摘要:随着社会经济及科技的不断发展,建筑理念的不断创新,特别是人们对建筑内部舒适程度的更高需求,都间接地推动了安装工程造价投入比重的提高。由于安装所涉及的专业较多,参与单位较多,交叉作业情况较多,施工工艺较复杂,导致安装工程的造价较难控制。本文分析结合影响安装工程造价的主要因素,力图阐述其解决方案及对策。
关键词:安装工程 造价影响因素 对策
Abstract: along with the social economy and the development of science and technology, building the innovative idea, especially people on the building of the internal comfort levels higher demand, indirectly, impetus installation project cost investment with the increase of the ratio. Because installation involved more professional, more participation units, crossover operation situation more, construction technology is complex, leading to the cost of installation project is hard to control. This paper analysis combined with influence the main factors of installation project cost, and tries to expound its solution and countermeasures.
Keywords: installation project cost factors countermeasures
中圖分类号: TU723.3 文献标识码:A 文章编号:
1引言
建设工程总造价由建筑安装工程费用、设备及工器具购置费用、工程建设其他费用等组成。安装工程涉及的专业较多,参与单位较多,交叉作业情况较多,施工工艺较复杂,导致安装工程的造价较难控制。
2影响安装工程造价的内在因素
2.1安装工程涉及的材料设备的品种多、品牌多、规格多
安装工程因为涉及的专业比较广,各专业所用到的材料千差万别。以给排水工程中的阀门为例,有闸阀、截止阀、蝶阀等,规格从DN15mm~DN350mm,如工程无特殊技术要求,三种阀门功能上可以等同。即使为同一种阀门种类,由于其连接方式、材质等特征的差异都会导致它们之间的价格相差较大。即使同一型号、同一品牌的产品,在不同的产地,不同的厂家生产,其价格差异就突出。
2.2新材料、新设备、新工艺层出不穷
安装工程涉及的新材料、新设备、新工艺的发展可谓日新月异。排水工程中,传统的镀锌钢管现在已经被塑料给水管、铝塑复合管、铜塑复合管、铜管甚至不锈钢管等新型材料所取代;通风空调工程中,保温空调风管系统也正以其保温节能、使用寿命长的优势逐步取代传统的镀锌铁板、无机玻璃钢管道。
2.3设计变更较多
安装工程需密切配合土建工程与装饰工程进行施工,如土建工程和装饰工程出现变化,安装工程也要随之发生相应的变更,另外安装工程也有自身的特有性质和要求,有些变化是无法提前完全表现出来,只能根据具体的施工情况来决定。图纸设计中难免会有各专业之间相互矛盾或考虑不周的现象,安装施工阶段是最容易发生变更的阶段,变更的发生对造价控制有很大影响。
2.4隐蔽工程较多
为了外观上的美感,安装工程多采用的是暗敷方式。由于安装工程中材料的价格的差异性,如果施工方以次充好、偷工减料的话,在工程竣工后单从外观上是很难看出破绽的。像这类隐蔽工程,给安装工程造价控制带来诸多麻烦。
3影响安装工程造价的外在因素
3.1设计阶段
设计阶段影响安装工程造价的外在因素为设计质量。设计阶段是建筑工程造价成本控制的关键与重点,而且是控制效果最明显的阶段。工程设计对工程造价的影响可达75%以上。但各设计单位设计人员素质参差不齐,加之管理及用人制度的诸多矛盾的影响,针对每一个工程项目,在设计人员安排上不可能做到最优组合,这直接影响建设工程的质量、造价、工期。由此可见,设计质量的好差直接影响建设费用的多少和建设工期的长短,直接决定人力、物力和财力投入的多少。合理科学的设计,可降低工程造价。
3.2招投标阶段
招投标阶段影响安装工程造价的外在因素有招标人工程量清单编制水平、现有安装定额落后于建筑领域的发展速度等。
目前我国大多数招标人不具备独立编制工程量清单的能力,一般委托具有资质的造价咨询单位编制。造价咨询单位其技术力量、造价人员思维不能跟上传统计价模式向清单计价模式的转变。造价人员在编制工程量清单时仍停留在传统预算编制层面,再加上对《建设工程工程量清单计价规范》计算规则不熟悉、缺乏必要的现场调查以及缺少施工现场的有关资料等因素,导致了编制的工程量清单可能存在子目不全、工程量计算错误问题。另外,因为安装工程图纸设计深度与施工阶段差距较大,招标人编制的工程量清单时,设备的选型、类别等存在的不明确性,会导致合同留有许多活口,不便于以后的造价控制。
4安装工程造价控制对策分析
4.1控制设计质量、建立变更严格审批程序、加强合同管理及现场监督管理
对设计单位,必须加强管理,强调按照标准设计,材料的型号、规格、数量要明确。要求设计单位严格按照设计任务进行设计,优化设计方案,细化施工设计,避免在施工过程中出现过多的失误,从而使施工图预算控制在计划投资的范围内。安装工程比较复杂,管道布置比较密集,为避免出现碰撞现象,在施工图设计完成后要进行图纸交底会审工作,听取施工单位提出的合理性建议,经济性进行确定。对于设计变更,同样进行经济技术分析,建立严格的审批程序,应针对设计变更对设计单位建立约束或者惩罚机制,督促其结合施工现场、保证设计质量。
加强合同管理,严格要求要求施工单位按图按规范施工,尽量避免不必要的签证及变更。对工程重要部位、重要环节、隐蔽部位,要求相关监理单位务必采取旁站措施,各方代表尽量到场监督施工,及时做好相关资料便于留底工作。
4.2采用多种材料设备询价方式,建立统一的造价信息平台
安装工程系统多、材料设备的种类多,严格控制材料价格是降低造价的有效手段。对于占造价比重较大或者质量对工程影响较大的材料设备采取甲供方式。对于有施工单位供应的材料设备,也可采取邀请招标、竞争性谈判、询价等方式,根据材料设备特点采用综合评议法或最低投标价法确定供应商范围,这样既可以保证材料设备质量,又能控制造价。
4.3强化招标代理机构和安装造价从业人员的业务水平
针对安装工程专业多、工艺复杂的特点,相关招标代理机构和造价从业人员要不断地总结经验,学习最新的施工工艺,了解材料设备价格的市场行情。对于具体项目,进行实地考察,分析工程特点,提前预测可能出现的各类情况,在招标文件中说明完善,避免业主方遭受不必要的经济损失。特别是相关造价从业人员,自身要加强主动学习和交流,不断提高工程量清单的编制水平。
5结语
综上所述,安装工程的造价的影响因素不仅涉及安装工程自身特点带来的内在因素,而且也与所处的行业环境带来的外在因素。因此,对于安装工程,应做到综合内在外在因素、贯穿工程建设各阶段等进行造价管理,建设单位才能有效地控制工程造价,施工单位才可以有效控制成本、提高利润。
参考文献:
[1]张艳萍.安装工程造价分析与控制[J].广东建材,2009(3)
[2]支武萍.浅谈安装工程造价控制[J].建设监理,2006(5)
关键词:安装工程 造价影响因素 对策
Abstract: along with the social economy and the development of science and technology, building the innovative idea, especially people on the building of the internal comfort levels higher demand, indirectly, impetus installation project cost investment with the increase of the ratio. Because installation involved more professional, more participation units, crossover operation situation more, construction technology is complex, leading to the cost of installation project is hard to control. This paper analysis combined with influence the main factors of installation project cost, and tries to expound its solution and countermeasures.
Keywords: installation project cost factors countermeasures
中圖分类号: TU723.3 文献标识码:A 文章编号:
1引言
建设工程总造价由建筑安装工程费用、设备及工器具购置费用、工程建设其他费用等组成。安装工程涉及的专业较多,参与单位较多,交叉作业情况较多,施工工艺较复杂,导致安装工程的造价较难控制。
2影响安装工程造价的内在因素
2.1安装工程涉及的材料设备的品种多、品牌多、规格多
安装工程因为涉及的专业比较广,各专业所用到的材料千差万别。以给排水工程中的阀门为例,有闸阀、截止阀、蝶阀等,规格从DN15mm~DN350mm,如工程无特殊技术要求,三种阀门功能上可以等同。即使为同一种阀门种类,由于其连接方式、材质等特征的差异都会导致它们之间的价格相差较大。即使同一型号、同一品牌的产品,在不同的产地,不同的厂家生产,其价格差异就突出。
2.2新材料、新设备、新工艺层出不穷
安装工程涉及的新材料、新设备、新工艺的发展可谓日新月异。排水工程中,传统的镀锌钢管现在已经被塑料给水管、铝塑复合管、铜塑复合管、铜管甚至不锈钢管等新型材料所取代;通风空调工程中,保温空调风管系统也正以其保温节能、使用寿命长的优势逐步取代传统的镀锌铁板、无机玻璃钢管道。
2.3设计变更较多
安装工程需密切配合土建工程与装饰工程进行施工,如土建工程和装饰工程出现变化,安装工程也要随之发生相应的变更,另外安装工程也有自身的特有性质和要求,有些变化是无法提前完全表现出来,只能根据具体的施工情况来决定。图纸设计中难免会有各专业之间相互矛盾或考虑不周的现象,安装施工阶段是最容易发生变更的阶段,变更的发生对造价控制有很大影响。
2.4隐蔽工程较多
为了外观上的美感,安装工程多采用的是暗敷方式。由于安装工程中材料的价格的差异性,如果施工方以次充好、偷工减料的话,在工程竣工后单从外观上是很难看出破绽的。像这类隐蔽工程,给安装工程造价控制带来诸多麻烦。
3影响安装工程造价的外在因素
3.1设计阶段
设计阶段影响安装工程造价的外在因素为设计质量。设计阶段是建筑工程造价成本控制的关键与重点,而且是控制效果最明显的阶段。工程设计对工程造价的影响可达75%以上。但各设计单位设计人员素质参差不齐,加之管理及用人制度的诸多矛盾的影响,针对每一个工程项目,在设计人员安排上不可能做到最优组合,这直接影响建设工程的质量、造价、工期。由此可见,设计质量的好差直接影响建设费用的多少和建设工期的长短,直接决定人力、物力和财力投入的多少。合理科学的设计,可降低工程造价。
3.2招投标阶段
招投标阶段影响安装工程造价的外在因素有招标人工程量清单编制水平、现有安装定额落后于建筑领域的发展速度等。
目前我国大多数招标人不具备独立编制工程量清单的能力,一般委托具有资质的造价咨询单位编制。造价咨询单位其技术力量、造价人员思维不能跟上传统计价模式向清单计价模式的转变。造价人员在编制工程量清单时仍停留在传统预算编制层面,再加上对《建设工程工程量清单计价规范》计算规则不熟悉、缺乏必要的现场调查以及缺少施工现场的有关资料等因素,导致了编制的工程量清单可能存在子目不全、工程量计算错误问题。另外,因为安装工程图纸设计深度与施工阶段差距较大,招标人编制的工程量清单时,设备的选型、类别等存在的不明确性,会导致合同留有许多活口,不便于以后的造价控制。
4安装工程造价控制对策分析
4.1控制设计质量、建立变更严格审批程序、加强合同管理及现场监督管理
对设计单位,必须加强管理,强调按照标准设计,材料的型号、规格、数量要明确。要求设计单位严格按照设计任务进行设计,优化设计方案,细化施工设计,避免在施工过程中出现过多的失误,从而使施工图预算控制在计划投资的范围内。安装工程比较复杂,管道布置比较密集,为避免出现碰撞现象,在施工图设计完成后要进行图纸交底会审工作,听取施工单位提出的合理性建议,经济性进行确定。对于设计变更,同样进行经济技术分析,建立严格的审批程序,应针对设计变更对设计单位建立约束或者惩罚机制,督促其结合施工现场、保证设计质量。
加强合同管理,严格要求要求施工单位按图按规范施工,尽量避免不必要的签证及变更。对工程重要部位、重要环节、隐蔽部位,要求相关监理单位务必采取旁站措施,各方代表尽量到场监督施工,及时做好相关资料便于留底工作。
4.2采用多种材料设备询价方式,建立统一的造价信息平台
安装工程系统多、材料设备的种类多,严格控制材料价格是降低造价的有效手段。对于占造价比重较大或者质量对工程影响较大的材料设备采取甲供方式。对于有施工单位供应的材料设备,也可采取邀请招标、竞争性谈判、询价等方式,根据材料设备特点采用综合评议法或最低投标价法确定供应商范围,这样既可以保证材料设备质量,又能控制造价。
4.3强化招标代理机构和安装造价从业人员的业务水平
针对安装工程专业多、工艺复杂的特点,相关招标代理机构和造价从业人员要不断地总结经验,学习最新的施工工艺,了解材料设备价格的市场行情。对于具体项目,进行实地考察,分析工程特点,提前预测可能出现的各类情况,在招标文件中说明完善,避免业主方遭受不必要的经济损失。特别是相关造价从业人员,自身要加强主动学习和交流,不断提高工程量清单的编制水平。
5结语
综上所述,安装工程的造价的影响因素不仅涉及安装工程自身特点带来的内在因素,而且也与所处的行业环境带来的外在因素。因此,对于安装工程,应做到综合内在外在因素、贯穿工程建设各阶段等进行造价管理,建设单位才能有效地控制工程造价,施工单位才可以有效控制成本、提高利润。