九月二十八日凌晨5时,市重点工程——苏州河闸桥工程闸底板安然沉放到位。苏州河闸桥工程包括主闸桥与引桥引道工程两部分,主闸桥三孔跨度全长142.67米,中跨为66.59米。中跨桥梁下悬挂门扇闸门,平时横卧于桥梁之中,遇台风高潮时关门档潮,沉放的阐底板是档潮闸重要的构筑物之一。钢筋混凝土空箱结构的阐底板长53.3米,宽10米、高3.8米,重1900余吨。该底板在芜湖市水泥船厂制作,由上海救助打捞局与港驻公司安全拖运主施工现场,一期工程的施工单
At 5:00 on September 28, the city’s key project - the sluice gate of the Suzhou Creek Sluice Gate safely settled. Suzhou River Gate Bridge project includes the main gate and the approach road approach two parts, the main gate bridge three-hole span of 142.67 meters in length, 66.59 meters in the span. Mid-span bridge hanging under the gate, usually lying in the bridge, in case of typhoon close tide, cling to the bottom plate is tide gate one of the important structures. Reinforced concrete box structure of the plate length of 53.3 meters long, 10 meters wide, 3.8 meters high, weighing 1900 tons. The floor in Wuhu Cement Shipyard produced by the Shanghai Rescue and Salvage Bureau and the Hong Kong-based company safe towing the construction site, a construction of a single