福建三明钢铁厂第二炼钢车间2×15吨氧气顶吹转炉附设的烟气净化、煤气回收、污泥处理及余热利用装置系统,是由马鞍山设计院与我厂三结合15吨转炉筹建组、省安装公司、省建一公司等单位设计施工的。15吨转炉于1978年元旦投产,79年对该转炉附设的烟气净化、煤气回收装置系统的工艺设备进行检验、试车,摸索有关工艺参数,并对原设计的工艺设备进行必要的改革,和进行生产准备。于79年4月中旬一次投产成功。到目前已运行二年整,基本上实现了安全运行、正常回收,被冶金部列为全国钢铁企业推广二十六条生产经验之一。
Fujian Sanming Iron and Steel Plant, the second steelmaking plant 2 × 15 tons oxygen top blown converter attached to the flue gas purification, gas recovery, sludge treatment and waste heat utilization system, is designed by the Ma On Shan Institute and I plant three 15-ton converter preparation group , The provincial installation company, the provincial construction of a company and other units design and construction. 15 tons of converter put into operation on New Year’s Day in 1978, 79 years of the converter attached to the flue gas purification, gas recovery unit of the process equipment to test, test, explore the relevant process parameters, and the original design of process equipment necessary reform, and Production preparation. In mid-April 79 a production was successful. Up till now, it has been running for two years and has basically realized the safe operation and normal recovery. It was listed by the Ministry of Metallurgical Industry as one of the 26 production experiences promoted by the national steel enterprises.