为使J4000型沥青混合料搅拌设备发挥最佳效能,缩短拆装和转场运输周期,实现科学维护和安全运行,满足道路施工需要,我们根据该设备技术特性,并结合实践经验,总结出其拆装和转场运输要点,仅供同行参考。1.拆装和运输原则该设备拆装工作实行分工负责制,制定并执行相关方案,以确保拆卸、吊装、运输和安装全过程安全无事故。同时执行先小后大、先易后难、先地面后高空、先外围后主机,以及谁拆卸、谁
In order to optimize the performance of J4000 asphalt mixing plant, shorten the disassembly and transit transportation cycle, achieve scientific maintenance and safe operation, and meet the needs of road construction, based on the technical characteristics of the equipment and based on practical experience, we conclude that Disassembly and transition transportation points, only for peer reference. 1. Disassembly and Transportation Principles The equipment disassembly work division of responsibility system responsible for the development and implementation of relevant programs to ensure that the demolition, lifting, transportation and installation of the entire process of safe and accident-free. At the same time the implementation of the first small, big easy after the first difficult after the first high ground after the first outside the host after the demolition, and who disassemble, who