平禹一矿“10.19”突水灾害发生后,仅用105天就完成注浆堵水工程,治水工程的堵水率达到100%。矿井比原计划提前4个月恢复生产。最终科学、快速、高效、节约地完成了复矿工作,使淹井造成的损失减少到最低,复矿速度在国内同类淹井事故恢复中处于领先水平。水害治理方案科学合理、先进高效。制定的先盖帽封堵突水口及突水通道(即先截流,截断流向矿井的地下水),后进一步充塞止水塞加固底板(即后堵源治本)的治水思路,符合实际、科学合理。为今后类似矿井水害的治理和快速复矿提供了借鉴的典范。
Ping Yu a mine 10.19 "water inrush disaster occurred, only 105 days to complete the grouting water shutoff project, flood control project water cut rate of 100%. The mine resumed production 4 months earlier than originally planned. In the end, the complex ore recovery was completed scientifically, quickly, efficiently and economically. The loss caused by flooding was reduced to a minimum. The recovery speed was at the leading level in the recovery of similar flooded wells in China. Water control program is scientific and rational, advanced and efficient. Developed by the first block plugging water inrush and water inrush channel (ie, first cut off, cut off the groundwater flow to the mine), and then plug the water plug to further strengthen the floor (that is, after the plugging the source of the cure), in line with the actual, scientific and rational. It provides a reference model for the treatment and quick recovery of similar mine water hazards in the future.