【案情】2009年9月20日,原告许根付与被告胜远公司签订了联合探矿合同书,由原告许根付为被告胜远公司坐落于内蒙古自治区商都县南炭窑的煤矿进行探矿。合同履行期限自2009年9月15日起至2011年4月26日止。2014年8月18日,被告为原告出具结账说明一份,实欠原告工程款330万元,押金待核对手续后一并结算。原、被告约定的合同履行地为内蒙古自治区察哈尔右翼后旗。被告胜远公司在答辩期间没有提出管辖权异议,并到庭
【Case】 On September 20, 2009, the plaintiff Xu Genfu signed a joint prospecting contract with the defendant Shengyuan Company, and the plaintiff Xu Genfu was the defendant, Shengyuan Company, located in the coal mine in Nanchao kiln, Shangdu County, Inner Mongolia Autonomous Region. The contract performance period from September 15, 2009 until April 26, 2011 only. On August 18, 2014, the defendant issued a statement of account settlement for the plaintiff, and actually owed the plaintiff an engineering payment of 3.3 million yuan. The deposit was settled after the check-up procedure was completed. The contractual performance between the original and defendant was carried out in Chahar Right Banner at Inner Mongolia Autonomous Region. The defendant Shengyuan Company did not submit any objection to jurisdiction during the defense and came to court