我厂为大庆房产公司生产了两台1000m~3液化石油气球型储罐和两台1000m~3低温天然气球型储罐.其对接焊缝一次合格率100%,角接焊缝磁粉检验一次合格率100%.设备投产一年多,运行完全正常.本文以一台1000m~3液化石油气球型储罐为例,介绍其预制球壳板配件的焊接.球壳板材质为16MnR,板厚40mm.制造球罐时首先要预制若干块球壳体并在球壳板上焊接好支柱、人孔、凸缘及接管等配件,然后再发往工地组装及焊接成球型储罐.在预制球壳板阶段,需要焊接的配件包括二个Dg500的人孔、10个上支柱(图1)及16个凸缘及接管(图2).为了能在车间里顺利地完成这些配件与预制球壳板的焊接,作了如下工作.
Our factory has produced two 1000m ~ 3 LPG spherical tanks and two 1000m ~ 3 low temperature natural gas spherical tanks for Daqing Real Estate Company with a pass rate of 100% for butt welds and a magnetic particle inspection for corner welded joints The rate of 100%. Equipment put into operation more than one year, run completely normal.This paper takes a 1000m ~ 3 liquefied petroleum gas ball tank as an example to introduce the welding of its prefabricated spherical shell plate parts.The spherical shell plate material is 16MnR, thickness 40mm When making the spherical tank, it is necessary to prefabricate a number of ball housings and weld the fittings such as pillars, manholes, flanges and splices to the spherical shell plate, and then send to the construction site to assemble and weld the spherical tank. In the cladding stage, the parts to be welded include two Dg500 manholes, ten upper pillars (Figure 1), and sixteen flanges and spigots (Figure 2). In order to be able to successfully complete these fittings in the workshop with prefabricated shells Plate welding, made the following work.