【摘 要】南水北调中线工程,渠道线路长,沿渠水文地质情况复杂,本文从渠道基础开挖、排水设施安装、粗砂垫层铺设、保温板铺设、土工膜铺设焊接、混凝土开仓前的检验、混凝土浇筑时应注意事项及养护、伸缩缝的切割等工序步骤进行了有益的探讨。
【关键词】渠道;混凝土;衬砌;施工质量;要求
North Water Transfer Project canal lining Construction should pay attention to several issues
Yuan Bin1,Wang Shuai1,Wu Wei-xing1Zou Ya-nan2
(1.Henan Provincial People's Victory Canal Authority Xinxiang Henan 453003;
2.Light Supervision Co., Ltd. Henan Branch Zhengzhou Henan 450001)
【Abstract】North Water Transfer Project, channel lines long, complicated hydrogeological along the canal, this article from the channel foundation excavation, drainage installation, laying sand bedding, insulation board laying, laying geomembrane welding, inspection before opening concrete, concrete pouring PRECAUTIONS and maintenance, process steps such as cutting expansion joints for a useful discussion.
【Key words】Construction quality;Concrete;Lining channel requirements
1. 工程概况
南水北调中线工程新乡辉县后段渠道全长24.17千米,桩号:Ⅳ91+730~Ⅳ115+900。包括(1)石门河倒虹吸标,Ⅳ91+730~Ⅳ93+280,倒虹吸1座;(2)辉县5标,Ⅳ93+280~Ⅳ101+230,公路桥4座、生产桥1座,倒虹吸2座,暗渠1座,退水闸、节制闸各一座;(3)辉县6标,Ⅳ101+230~Ⅳ108+000,公路桥7座,暗渠1座,排水渡槽3座、引水渡槽1座;(4)辉县7标,Ⅳ108+000~Ⅳ115+900,公路桥7座、生产桥2座,倒虹吸2座,排水倒虹吸1座、排水渡槽1座,分水闸、退水闸、节制闸各一座。全段分四个施工标段,有土建工程施工、机电设备安装工程、金属结构设备安装、安全监测、桥梁施工等专业。
2. 渠道设计指标及施工方法
根据设计指标要求渠道衬砌工程主要由基础开挖(含齿槽及集水沟开挖)、排水安装、粗砂垫层铺筑、保温板铺设、土工膜铺设、砼浇筑、逆止阀检查、伸缩缝切割及密封胶填筑等工序组成。
2.1 基础开挖。
即削坡,人工配合反铲进行,削坡平整,无欠挖,无虚土,无杂草杂物等,如有超挖及雨淋沟超过10cm的按86号文要求采用M5砂浆进行补坡找平处理。原始开挖面属一般隐蔽单元工程,须四方联合验收;换填面为一般单元工程,由现场监理验收。验收程序为施工单位自检合格后,报现场监理进行验收,验收合格,方可进行下道工序。
2.2 排水设施安装。
(1)沟槽开挖尺寸符合设计(400mm*400mm&500mm*500mm)要求,无超挖欠挖。
(2)沟槽底部铺设5cm(压实厚度)粗砂,洒水、整平、压实、取样检测,监理单位每600m3,抽检1组。
(3)居中铺设集水管,集水管与集水管连接,上游集水管截断30cm长钢丝,剪开管布套住下游集水管,接缝处外包长50cm土工布,绑扎牢固,集水管位置可用粗砂固定,集水管与连接逆止阀透水管、渠底预留透水管采用三通连接,三通与透水管结合部位采用土工布包裹,长度不小于30cm,捆绑结实;沟槽集水管在三通连接逆止阀处必须开口;连接逆止阀透水管及渠底预留透水管预留长度要足够,暂不连接端必须封闭避免杂物进入堵塞管道,连接逆止阀透水管必须垂直坡面,内设PVC管。
(4)集水管两侧均匀回填粗砂,洒水均匀充分,分层夯实,每层不超过15cm。
2.3 粗砂垫层铺筑。
(1)粗砂垫层铺设,人工布料整平、洒水、碾压。
(2)验收标准:手压有坚实感,平整度10mm/2m,相对密度不小于0.75。沟槽处重点检查。压实密度检测,采用灌砂法,一个单元(100m)监理取样1组,施工单位取样一个单元或每次不少于3组。
2.4 保温板铺设。
(1)从坡面底部一层接一层向上铺设,错缝、靠紧,用U型钉固定,钉顶部要夯至低于保温板顶面不小于2~3mm,以免刺破土工膜。
(2)铺设效果要求整齐、平整(相邻板面高差低于2mm)紧贴基面、无局部悬空现象,外观无缺角、断裂、尺寸不够、局部凹凸现象。
(3)连接逆止阀的透水管在保温板处的处理方法:保温板上部留不少于20cm长透水管,管内钢丝剪断抽出,管布分割成4~6份粘贴到保温板上。如图1。
2.5 土工膜铺设焊接。
(1)土工膜铺设前保证下面平整,无杂物,无尖锐硬物。
(2)土工膜铺设:自然松弛与支持面贴实、不得褶皱、悬空,上游土工膜压下游土工膜,上下土工布相反方向缝合粘贴,不得方向相同。铺设后上端牢固定位。土工膜上部固定保证预留长度75cm之外用刚钎固定,尽量减少土工膜损坏。 (3)焊接:采用双缝焊接,搭接宽度不小于10cm,外观要求轮廓明显顺直,无虚焊、漏焊、烫伤。渠坡土工膜严禁出现顺水流方向焊缝,不得出现十字接缝。手撕检查土工膜焊缝边缘处有无焊破;充气检查,压力达到0.15mpa~0.2mpa,保持2min~5min气压无下降,齿槽部位土工膜要重点检查。
(4)粘接:采用KS热熔胶粘结,搭接宽度不小于10cm,涂胶均匀,无漏涂,粘接平整,手撕检测。
(5)自检合格后质检人员和焊接人员要签字,标注桩号,报现场监理验收合格后,现场监理人员也要签字,并通知有关人员进行隐蔽工程联合验收。
2.6 浇筑前验仓。
(1)检查仓位清理是否清洁,有无杂物、灰尘、砂石、混凝土渣、积水等。
(2)查看模板周边是否顺直。
(3)通过手摸检查坡角齿槽处保温板是否与其下砂垫层贴实,有无悬空现象,若空,必须返工处理。
(4)通过脚踩检查齿槽内土工膜的松弛度,看能否与齿槽底部及两侧基面贴实,禁止悬空。
(5)检查上次浇筑边缘处土工膜有无破损。
(6)逆止阀安装采用PVC管连接,PVC管插入下部三通口内,上部插入逆止阀内,形成周围不透水连接,逆止阀配件圆盘采用KS热熔胶粘接,土工膜上层土工布去掉,土工膜上均匀涂胶粘接圆盘,不允许有空洞。拍门方向必须与渠道方向垂直且在逆止阀上必须有拍门方向标记,连接逆止阀的透水管内干净无杂物。
(7)通缝位置放置宽5~8cm,厚2~3cm保温板,固定牢固。齿槽内通缝处根据齿槽深度宽度放置2cm避孔泡沫板。
(8)仓号边缘土工膜是否用土工布、彩条布等保护以防止新土工膜污染损坏。
2.7 C20混凝土浇筑。
(1)监理及质检人员必须旁站,对首盘混凝土的塌落度、温度、含气量进行检测并对混凝土拌合物的称量结果及和易性进行检查并在记录在旁站记录中,不合格料不得运出拌合站或入仓,已入仓的应清除。
(2)浇筑过程中渠肩部位安排专人查看上部模板是否有移动,如有移动应及时停止一切机器使用,防止因外力作用发生滑坡现象。
(3)严格检查衬砌面板厚度,不够时必须调整。
(4)衬砌面边缘,机器振捣或磨光不到的部位要求辅以人工补振、抹光。收面严禁加水,撒水泥,终凝后补砂浆等现象,收面要及时,保证平整度及光洁度。
(5)逆止阀安装位置要准确,浇筑混凝土时要注意保护,避免灰浆污染,已完成衬砌面的逆止阀采用土工布覆盖保护,避免灰土堵塞逆止阀。
(6)天气炎热、干燥或风大时,仓面混凝土应设专人雾化补水,补水宜连续进行,必要时应辅以补水覆盖措施。养护要及时到位。
(7)每300m监理取试块一组。
2.8 逆止阀检查。
已衬砌混凝土面逆止阀要全部打开检查,有问题的做好记录及时处理。
2.9 伸缩缝切割。
(1)在36小时内进行切缝。
(2)渠坡切缝:纵缝均为宽1cm,深5.5~6cm;横缝分通缝和半缝,通缝宽1cm,深度为混凝土厚度(下垫宽5~8cm,宽厚2~3cm保温板),半缝宽1cm,深5.5~6cm。
(3)渠底切缝:纵缝宽1cm,深5.5~6cm;横缝分通缝和半缝,通缝宽1cm,深度为混凝土厚度(下垫宽5~8cm宽厚2~3cm保温板),半缝宽1cm,深5.5~6cm。切缝要求顺直。
2.10 密封胶施工。
(1)伸缩缝清理要求伸缩缝内的灰粉及松动混凝土余渣等杂物必须清理干净。
(2)缝内闭孔泡沫板填充密实,确保上部预留不低于2cm涂密封胶。
(3)涂胶部位必须打磨掉乳皮至坚实面,然后刷底涂,底涂完全晾干后进行密封胶灌缝。伸缩缝填充要求材料准确到位,灌缝材料饱满、表面整齐、粘结牢固、压实抹光、边缘顺直。
(4)聚流密封胶灌缝厚度不小于2cm,不足的必须返工。
3. 渠道衬砌主要工序施工前、施工过程中的要求
(1)粗砂垫层铺设前应检查渠坡、渠低高程是否符合设计要求;土渠基础若有雨淋沟及干裂缝要挖除,用水泥砂浆添实至设计高程。
(2)保温板铺设固定的U型卡不能刺破保温板,土工膜焊接界面应保持清洁不能潮湿有水。
(3)混凝土浇筑时,模板四周应振捣到位,查看仓位混凝土平整度及时覆盖、洒水养护。
(4)逆止阀要分清正反方向。
(5)切割伸缩缝时,禁止切伤土工膜。
4. 结语
通过对南水北调中线新乡辉县后段供水工程渠道衬砌的施工和总结,目前渠道衬砌从设计理念、到施工工艺都有了全面提高,我们通过每道工序的检验控制,对各工序进行全面的质量管理,建立工序质量持续改进的循环机制,再经过现场监理旁站、检验、评定,使衬砌质量上了一个新台阶,为保证南水北调中线工程顺利通水,创造了有利条件。
[文章编号]1006-7619(2013)11-20-979
[作者简介] 袁宾(1962-)男,籍贯:湖南邵阳洞口县人,职称:高级工程师,目前从事南水北调中线工程监理。
【关键词】渠道;混凝土;衬砌;施工质量;要求
North Water Transfer Project canal lining Construction should pay attention to several issues
Yuan Bin1,Wang Shuai1,Wu Wei-xing1Zou Ya-nan2
(1.Henan Provincial People's Victory Canal Authority Xinxiang Henan 453003;
2.Light Supervision Co., Ltd. Henan Branch Zhengzhou Henan 450001)
【Abstract】North Water Transfer Project, channel lines long, complicated hydrogeological along the canal, this article from the channel foundation excavation, drainage installation, laying sand bedding, insulation board laying, laying geomembrane welding, inspection before opening concrete, concrete pouring PRECAUTIONS and maintenance, process steps such as cutting expansion joints for a useful discussion.
【Key words】Construction quality;Concrete;Lining channel requirements
1. 工程概况
南水北调中线工程新乡辉县后段渠道全长24.17千米,桩号:Ⅳ91+730~Ⅳ115+900。包括(1)石门河倒虹吸标,Ⅳ91+730~Ⅳ93+280,倒虹吸1座;(2)辉县5标,Ⅳ93+280~Ⅳ101+230,公路桥4座、生产桥1座,倒虹吸2座,暗渠1座,退水闸、节制闸各一座;(3)辉县6标,Ⅳ101+230~Ⅳ108+000,公路桥7座,暗渠1座,排水渡槽3座、引水渡槽1座;(4)辉县7标,Ⅳ108+000~Ⅳ115+900,公路桥7座、生产桥2座,倒虹吸2座,排水倒虹吸1座、排水渡槽1座,分水闸、退水闸、节制闸各一座。全段分四个施工标段,有土建工程施工、机电设备安装工程、金属结构设备安装、安全监测、桥梁施工等专业。
2. 渠道设计指标及施工方法
根据设计指标要求渠道衬砌工程主要由基础开挖(含齿槽及集水沟开挖)、排水安装、粗砂垫层铺筑、保温板铺设、土工膜铺设、砼浇筑、逆止阀检查、伸缩缝切割及密封胶填筑等工序组成。
2.1 基础开挖。
即削坡,人工配合反铲进行,削坡平整,无欠挖,无虚土,无杂草杂物等,如有超挖及雨淋沟超过10cm的按86号文要求采用M5砂浆进行补坡找平处理。原始开挖面属一般隐蔽单元工程,须四方联合验收;换填面为一般单元工程,由现场监理验收。验收程序为施工单位自检合格后,报现场监理进行验收,验收合格,方可进行下道工序。
2.2 排水设施安装。
(1)沟槽开挖尺寸符合设计(400mm*400mm&500mm*500mm)要求,无超挖欠挖。
(2)沟槽底部铺设5cm(压实厚度)粗砂,洒水、整平、压实、取样检测,监理单位每600m3,抽检1组。
(3)居中铺设集水管,集水管与集水管连接,上游集水管截断30cm长钢丝,剪开管布套住下游集水管,接缝处外包长50cm土工布,绑扎牢固,集水管位置可用粗砂固定,集水管与连接逆止阀透水管、渠底预留透水管采用三通连接,三通与透水管结合部位采用土工布包裹,长度不小于30cm,捆绑结实;沟槽集水管在三通连接逆止阀处必须开口;连接逆止阀透水管及渠底预留透水管预留长度要足够,暂不连接端必须封闭避免杂物进入堵塞管道,连接逆止阀透水管必须垂直坡面,内设PVC管。
(4)集水管两侧均匀回填粗砂,洒水均匀充分,分层夯实,每层不超过15cm。
2.3 粗砂垫层铺筑。
(1)粗砂垫层铺设,人工布料整平、洒水、碾压。
(2)验收标准:手压有坚实感,平整度10mm/2m,相对密度不小于0.75。沟槽处重点检查。压实密度检测,采用灌砂法,一个单元(100m)监理取样1组,施工单位取样一个单元或每次不少于3组。
2.4 保温板铺设。
(1)从坡面底部一层接一层向上铺设,错缝、靠紧,用U型钉固定,钉顶部要夯至低于保温板顶面不小于2~3mm,以免刺破土工膜。
(2)铺设效果要求整齐、平整(相邻板面高差低于2mm)紧贴基面、无局部悬空现象,外观无缺角、断裂、尺寸不够、局部凹凸现象。
(3)连接逆止阀的透水管在保温板处的处理方法:保温板上部留不少于20cm长透水管,管内钢丝剪断抽出,管布分割成4~6份粘贴到保温板上。如图1。
2.5 土工膜铺设焊接。
(1)土工膜铺设前保证下面平整,无杂物,无尖锐硬物。
(2)土工膜铺设:自然松弛与支持面贴实、不得褶皱、悬空,上游土工膜压下游土工膜,上下土工布相反方向缝合粘贴,不得方向相同。铺设后上端牢固定位。土工膜上部固定保证预留长度75cm之外用刚钎固定,尽量减少土工膜损坏。 (3)焊接:采用双缝焊接,搭接宽度不小于10cm,外观要求轮廓明显顺直,无虚焊、漏焊、烫伤。渠坡土工膜严禁出现顺水流方向焊缝,不得出现十字接缝。手撕检查土工膜焊缝边缘处有无焊破;充气检查,压力达到0.15mpa~0.2mpa,保持2min~5min气压无下降,齿槽部位土工膜要重点检查。
(4)粘接:采用KS热熔胶粘结,搭接宽度不小于10cm,涂胶均匀,无漏涂,粘接平整,手撕检测。
(5)自检合格后质检人员和焊接人员要签字,标注桩号,报现场监理验收合格后,现场监理人员也要签字,并通知有关人员进行隐蔽工程联合验收。
2.6 浇筑前验仓。
(1)检查仓位清理是否清洁,有无杂物、灰尘、砂石、混凝土渣、积水等。
(2)查看模板周边是否顺直。
(3)通过手摸检查坡角齿槽处保温板是否与其下砂垫层贴实,有无悬空现象,若空,必须返工处理。
(4)通过脚踩检查齿槽内土工膜的松弛度,看能否与齿槽底部及两侧基面贴实,禁止悬空。
(5)检查上次浇筑边缘处土工膜有无破损。
(6)逆止阀安装采用PVC管连接,PVC管插入下部三通口内,上部插入逆止阀内,形成周围不透水连接,逆止阀配件圆盘采用KS热熔胶粘接,土工膜上层土工布去掉,土工膜上均匀涂胶粘接圆盘,不允许有空洞。拍门方向必须与渠道方向垂直且在逆止阀上必须有拍门方向标记,连接逆止阀的透水管内干净无杂物。
(7)通缝位置放置宽5~8cm,厚2~3cm保温板,固定牢固。齿槽内通缝处根据齿槽深度宽度放置2cm避孔泡沫板。
(8)仓号边缘土工膜是否用土工布、彩条布等保护以防止新土工膜污染损坏。
2.7 C20混凝土浇筑。
(1)监理及质检人员必须旁站,对首盘混凝土的塌落度、温度、含气量进行检测并对混凝土拌合物的称量结果及和易性进行检查并在记录在旁站记录中,不合格料不得运出拌合站或入仓,已入仓的应清除。
(2)浇筑过程中渠肩部位安排专人查看上部模板是否有移动,如有移动应及时停止一切机器使用,防止因外力作用发生滑坡现象。
(3)严格检查衬砌面板厚度,不够时必须调整。
(4)衬砌面边缘,机器振捣或磨光不到的部位要求辅以人工补振、抹光。收面严禁加水,撒水泥,终凝后补砂浆等现象,收面要及时,保证平整度及光洁度。
(5)逆止阀安装位置要准确,浇筑混凝土时要注意保护,避免灰浆污染,已完成衬砌面的逆止阀采用土工布覆盖保护,避免灰土堵塞逆止阀。
(6)天气炎热、干燥或风大时,仓面混凝土应设专人雾化补水,补水宜连续进行,必要时应辅以补水覆盖措施。养护要及时到位。
(7)每300m监理取试块一组。
2.8 逆止阀检查。
已衬砌混凝土面逆止阀要全部打开检查,有问题的做好记录及时处理。
2.9 伸缩缝切割。
(1)在36小时内进行切缝。
(2)渠坡切缝:纵缝均为宽1cm,深5.5~6cm;横缝分通缝和半缝,通缝宽1cm,深度为混凝土厚度(下垫宽5~8cm,宽厚2~3cm保温板),半缝宽1cm,深5.5~6cm。
(3)渠底切缝:纵缝宽1cm,深5.5~6cm;横缝分通缝和半缝,通缝宽1cm,深度为混凝土厚度(下垫宽5~8cm宽厚2~3cm保温板),半缝宽1cm,深5.5~6cm。切缝要求顺直。
2.10 密封胶施工。
(1)伸缩缝清理要求伸缩缝内的灰粉及松动混凝土余渣等杂物必须清理干净。
(2)缝内闭孔泡沫板填充密实,确保上部预留不低于2cm涂密封胶。
(3)涂胶部位必须打磨掉乳皮至坚实面,然后刷底涂,底涂完全晾干后进行密封胶灌缝。伸缩缝填充要求材料准确到位,灌缝材料饱满、表面整齐、粘结牢固、压实抹光、边缘顺直。
(4)聚流密封胶灌缝厚度不小于2cm,不足的必须返工。
3. 渠道衬砌主要工序施工前、施工过程中的要求
(1)粗砂垫层铺设前应检查渠坡、渠低高程是否符合设计要求;土渠基础若有雨淋沟及干裂缝要挖除,用水泥砂浆添实至设计高程。
(2)保温板铺设固定的U型卡不能刺破保温板,土工膜焊接界面应保持清洁不能潮湿有水。
(3)混凝土浇筑时,模板四周应振捣到位,查看仓位混凝土平整度及时覆盖、洒水养护。
(4)逆止阀要分清正反方向。
(5)切割伸缩缝时,禁止切伤土工膜。
4. 结语
通过对南水北调中线新乡辉县后段供水工程渠道衬砌的施工和总结,目前渠道衬砌从设计理念、到施工工艺都有了全面提高,我们通过每道工序的检验控制,对各工序进行全面的质量管理,建立工序质量持续改进的循环机制,再经过现场监理旁站、检验、评定,使衬砌质量上了一个新台阶,为保证南水北调中线工程顺利通水,创造了有利条件。