城镇化的迅速扩张,建筑业如日中天的迅猛发展,一幢幢高层、超高层的建筑物拔地而起。悬挑式外挑脚手架以其构造简单,操作方便,减少钢管的投入量、节约人工费等优点,得以广泛应用,且建筑物越高越经济。因此,高层建筑结构施工中,分段悬挑搭设的扣件式钢管脚手架应用得非常普遍。由于悬挑式外脚手架荷载传递路线特殊,技术要求复杂,对人员安全、施工质量、施工速度和工程成本以及邻近建筑物和场地都有着重大的影响,因此,加强悬挑式外脚手架搭设质量控制与安全管理就显得尤为重要。
关键词:悬挑式外脚手架, 质量控制 , 安全管理
Abstract: in recent years, as cities, of the rapid expansion of the urbanization, despite the rapid development of the construction industry, acknowledged the top, super-tall buildings go up. Overhung type outside carry scaffold with its simple structure, convenient operation, reduce steel tube, saving artificial cost advantages of authors, be widely used, and building the higher the economy. Therefore, high building structure construction, segmentation cantilever of the fastener type steel tube scaffold built very common application. Because of cantilever scaffold outside the load transfer line special, technical requirements complex, to the personnel security, construction quality, construction speed and engineering cost and adjacent building and ground has had a significant impact, therefore, strengthen overhung type the scaffolding, quality control and safety management are particularly important.
Keywords: overhung type the scaffold, quality control, safety management
中图分类号:O213.1文献标识码:A 文章编号:
近年来,随着城市、城镇化的迅速扩张,建筑业如日中天的迅猛发展,一幢幢高层、超高层的建筑物拔地而起。悬挑式外挑脚手架以其构造简单,操作方便,减少钢管的投入量、节约人工费等优点,得以广泛应用,且建筑物越高越经济。因此,高层建筑结构施工中,分段悬挑搭设的扣件式钢管脚手架应用得非常普遍。由于悬挑式外脚手架荷载传递路线特殊,技术要求复杂,对人员安全、施工质量、施工速度和工程成本以及邻近建筑物和场地都有着重大的影响,因此,加强悬挑式外脚手架搭设质量控制与安全管理就显得尤为重要。
一、悬挑式挑脚手架的特点
1、悬挑式脚手架是指架体结构卸荷在附着于建筑结构的刚性悬挑梁(架)上的脚手架,用于建筑施工中的主体或装修工程的作业及其安全防护需要,每段搭设高度不得大于20m。悬挑架依附的建筑结构应是钢筋混凝土结构或钢结构,不得依附在砖混结构或石结构上。悬挑架的支承结构应为型钢制作的悬挑梁或悬挑桁架等,不得采用钢管;其节点应螺栓联结或焊接,不得采用扣件连接。与建筑结构的固定方式应经设计计算确定,并经工程设计单位认可。
2、将全高的脚手架分段搭设,不受常规落地式外脚手架搭设高度的限制,适应范围广,安全可靠。
3、工作面位于建筑物的二楼及以上任意楼层,因此不受施工场地及周边环境的制约,可以节约施工场地,加快施工进度,有利于缩短工期。
4、工字钢及其他配件属工具性质,可周转重复利用,节约成本。
二、适用范围
悬挑式脚手架的全部荷载都最终通过悬挑结构传递给建筑结构,因此,悬挑式脚手架的关键是悬挑结构,它必须具有足够的强度、刚度和稳定性,并能与建筑结构可靠连接,以将脚手架的荷载安全地传递给建筑结构。悬挑式外脚手架适用于新建或改建的现浇钢筋混凝土结构工程,在以下三种施工条件时,其优点尤为突出:
1、建筑物 0以下结构工程,基坑不能及时回填,而主体结构工程必须立即施工,否则将影响工期。
2、高层建筑主体结构四周为裙房或其他建筑物,脚手架不能直接支承在上面。
3、超高层建筑施工,脚手架搭设高度超过了落地式脚手架的容许搭设高度。
三、工艺流程
编制悬挑式外脚手架的搭设方案→ 绘制悬挑型钢的平面布置图和立面、剖面图 → 型钢的二次加工準备 →楼层钢筋环的预埋 → 放置和固定型钢 → 反拉钢丝绳 → 支承结构检查与验收 → 搭设内、外排立杆 → 搭设扫地杆 → 搭设纵向内、外排大横杆 → 设置小横杆 → 设置脚手架连墙件 → 底部硬质封闭 → 设置脚手架外立面剪刀撑 → 铺设脚手板 → 立面及水平方向的防护 → 检查验收及交付使用。
四、质量控制措施
1.技术保障措施
(1) 架子搭设完毕,用合格密目安全网铺围护于架子的外围及底部。(2) 钢管与扣件进场前应经过检查挑选(选择标准应符合规范JGJ 130-200 第3条),所用扣件在使用前应清理加油一次,扣件一定要上紧,不得松动。每个螺栓的预紧力在40N·m~65 N·m之间。^(3) 架子搭设到10m高度时由架子搭设人员进行自检;架子搭设完毕后由搭设会同施工单位、监理单位和质检单位对整个脚手架进行验收检查,验收合格后方可投入使用。(4) 该脚手架作为安全防护屏障及装修作业平台,严禁将模板支架、揽风绳、泵送混凝土和砂浆的输送管道等固定在脚手架上;脚手架严禁悬挂起重设备。
(5) 脚手架的安全性是由架子的整体性和架子结构完整性来保证的,未经允许严禁他人破坏架子结构或在架子上擅自拆除与搭设脚手架各构件。其中在脚手架使用期间,下列杆件严禁拆除:主节点处横、纵向水平杆、扫地杆、连墙件。2.质量保障措施(1) 操作人员作业前必须进行岗位技术培训与安全教育。(2) 技术人员在脚手架搭设、拆除前必须给作业人员下达安全技术交底,并传达至所有操作人员。
(3) 脚手架必须严格依据本《施工方案》进行搭设;搭设时,技术人员必须在现场监督搭设情况,保证搭设质量达到设计要求。(4) 脚手架搭设完备,依据施工组织设计与单项作业验收表对脚手架进行验收,发现不符合要求处,必须限时或立即整改。
五、安全管理措施
1、现场安全管理措施
(1)安全技术交底、三级教育、工人班前教育措施:
①开工前,工程技术负责人要将工程概况、施工方法、安全技术措施等的情况向全体职工进行详细的交底。
②公司承包部、项目部安全员及班组长对新进场工人进行安全三级教育辦理签字手续,并将工人身份证等相关证明证件收集整理成劳务队组工人花名册留项目部备案。
③分部分项工程施工前,工长要按规定向班组长进行安全技术的书面交底,并须有安全员签字认可。
④在进入每一项工程施工前,班组长须向本班组全体人员将工长的安全技术措施交底,并根据现场实际情况提出具体的要求。
⑤班组长对工人实行班前安全教育活动并作好记录。各分部分项安全技术交底,各施工员针对工程的实际情况进行有针对性的交底,由技术负责人审查签字后,协助班组长组织班组进行交底并办理签字手续。
(2)安全生产检查措施:
①项目部每周组织项目主要成员进行一次安全周检。
②项目部工长及安全员每日对施工现场巡回检查,发现隐患立即整改。
③项目部设备员、安全员和相应的操作人员每周对现场的施工临时用电、施工机具等的设备进行检查,保证其正常使用。
④对每次检查出的隐患,马上发出“隐患整改通知书”,定人、定时、定措施进行整改,并有相应的复检记录。对即发性事故及危险的隐患,应责令停工,立即整改,杜绝冒险施工。
2.安全保障措施(1) 操作人员必须持有岗位证,方可上岗。(2) 架子在搭设(拆卸)过程要做到文明作业,不得从架子上掉落工具、物品;同时必须保证自身安全,高空作业需穿防滑鞋,佩戴安全帽、安全带,未佩戴安全防护用品不得上架子。(3) 在架子上施工的各工种作业人员,应注意自身安全(尤其是在卸料平台上的工作人员);不得随意向下、向外抛、掉物品,不得随意拆除安全防护装置。(4) 雨、雪、雾及六级以上大风等天气,严禁进行脚手架搭设、拆除工作。(5) 应设安全员负责对脚手架进行经常检查和保修。
(6) 脚手架应做接地、避雷措施等,须按有关规定执行。A.在下列情况下,必须对脚手架进行检查|a.在六级以上大风和大雨后b.停用超过二个月,复工前。B.检查保修项目a.各主节点处各杆件的安装、连墙件等构造是否符合《施工方案》的要求;b.扣件螺丝是否松动;c.安全防护措施是否符合要求。(7) 在脚手架上进行电、气焊作业时,必须有防火措施和专人看护,安全员巡视检查。
(8) 脚手架临街面必须有防止坠物伤人的防护措施。
(9)工地临时用电线路的架设及脚手架接地、避雷措施等,应按有关规定执行。(10) 搭拆脚手架期间,地面应设置围栏和警戒标志,安排专人看护,严禁非操作人员入内。
六、结束语
综上所述,由于悬挑式外脚手架荷载传递路线特殊,技术要求复杂,对人员安全、施工质量、施工速度和工程成本以及邻近建筑物和场地都有着重大的影响,因此,根据项目工程的特点,加强悬挑式外脚手架搭设质量控制与安全管理是十分必要的,应该引起足够的重视。
实践证明,由广西土木建筑工程有限公司承建的广西某工程结合实际情况,综合考虑了以往的施工经验,决定1-5层采用落地式钢管脚手架,6层以上采用悬挑式钢管脚手架,为全高全封闭的扣件式双排钢管脚手架。脚手架搭设总高度 100.45米,悬挑式外脚手架设计分五段悬挑搭设,在6层、11层、16层、21层、27层各一次悬挑,悬挑高度最大为20米。工字钢梁悬挑长度达2.5米。整个施工过程中,无任何质量和安全事故发生,产生了较好的社会效益和经济效益。
关键词:悬挑式外脚手架, 质量控制 , 安全管理
Abstract: in recent years, as cities, of the rapid expansion of the urbanization, despite the rapid development of the construction industry, acknowledged the top, super-tall buildings go up. Overhung type outside carry scaffold with its simple structure, convenient operation, reduce steel tube, saving artificial cost advantages of authors, be widely used, and building the higher the economy. Therefore, high building structure construction, segmentation cantilever of the fastener type steel tube scaffold built very common application. Because of cantilever scaffold outside the load transfer line special, technical requirements complex, to the personnel security, construction quality, construction speed and engineering cost and adjacent building and ground has had a significant impact, therefore, strengthen overhung type the scaffolding, quality control and safety management are particularly important.
Keywords: overhung type the scaffold, quality control, safety management
中图分类号:O213.1文献标识码:A 文章编号:
近年来,随着城市、城镇化的迅速扩张,建筑业如日中天的迅猛发展,一幢幢高层、超高层的建筑物拔地而起。悬挑式外挑脚手架以其构造简单,操作方便,减少钢管的投入量、节约人工费等优点,得以广泛应用,且建筑物越高越经济。因此,高层建筑结构施工中,分段悬挑搭设的扣件式钢管脚手架应用得非常普遍。由于悬挑式外脚手架荷载传递路线特殊,技术要求复杂,对人员安全、施工质量、施工速度和工程成本以及邻近建筑物和场地都有着重大的影响,因此,加强悬挑式外脚手架搭设质量控制与安全管理就显得尤为重要。
一、悬挑式挑脚手架的特点
1、悬挑式脚手架是指架体结构卸荷在附着于建筑结构的刚性悬挑梁(架)上的脚手架,用于建筑施工中的主体或装修工程的作业及其安全防护需要,每段搭设高度不得大于20m。悬挑架依附的建筑结构应是钢筋混凝土结构或钢结构,不得依附在砖混结构或石结构上。悬挑架的支承结构应为型钢制作的悬挑梁或悬挑桁架等,不得采用钢管;其节点应螺栓联结或焊接,不得采用扣件连接。与建筑结构的固定方式应经设计计算确定,并经工程设计单位认可。
2、将全高的脚手架分段搭设,不受常规落地式外脚手架搭设高度的限制,适应范围广,安全可靠。
3、工作面位于建筑物的二楼及以上任意楼层,因此不受施工场地及周边环境的制约,可以节约施工场地,加快施工进度,有利于缩短工期。
4、工字钢及其他配件属工具性质,可周转重复利用,节约成本。
二、适用范围
悬挑式脚手架的全部荷载都最终通过悬挑结构传递给建筑结构,因此,悬挑式脚手架的关键是悬挑结构,它必须具有足够的强度、刚度和稳定性,并能与建筑结构可靠连接,以将脚手架的荷载安全地传递给建筑结构。悬挑式外脚手架适用于新建或改建的现浇钢筋混凝土结构工程,在以下三种施工条件时,其优点尤为突出:
1、建筑物 0以下结构工程,基坑不能及时回填,而主体结构工程必须立即施工,否则将影响工期。
2、高层建筑主体结构四周为裙房或其他建筑物,脚手架不能直接支承在上面。
3、超高层建筑施工,脚手架搭设高度超过了落地式脚手架的容许搭设高度。
三、工艺流程
编制悬挑式外脚手架的搭设方案→ 绘制悬挑型钢的平面布置图和立面、剖面图 → 型钢的二次加工準备 →楼层钢筋环的预埋 → 放置和固定型钢 → 反拉钢丝绳 → 支承结构检查与验收 → 搭设内、外排立杆 → 搭设扫地杆 → 搭设纵向内、外排大横杆 → 设置小横杆 → 设置脚手架连墙件 → 底部硬质封闭 → 设置脚手架外立面剪刀撑 → 铺设脚手板 → 立面及水平方向的防护 → 检查验收及交付使用。
四、质量控制措施
1.技术保障措施
(1) 架子搭设完毕,用合格密目安全网铺围护于架子的外围及底部。(2) 钢管与扣件进场前应经过检查挑选(选择标准应符合规范JGJ 130-200 第3条),所用扣件在使用前应清理加油一次,扣件一定要上紧,不得松动。每个螺栓的预紧力在40N·m~65 N·m之间。^(3) 架子搭设到10m高度时由架子搭设人员进行自检;架子搭设完毕后由搭设会同施工单位、监理单位和质检单位对整个脚手架进行验收检查,验收合格后方可投入使用。(4) 该脚手架作为安全防护屏障及装修作业平台,严禁将模板支架、揽风绳、泵送混凝土和砂浆的输送管道等固定在脚手架上;脚手架严禁悬挂起重设备。
(5) 脚手架的安全性是由架子的整体性和架子结构完整性来保证的,未经允许严禁他人破坏架子结构或在架子上擅自拆除与搭设脚手架各构件。其中在脚手架使用期间,下列杆件严禁拆除:主节点处横、纵向水平杆、扫地杆、连墙件。2.质量保障措施(1) 操作人员作业前必须进行岗位技术培训与安全教育。(2) 技术人员在脚手架搭设、拆除前必须给作业人员下达安全技术交底,并传达至所有操作人员。
(3) 脚手架必须严格依据本《施工方案》进行搭设;搭设时,技术人员必须在现场监督搭设情况,保证搭设质量达到设计要求。(4) 脚手架搭设完备,依据施工组织设计与单项作业验收表对脚手架进行验收,发现不符合要求处,必须限时或立即整改。
五、安全管理措施
1、现场安全管理措施
(1)安全技术交底、三级教育、工人班前教育措施:
①开工前,工程技术负责人要将工程概况、施工方法、安全技术措施等的情况向全体职工进行详细的交底。
②公司承包部、项目部安全员及班组长对新进场工人进行安全三级教育辦理签字手续,并将工人身份证等相关证明证件收集整理成劳务队组工人花名册留项目部备案。
③分部分项工程施工前,工长要按规定向班组长进行安全技术的书面交底,并须有安全员签字认可。
④在进入每一项工程施工前,班组长须向本班组全体人员将工长的安全技术措施交底,并根据现场实际情况提出具体的要求。
⑤班组长对工人实行班前安全教育活动并作好记录。各分部分项安全技术交底,各施工员针对工程的实际情况进行有针对性的交底,由技术负责人审查签字后,协助班组长组织班组进行交底并办理签字手续。
(2)安全生产检查措施:
①项目部每周组织项目主要成员进行一次安全周检。
②项目部工长及安全员每日对施工现场巡回检查,发现隐患立即整改。
③项目部设备员、安全员和相应的操作人员每周对现场的施工临时用电、施工机具等的设备进行检查,保证其正常使用。
④对每次检查出的隐患,马上发出“隐患整改通知书”,定人、定时、定措施进行整改,并有相应的复检记录。对即发性事故及危险的隐患,应责令停工,立即整改,杜绝冒险施工。
2.安全保障措施(1) 操作人员必须持有岗位证,方可上岗。(2) 架子在搭设(拆卸)过程要做到文明作业,不得从架子上掉落工具、物品;同时必须保证自身安全,高空作业需穿防滑鞋,佩戴安全帽、安全带,未佩戴安全防护用品不得上架子。(3) 在架子上施工的各工种作业人员,应注意自身安全(尤其是在卸料平台上的工作人员);不得随意向下、向外抛、掉物品,不得随意拆除安全防护装置。(4) 雨、雪、雾及六级以上大风等天气,严禁进行脚手架搭设、拆除工作。(5) 应设安全员负责对脚手架进行经常检查和保修。
(6) 脚手架应做接地、避雷措施等,须按有关规定执行。A.在下列情况下,必须对脚手架进行检查|a.在六级以上大风和大雨后b.停用超过二个月,复工前。B.检查保修项目a.各主节点处各杆件的安装、连墙件等构造是否符合《施工方案》的要求;b.扣件螺丝是否松动;c.安全防护措施是否符合要求。(7) 在脚手架上进行电、气焊作业时,必须有防火措施和专人看护,安全员巡视检查。
(8) 脚手架临街面必须有防止坠物伤人的防护措施。
(9)工地临时用电线路的架设及脚手架接地、避雷措施等,应按有关规定执行。(10) 搭拆脚手架期间,地面应设置围栏和警戒标志,安排专人看护,严禁非操作人员入内。
六、结束语
综上所述,由于悬挑式外脚手架荷载传递路线特殊,技术要求复杂,对人员安全、施工质量、施工速度和工程成本以及邻近建筑物和场地都有着重大的影响,因此,根据项目工程的特点,加强悬挑式外脚手架搭设质量控制与安全管理是十分必要的,应该引起足够的重视。
实践证明,由广西土木建筑工程有限公司承建的广西某工程结合实际情况,综合考虑了以往的施工经验,决定1-5层采用落地式钢管脚手架,6层以上采用悬挑式钢管脚手架,为全高全封闭的扣件式双排钢管脚手架。脚手架搭设总高度 100.45米,悬挑式外脚手架设计分五段悬挑搭设,在6层、11层、16层、21层、27层各一次悬挑,悬挑高度最大为20米。工字钢梁悬挑长度达2.5米。整个施工过程中,无任何质量和安全事故发生,产生了较好的社会效益和经济效益。