经过5年多的艰苦奋斗,泗南江水电站~#3机组于2008年6月10日顺利完成试运行,正式开始商业发电,这标志着泗南江电站全部建成发电,提前20天完成董事会确定的目标。泗南江电站安装3台6.7万千瓦机组,首台机组于4月26日并网发电,到第3台机组完成72小时,历时45天,在一个半月的时间内完成3台中型水电机组的投产工作,创造了水电站建设的奇迹。泗南江电站装机容量20.1万千瓦(3×6.7万千瓦),具有年调节水库。工程于2003年10月开工建设,2005年2月截流,2007
After more than five years of hard work, Unit # 3 of the Si-Nan River Hydropower Station successfully completed trial operation on June 10, 2008 and officially started commercial power generation. This indicates that all of the power plants in Si-Nan River have been completed and power generation completed, and the target set by the Board of Directors completed 20 days in advance . Three units of 67,000 kilowatts were installed in Si’nanjiang Power Station. The first unit was connected to the grid on April 26 to complete the 72 hours of the third unit, which lasted 45 days and completed the commissioning of three medium-sized hydropower units within a month and a half Work, created a miracle of hydropower construction. The installed capacity of Sinanjiang Power Plant is 201,000 kilowatts (3 × 67,000 kilowatts), with annual regulation of reservoirs. The project started construction in October 2003, and intercepted in February 2005, 2007