一、工程概况烟台港三期工程是国家“九五”重点建设项目,也是亚行贷款国际招标的项目,其建设现模为:新建1.5万t级及3万t级集装箱泊位各一个,1 5万t级及2万t级杂货泊位各一个,设计年吞吐能力255万t(其中:集装箱175万t,24万标准箱)及相应的供水、供电、道路堆场等生产、生活辅助设施,项目概算总投资为13.68亿元,建设工期4年。疏浚工程包括港池、航道两部分,挖泥总量为1197万m3。港地面积约40万m2,航道长约4km,宽130m。
First, the project overview Yantai Port Phase III project is the national “Ninth Five-Year” key construction projects, but also the ADB international bidding project, the construction of the current model is: the new 15,000 t-class and 30,000 t-class container berth each one , 150,000 t class and 20000 t class garages each with a design annual throughput of 2.55 million tons (including: 1.75 million t of containers and 240,000 TEUs) and corresponding production and living of water supply, power supply and road yard, etc. Auxiliary facilities, the project total estimated investment of 1.368 billion yuan, the construction period of 4 years. Dredging projects including the port pool, waterway two parts, the total amount of dredging 11970000 m3. Hong Kong covers an area of about 400,000 m2, the channel length of about 4km, width 130m.