一、摘要:近年来,随着我国经济的发展,工程建设的速度和技術也在不断的提升,机电设备安装工程作为工程建设中的重要环节,关系着整个工程机电的安全运行和合理的使用。本文将在工程实例中,浅谈机电安装的步骤,以及针对机电设备安装过程中常见的问题进行的原理分析和给出相应对策,为同类的机电安装工程起到借鉴参考的作用。
关键词:机电安装;施工;问题处理;
Abstract:
In recent years, with the development of our national economy, the construction speed and technology has also been improved, electrical and mechanical equipment installation engineering as an important link of engineering. This paper will in practice, on the mechanical and electrical installation steps, principle analysis and give the corresponding countermeasures and common problems in mechanical and electrical equipment installation process, to the role of reference for the same kind of electromechanical installation engineering.
Keywords: mechanical and electrical installation; construction; problem;
中图分类号:TU85文献标识码:A文章编号:
二、概况:
蓬远河发源于广东省云安县大绀山,从西南向东北流经云城区的高峰镇和云安县的六都镇,在六都镇黄湾蓬远村出口流入西江。六都排涝泵站扩容工程位于蓬远河出口,主要担负蓬远河流域内云安县城区及六都镇黄湾、南乡、庆丰、六都等堤围内村庄、10.66万亩农田和0.42万亩城区的排涝任务。本工程机电设备安装的主要内容包括:五台混流泵,其中两台装机由2×1600kw扩容为2×2400kw,新装机三台,装机容量为3×2150kw,排水流量为3×17.67m3/s,电动机电压等级均为10kV,转速214.5r/min,水泵与电动机采用直联传动方式;出水闸七台固定式卷扬机安装等。
三、水泵机组安装步骤
1、施工准备:仔细研读相关技术资料,编制专项施工方案;会同指挥部、监理、厂家代表等有关部门现场验收机组设备;一次放出3台机组中心X、Y轴线,设定各安装高程,并对中心、高程标记采取保护措施。
2、底座安装:底座安装前,再次复查有关尺寸,与图纸相符;根据现场基准高程,在基础上用坐浆法均匀埋设6块δ=12mm垫板,并在垫板上相应位置放上成对楔子板,将底座吊入置于楔子板上,然后按基准中心线挂十字线,利用千斤顶、楔子板调整底座中心、高程、水平,使其符合规范及厂方要求后,交付浇捣二期砼。
3、伸缩节套管、转轮室、转轮吊入就位:底座二期砼强度达到设计要求后,将伸缩节套管先行就位,再将转轮室吊入放在一侧。转轮体在安装间按要求清扫检查并进行油压严密性渗漏试验。合格后,在套管放在支撑物(枕木),用天车吊入转轮,使其安放位置基本中心,高程比设计低10~20mm,固定牢固。
4、泵座、导叶体安装:泵座安装前,必须复查相关尺寸,与图纸相符,外表清扫干净,将泵座与导叶体组装后整体吊入置于底座上,然后按基准中心线挂十字线,利用千斤顶、楔子板调整泵座中心、高程、水平必须同时符合规范及厂方要求。
5、弯管、液控阀、出水钢管安装:吊弯管与泵座联接,并以导叶体上的下水导轴承孔为基准中心悬挂钢琴线,调整弯管使其上水导轴承孔与下水导轴承孔同心。然后以弯管的实际中心、高程安装出水管及液控阀并加固牢靠,经验收合格后,交付浇捣出水钢管的二期砼。
6、电动机机座安装:吊入电动机机座,以导叶体上的下水导轴承孔为基准中心悬挂钢琴线,调整电动机机座与下水导轴承孔同心合格后加固牢靠,经验收合格后,交付浇捣二期砼。
7、泵主轴吊入与转轮联接:
(1)在叶轮体上对称地装入两根连轴螺栓,作为吊装主轴时的导向杆。
(2)用厂家配给的专用吊具吊起主轴,对正方向后落在叶轮上
(3)在法兰止口装入后,对号入座地装入其它连轴螺栓。
这一过程中连轴螺栓及螺母应加适量的润滑剂,如水银软膏或黄油、透平油。螺栓插入有困难时,可用千斤顶缓慢推送,但不得锤击。
(4)逐步拧紧连轴螺栓,使各螺栓压紧力均匀一致而且达到设计要求。
(5)用塞尺检查结合面的贴合情况。一般说来结合面应无间隙,某些局部的合缝处可能未贴合,但0.05mm的塞尺应不能插入。
(6)将螺栓头及螺母用点焊方法固定在法兰上。连接螺栓的点焊固定须在测圆和修磨之后进行。
8、水泵转动部分的中心高程调整:在电动机吊入之前,初步调整水泵转动部分的中心符合规范要求。水泵法兰面高程比设计高程低约200mm。并固定好。
9、电动机安装:安装前核对和检查电机的零部件是否齐全,起吊工具、起吊设备是否满足吊装需要;机座标高,定子引出线的位置,温度计、电缆的引出位置都必须依据建筑物的实际情况及水力机械部分核对是否与原设计一致;上述准备工作完毕后,清扫零部件上泥垢,然后依安装的先后次序,将零部件排列好安装场地上,并在整个安装过程中都需保持零部件的清洁及不受损害,按施工方案规定程序对电动机进行吊装。
10、电动机与泵轴联接、叶轮室安装:将电机轴与泵组主轴用螺栓紧固地联结起来。电机与主轴联结好后,将分瓣的转轮室把合,按设计要求安装就位调整叶轮室与叶轮间隙再调整上导轴承瓦间隙。
11、轴线调整:泵组整体盘车,测量上、下水导摆度值,要求相对摆度值符合规范的要求,否则在法兰处加铜垫来调整。
12、伸缩节套管安装:将伸缩节套与转轮室联接安装,调整好其中心、高程后,并加固牢靠,经验收合格后,交付浇捣二期砼。
13、泵组附件安装:将分半轴承就位配合,间隙调整合格后与轴承重把合牢固。
14、水泵密封填料涵及泵组各部件安装:安装密封填料涵,调整其间隙保持均匀,填料稍微压紧即可,待试机时视漏水情况调节。在泵组调试之前按有关设计要求完善泵组其它部件的安装。
四、机电设备安装过程中必须引起重视的技术问题
螺栓联接
螺栓、螺母联接是最基本的装配,其作用分两种:一是纯机械联接,另一种是过载电流的联接。在机电安装工程中,应综合考虑机械力、电磁力、电流产生的电热对螺栓的破坏。相应的对策有:
(1)在施工方案中,对施工中的螺栓联接进行分类、相应的松紧程度等,并且应符合相关规范、设计要求;
(2)严格验收螺栓的质量,包括对产品的相关资料的收集,现场对产品的检验等;
(3)施工过程中,重视对螺栓联接的施工质量的检查。
2、设备振动
泵和电机是设备产生振动的主要部位。其中泵产生振动的原因有:转子不平衡、转子和定子相磨擦、轴承间隙大、转子与壳体同心度差等;电机则是由于转子不平衡,轴承间隙大,转子和定子气隙不均匀等原因产生振动。相应的对策有:
(1)在设备安装前,严格复合各个安装尺寸,使其符合规范、设计要求;
(2)操作过程中,注意工艺操作参数与设备的额定参数相互关系,使设备在非额定参数的运行时间尽可能短;
(3)在试运行过程中,对发现的振动问题进行记录分析,处理完前严禁再次启动设备;
(4)由于设备的运行会对各个联接、安装部位产生正常的振动,应此应在试运行结束后,对联接螺栓、安装尺寸进行再次复查。
3、超电流
通常产生超电流的原因是设备的超负荷运转。相应的对策有:
(1)严格设备验收,确认设备的相关参数符合设计要求;
(2)检查设备泵的运转是否平稳,有无异响;
4、电气设备
必须重视由电气设备故障导致的事故,这些原因有:电气设备本身的质量问题、错误安装、安装过程中异物进入设备内造成短路或者设备不工作等,相应的对策有:
(1)严格电气设备的验收管理制度,从源头上删除不具备设计质量要求的产品;
(2)安装过程中,对含有触头联接、断开动作的设备,比如隔离开关、断路器等,认真检查触头的接触动作、接触压力与接触面积;
(3)所有电气设备在安装过程中,都要防止像小螺丝、剪断铁线铁丝等的小杂物掉如设备中,从而造成阻碍设备动作、短路等事故
五、结论
机电安装工程作为系统工程,除了需要制订科学、详细的施工方案外,同时还需要从机电设备的采购源头,到安装人员的素质以及安装过程中可能出现的问题都给予足够的重视,才能确保工程顺利完成。
关键词:机电安装;施工;问题处理;
Abstract:
In recent years, with the development of our national economy, the construction speed and technology has also been improved, electrical and mechanical equipment installation engineering as an important link of engineering. This paper will in practice, on the mechanical and electrical installation steps, principle analysis and give the corresponding countermeasures and common problems in mechanical and electrical equipment installation process, to the role of reference for the same kind of electromechanical installation engineering.
Keywords: mechanical and electrical installation; construction; problem;
中图分类号:TU85文献标识码:A文章编号:
二、概况:
蓬远河发源于广东省云安县大绀山,从西南向东北流经云城区的高峰镇和云安县的六都镇,在六都镇黄湾蓬远村出口流入西江。六都排涝泵站扩容工程位于蓬远河出口,主要担负蓬远河流域内云安县城区及六都镇黄湾、南乡、庆丰、六都等堤围内村庄、10.66万亩农田和0.42万亩城区的排涝任务。本工程机电设备安装的主要内容包括:五台混流泵,其中两台装机由2×1600kw扩容为2×2400kw,新装机三台,装机容量为3×2150kw,排水流量为3×17.67m3/s,电动机电压等级均为10kV,转速214.5r/min,水泵与电动机采用直联传动方式;出水闸七台固定式卷扬机安装等。
三、水泵机组安装步骤
1、施工准备:仔细研读相关技术资料,编制专项施工方案;会同指挥部、监理、厂家代表等有关部门现场验收机组设备;一次放出3台机组中心X、Y轴线,设定各安装高程,并对中心、高程标记采取保护措施。
2、底座安装:底座安装前,再次复查有关尺寸,与图纸相符;根据现场基准高程,在基础上用坐浆法均匀埋设6块δ=12mm垫板,并在垫板上相应位置放上成对楔子板,将底座吊入置于楔子板上,然后按基准中心线挂十字线,利用千斤顶、楔子板调整底座中心、高程、水平,使其符合规范及厂方要求后,交付浇捣二期砼。
3、伸缩节套管、转轮室、转轮吊入就位:底座二期砼强度达到设计要求后,将伸缩节套管先行就位,再将转轮室吊入放在一侧。转轮体在安装间按要求清扫检查并进行油压严密性渗漏试验。合格后,在套管放在支撑物(枕木),用天车吊入转轮,使其安放位置基本中心,高程比设计低10~20mm,固定牢固。
4、泵座、导叶体安装:泵座安装前,必须复查相关尺寸,与图纸相符,外表清扫干净,将泵座与导叶体组装后整体吊入置于底座上,然后按基准中心线挂十字线,利用千斤顶、楔子板调整泵座中心、高程、水平必须同时符合规范及厂方要求。
5、弯管、液控阀、出水钢管安装:吊弯管与泵座联接,并以导叶体上的下水导轴承孔为基准中心悬挂钢琴线,调整弯管使其上水导轴承孔与下水导轴承孔同心。然后以弯管的实际中心、高程安装出水管及液控阀并加固牢靠,经验收合格后,交付浇捣出水钢管的二期砼。
6、电动机机座安装:吊入电动机机座,以导叶体上的下水导轴承孔为基准中心悬挂钢琴线,调整电动机机座与下水导轴承孔同心合格后加固牢靠,经验收合格后,交付浇捣二期砼。
7、泵主轴吊入与转轮联接:
(1)在叶轮体上对称地装入两根连轴螺栓,作为吊装主轴时的导向杆。
(2)用厂家配给的专用吊具吊起主轴,对正方向后落在叶轮上
(3)在法兰止口装入后,对号入座地装入其它连轴螺栓。
这一过程中连轴螺栓及螺母应加适量的润滑剂,如水银软膏或黄油、透平油。螺栓插入有困难时,可用千斤顶缓慢推送,但不得锤击。
(4)逐步拧紧连轴螺栓,使各螺栓压紧力均匀一致而且达到设计要求。
(5)用塞尺检查结合面的贴合情况。一般说来结合面应无间隙,某些局部的合缝处可能未贴合,但0.05mm的塞尺应不能插入。
(6)将螺栓头及螺母用点焊方法固定在法兰上。连接螺栓的点焊固定须在测圆和修磨之后进行。
8、水泵转动部分的中心高程调整:在电动机吊入之前,初步调整水泵转动部分的中心符合规范要求。水泵法兰面高程比设计高程低约200mm。并固定好。
9、电动机安装:安装前核对和检查电机的零部件是否齐全,起吊工具、起吊设备是否满足吊装需要;机座标高,定子引出线的位置,温度计、电缆的引出位置都必须依据建筑物的实际情况及水力机械部分核对是否与原设计一致;上述准备工作完毕后,清扫零部件上泥垢,然后依安装的先后次序,将零部件排列好安装场地上,并在整个安装过程中都需保持零部件的清洁及不受损害,按施工方案规定程序对电动机进行吊装。
10、电动机与泵轴联接、叶轮室安装:将电机轴与泵组主轴用螺栓紧固地联结起来。电机与主轴联结好后,将分瓣的转轮室把合,按设计要求安装就位调整叶轮室与叶轮间隙再调整上导轴承瓦间隙。
11、轴线调整:泵组整体盘车,测量上、下水导摆度值,要求相对摆度值符合规范的要求,否则在法兰处加铜垫来调整。
12、伸缩节套管安装:将伸缩节套与转轮室联接安装,调整好其中心、高程后,并加固牢靠,经验收合格后,交付浇捣二期砼。
13、泵组附件安装:将分半轴承就位配合,间隙调整合格后与轴承重把合牢固。
14、水泵密封填料涵及泵组各部件安装:安装密封填料涵,调整其间隙保持均匀,填料稍微压紧即可,待试机时视漏水情况调节。在泵组调试之前按有关设计要求完善泵组其它部件的安装。
四、机电设备安装过程中必须引起重视的技术问题
螺栓联接
螺栓、螺母联接是最基本的装配,其作用分两种:一是纯机械联接,另一种是过载电流的联接。在机电安装工程中,应综合考虑机械力、电磁力、电流产生的电热对螺栓的破坏。相应的对策有:
(1)在施工方案中,对施工中的螺栓联接进行分类、相应的松紧程度等,并且应符合相关规范、设计要求;
(2)严格验收螺栓的质量,包括对产品的相关资料的收集,现场对产品的检验等;
(3)施工过程中,重视对螺栓联接的施工质量的检查。
2、设备振动
泵和电机是设备产生振动的主要部位。其中泵产生振动的原因有:转子不平衡、转子和定子相磨擦、轴承间隙大、转子与壳体同心度差等;电机则是由于转子不平衡,轴承间隙大,转子和定子气隙不均匀等原因产生振动。相应的对策有:
(1)在设备安装前,严格复合各个安装尺寸,使其符合规范、设计要求;
(2)操作过程中,注意工艺操作参数与设备的额定参数相互关系,使设备在非额定参数的运行时间尽可能短;
(3)在试运行过程中,对发现的振动问题进行记录分析,处理完前严禁再次启动设备;
(4)由于设备的运行会对各个联接、安装部位产生正常的振动,应此应在试运行结束后,对联接螺栓、安装尺寸进行再次复查。
3、超电流
通常产生超电流的原因是设备的超负荷运转。相应的对策有:
(1)严格设备验收,确认设备的相关参数符合设计要求;
(2)检查设备泵的运转是否平稳,有无异响;
4、电气设备
必须重视由电气设备故障导致的事故,这些原因有:电气设备本身的质量问题、错误安装、安装过程中异物进入设备内造成短路或者设备不工作等,相应的对策有:
(1)严格电气设备的验收管理制度,从源头上删除不具备设计质量要求的产品;
(2)安装过程中,对含有触头联接、断开动作的设备,比如隔离开关、断路器等,认真检查触头的接触动作、接触压力与接触面积;
(3)所有电气设备在安装过程中,都要防止像小螺丝、剪断铁线铁丝等的小杂物掉如设备中,从而造成阻碍设备动作、短路等事故
五、结论
机电安装工程作为系统工程,除了需要制订科学、详细的施工方案外,同时还需要从机电设备的采购源头,到安装人员的素质以及安装过程中可能出现的问题都给予足够的重视,才能确保工程顺利完成。