【摘 要】根据电缆桥架施工作业流程特点和容易产生的质量问题,阐述电缆桥架安装质量的控制方法,做好电缆桥架安装工程优化设计,加强对电缆桥架安装工程施工重点、工艺难点进行过程控制和质量管理。
【关键词】电缆桥架;安装施工工艺;工程优化设计;材料进场检验;技术交底;施工组织方案;质量控制
【Abstract】 In consideration of process features and possible quality problems during cable supporting system installation ,the paper illustrates the quality control measures for cable supporting system installation by providing engineering optimization design for cable supporting system installation work and highlighting the process control and management of key points and difficulties of cable supporting system installation work.
【Key words】 Cable supporting system Installation process Engineering optimization design Inspection of approached material Pre-job operation training Technical disclosure Construction scheme Quality control.
工业厂房和高层楼建筑的电缆桥架大多安装在厂房内和高层建筑的竖井内,工程量大面广,工艺复杂,安装工程的质量直接影响区域供配电安全和用电设备正常使用。本文以提高电缆桥架安装工程质量为目的,根据施工作业流程特点和容易产生的质量问题,阐述电缆桥架安装质量的控制方法。
1电缆桥架的组成
电缆桥架由支架、吊架、托架支撑、线槽或梯架直线段、弯通非直线段组合而成,是具有连续性的刚性结构系统。按电缆种类分为电力电缆桥架、控制电缆桥架和弱电电缆桥架,可按电缆用途分别架设桥架。
2电缆桥架安装工程优化设计
电缆桥架安装工程应根据施工图、电缆数量、桥架所在建筑空间和电气管线的设置,进行优化设计。
2.1绘制桥架系统安装路径平面图
工程安装优化设计须与土建、暖通、消防、给排水及有关专业配合,检查桥架系统路径有无与其他设备、管线交叉或重叠,与监理或建设单位及设计单位协商,确定最佳电缆桥架安装方案和布局,绘出桥架系统路径平面布置图、剖面图、局部空间图,并编写桥架安装说明书。
2.2确定桥架规格及附件
选择桥架宽度和高度可根据敷设电缆条数、电缆直径;计算电缆的截面积。应该注意到,由于电缆条数较多,有时施工图选用的桥架规格偏小,电缆在桥架内的填充率余量空间不足,影响电缆敷设,因此,有必要复核桥架横截面积,确定电缆桥架型号规格。各种弯通和附件规格,应符合桥架系统工程安装布置条件,并与线槽或梯架相配套。
支架、吊架、托架支撑规格选择,应按线槽和梯架规格配置,根据荷载和工程环境条件,确定其型号、规格和数量。
3桥架及其附件材料进场检验
进入施工现场的桥架及其附件材料、构配件、设备,必须符合设计文件、合同要求和相关技术标准规定,进场时应有桥架产品合格证、技术说明书和包装箱清单,应按桥架安装工程优化设计细节确定的桥架线槽、梯架、弯通、附件规格进行核对清点,防止桥架安装时遗漏缺件。安装前由施工承包单位按规定向监理机构和建设单位提交准备在工程上采用的桥架材料、构配件、设备报审表,经监理工程师核对桥架材料产品数量、品种和板材厚度符合规定,检查和检验产品,确认质量合格,才能进行工程安装。凡是产品质量不符合要求、没有产品出厂合格证及检验不合格,不得使用,必须限期退场。如果对产品质量有异议,必要时可以取样检验。
4桥架安装技术交底
桥架安装作业技术交底是施工组织方案的具体化,由专业技术人员负责向施工人员和具体施工操作者进行技术交底。交底的内容围绕桥架安装工程特点,工程量,工序复杂程度,使用的材料、构配件、设备,施工环境,对桥架安装工艺流程、施工方法、施工作业标准要求,采用的施工机具设备,人员配备和是施工安全防护措施进行具体总体部署。
4.1桥架安装工艺流程
桥架定位划线→预埋钢固件→支、吊、托架安装→桥架安装→保护接地联结安装。
根据安装工艺流程,以施工图和优化设计方案确定桥架的起始到终端位置,分析沿图标定的桥架走向和安装工序,重视在安装过程中容易出现的质量问题、施工难点,提出相应的要求,制定预控方案,采用措施预防质量问题的产生。
4.2施工人员资质和岗前操作培训
根据安装工序需要,有计划地配备施工人员,特殊岗位人员必须经过有关部门上岗操作培训,获取资格证书,持证上岗,施工人员资质及其技能应满足施工作业的要求。
4.3施工机具的配备
制订机具设备检验计划,检定进场机具和设备符合标准要求,功能和参数满足施工工艺要求。
5桥架安裝施工工艺和质量控制
5.1桥架定位划线
根据施工图和优化设计方案。沿桥架走向找好水平、垂直、弯通与地面的相对标高和墙壁的相对距离,弹出相应线条或划线,均匀的等距离划出支架、吊架和托架位置。
5.2预埋钢固件、支吊架制作和安装
预埋钢固件的尺寸应大于120mm×80mm×6mm,锚固件圆钢不小于Ф10mm,与土建结构配合做好固件、锚件的预留预埋。自制的支架、吊架采用钢材合格品,符合设计规定型号规格,钢材(或角钢)应平直,加工制作合理,焊接牢固,焊缝均匀平整,焊接长度符合规范,无明显变形。支架、吊架安装固定可靠,水平标高一致,并做好除锈防腐。
5.3桥架(梯架)安装
电缆桥架水平敷设时,应高出地面2.2m以上,桥架顶部距屋顶板不应小于0.3m支撑跨距一般1.5m~3m;考虑桥架的荷载重量、桥架挠度,跨距应适当缩小。桥架在竖井中垂直敷设时,固定点的距离不宜大于2m。桥架弯曲半径不大于300mm时,在与直线段连接处距弯曲段300~600mm设置一个支架或吊架;当弯曲半径大于300mm时,弯曲段中间设一个支撑。桥架安装必须考虑满足电缆敷设弯曲最小半径的规范要求。直线段钢制电缆桥架长度超过30m,应设有伸缩节;电缆桥架跨越建筑物变形缝处设置补偿装置。敷设在竖井内和穿越不同防火区的桥架按设计要求采取防火隔堵措施。
5.4桥架保护接地联结
敷设电缆桥架应做良好接地,每两节之间的链接处都应做接地,接地跨接应用截面积不下小于4m㎡的多股铜芯线跨接地线。桥架敷设施工完成,自检合格,报监理机构检验,验收合格才能进行电缆敷设。
6结束语
电缆桥架工程安装应根据应根据工程环境条件,以施工图和有关规范为依据,优化桥架安装设计方案,同时选择技术力量强的施工队伍。搞好桥架安装作业技术交底,并对施工过程中投入人力、材料、机具和采取的工艺进行质量控制及管理,使电缆桥架安装工程达到电气工程整体功能预期目的。
参考文献:
[1]建设工程质量控制[M]北京:化学工业出版社,2011.
[2]GB50303-2002建筑电气工程施工质量验收规范[s].北京:中国计划出版社,2004.
[3]GB50300-2001建筑工程质量施工验收统一标准[s].北京:中国建筑工业出版社,2002.
[4]04D701-3电缆桥架线槽安装规范工艺施工图集[M].北京:中国建筑标准设计研究院,2004
【关键词】电缆桥架;安装施工工艺;工程优化设计;材料进场检验;技术交底;施工组织方案;质量控制
【Abstract】 In consideration of process features and possible quality problems during cable supporting system installation ,the paper illustrates the quality control measures for cable supporting system installation by providing engineering optimization design for cable supporting system installation work and highlighting the process control and management of key points and difficulties of cable supporting system installation work.
【Key words】 Cable supporting system Installation process Engineering optimization design Inspection of approached material Pre-job operation training Technical disclosure Construction scheme Quality control.
工业厂房和高层楼建筑的电缆桥架大多安装在厂房内和高层建筑的竖井内,工程量大面广,工艺复杂,安装工程的质量直接影响区域供配电安全和用电设备正常使用。本文以提高电缆桥架安装工程质量为目的,根据施工作业流程特点和容易产生的质量问题,阐述电缆桥架安装质量的控制方法。
1电缆桥架的组成
电缆桥架由支架、吊架、托架支撑、线槽或梯架直线段、弯通非直线段组合而成,是具有连续性的刚性结构系统。按电缆种类分为电力电缆桥架、控制电缆桥架和弱电电缆桥架,可按电缆用途分别架设桥架。
2电缆桥架安装工程优化设计
电缆桥架安装工程应根据施工图、电缆数量、桥架所在建筑空间和电气管线的设置,进行优化设计。
2.1绘制桥架系统安装路径平面图
工程安装优化设计须与土建、暖通、消防、给排水及有关专业配合,检查桥架系统路径有无与其他设备、管线交叉或重叠,与监理或建设单位及设计单位协商,确定最佳电缆桥架安装方案和布局,绘出桥架系统路径平面布置图、剖面图、局部空间图,并编写桥架安装说明书。
2.2确定桥架规格及附件
选择桥架宽度和高度可根据敷设电缆条数、电缆直径;计算电缆的截面积。应该注意到,由于电缆条数较多,有时施工图选用的桥架规格偏小,电缆在桥架内的填充率余量空间不足,影响电缆敷设,因此,有必要复核桥架横截面积,确定电缆桥架型号规格。各种弯通和附件规格,应符合桥架系统工程安装布置条件,并与线槽或梯架相配套。
支架、吊架、托架支撑规格选择,应按线槽和梯架规格配置,根据荷载和工程环境条件,确定其型号、规格和数量。
3桥架及其附件材料进场检验
进入施工现场的桥架及其附件材料、构配件、设备,必须符合设计文件、合同要求和相关技术标准规定,进场时应有桥架产品合格证、技术说明书和包装箱清单,应按桥架安装工程优化设计细节确定的桥架线槽、梯架、弯通、附件规格进行核对清点,防止桥架安装时遗漏缺件。安装前由施工承包单位按规定向监理机构和建设单位提交准备在工程上采用的桥架材料、构配件、设备报审表,经监理工程师核对桥架材料产品数量、品种和板材厚度符合规定,检查和检验产品,确认质量合格,才能进行工程安装。凡是产品质量不符合要求、没有产品出厂合格证及检验不合格,不得使用,必须限期退场。如果对产品质量有异议,必要时可以取样检验。
4桥架安装技术交底
桥架安装作业技术交底是施工组织方案的具体化,由专业技术人员负责向施工人员和具体施工操作者进行技术交底。交底的内容围绕桥架安装工程特点,工程量,工序复杂程度,使用的材料、构配件、设备,施工环境,对桥架安装工艺流程、施工方法、施工作业标准要求,采用的施工机具设备,人员配备和是施工安全防护措施进行具体总体部署。
4.1桥架安装工艺流程
桥架定位划线→预埋钢固件→支、吊、托架安装→桥架安装→保护接地联结安装。
根据安装工艺流程,以施工图和优化设计方案确定桥架的起始到终端位置,分析沿图标定的桥架走向和安装工序,重视在安装过程中容易出现的质量问题、施工难点,提出相应的要求,制定预控方案,采用措施预防质量问题的产生。
4.2施工人员资质和岗前操作培训
根据安装工序需要,有计划地配备施工人员,特殊岗位人员必须经过有关部门上岗操作培训,获取资格证书,持证上岗,施工人员资质及其技能应满足施工作业的要求。
4.3施工机具的配备
制订机具设备检验计划,检定进场机具和设备符合标准要求,功能和参数满足施工工艺要求。
5桥架安裝施工工艺和质量控制
5.1桥架定位划线
根据施工图和优化设计方案。沿桥架走向找好水平、垂直、弯通与地面的相对标高和墙壁的相对距离,弹出相应线条或划线,均匀的等距离划出支架、吊架和托架位置。
5.2预埋钢固件、支吊架制作和安装
预埋钢固件的尺寸应大于120mm×80mm×6mm,锚固件圆钢不小于Ф10mm,与土建结构配合做好固件、锚件的预留预埋。自制的支架、吊架采用钢材合格品,符合设计规定型号规格,钢材(或角钢)应平直,加工制作合理,焊接牢固,焊缝均匀平整,焊接长度符合规范,无明显变形。支架、吊架安装固定可靠,水平标高一致,并做好除锈防腐。
5.3桥架(梯架)安装
电缆桥架水平敷设时,应高出地面2.2m以上,桥架顶部距屋顶板不应小于0.3m支撑跨距一般1.5m~3m;考虑桥架的荷载重量、桥架挠度,跨距应适当缩小。桥架在竖井中垂直敷设时,固定点的距离不宜大于2m。桥架弯曲半径不大于300mm时,在与直线段连接处距弯曲段300~600mm设置一个支架或吊架;当弯曲半径大于300mm时,弯曲段中间设一个支撑。桥架安装必须考虑满足电缆敷设弯曲最小半径的规范要求。直线段钢制电缆桥架长度超过30m,应设有伸缩节;电缆桥架跨越建筑物变形缝处设置补偿装置。敷设在竖井内和穿越不同防火区的桥架按设计要求采取防火隔堵措施。
5.4桥架保护接地联结
敷设电缆桥架应做良好接地,每两节之间的链接处都应做接地,接地跨接应用截面积不下小于4m㎡的多股铜芯线跨接地线。桥架敷设施工完成,自检合格,报监理机构检验,验收合格才能进行电缆敷设。
6结束语
电缆桥架工程安装应根据应根据工程环境条件,以施工图和有关规范为依据,优化桥架安装设计方案,同时选择技术力量强的施工队伍。搞好桥架安装作业技术交底,并对施工过程中投入人力、材料、机具和采取的工艺进行质量控制及管理,使电缆桥架安装工程达到电气工程整体功能预期目的。