1994年10月25日,也就是沙捞越壳牌(SSB)公司首次从BYG-A/D35海上油田泵输原油上岸17天后,又开始首次在DCS控制下外输天然气。这是SSB采用的第一套由费希尔-罗斯蒙特(Fisher-Rosemount)公司提供和安装的海上DCS系统。BYG-A/D35工程配备着包括智能仪表和一整套的罗斯蒙特系统-3
On October 25, 1994, the first time that Sahrawean Shell (SSB) landed 17 days after pumping crude oil from the BYG-A / D35 offshore oilfield, it began to export natural gas for the first time under DCS control. This is the first DCS at sea to be provided and installed by Fisher-Rosemount. The BYG-A / D35 project is equipped with smart meters and a complete suite of Rosemount systems - 3