摘要:城市自来水厂在建设过程中容易出现混凝土结构表面产生裂缝、麻面、蜂窝、管道内部积水、管道位置偏移、管道密封性不足等质量缺陷。通常这些情况的出现反映出施工单位在一些关键工序的施工中没有严格落实各项技术措施。本文从技术层面分析了自来水厂建设中容易出现的质量缺陷,并提出了应对措施。
关键词:城市自来水厂;项目建设;常见问题;组织管理
Abstract: During the construction of urban water plants, quality defects such as cracks on the surface of the concrete structure, pockmarked surfaces, honeycombs, water accumulation in the pipeline, deviation of the pipeline position, and insufficient pipeline sealing are prone to occur. Usually the appearance of these situations reflects that the construction unit has not strictly implemented various technical measures in the construction of some key procedures. This article analyzes the quality defects that easily occur in the construction of water plants from the technical level, and proposes countermeasures.
Keywords: urban waterworks; project construction; common problems; organization and management
引言
城市自來水厂在建设中要安装大量的大型设备、阀门、管道、法兰以及等其他类型的附属装置,但是有可能因为技术措施落实不到位而产生基础的不均匀沉降、回填土沉降、管道泄漏、管线位置偏移等质量问题。施工单位应该充分掌握造成此类问题的原因,并在其基础上制定应对措施。
1自来水厂建造工艺及常见问题
1.1 建造工艺
自来水厂在建设过程中可分为水源地选择、取水泵房施工、净水厂施工以及配套管线系统施工几个主要环节。取水泵房主要是借助大功率的水泵从水源地向净水泵房供水。净水厂的絮凝池要借助回转式隔板或者折板式隔板来实现水中胶体和悬浮颗粒物的清除,然后将经过絮凝的水体输送到砂率池中,借助石英砂进一步过滤水中的悬浮颗粒物。紧接着再利用提升泵房将经过过滤的水体转移至臭氧池和活性炭池,以实现杀菌的目的。活性炭池自上而下设置了一定厚度的活性炭、石英砂、承托层。经过以上的净化作用之后水体进入清水池,分流给不同的用户。
1.2 常见问题
1.2.1 混凝土工程质量差
自来水厂在建设过程中要大量使用钢筋混凝土材料来完成厂区内各种设备基础、道路以及建筑物的施工,并且这些结构物的体积都比较大。此类施工中容易出现的质量问题包括大体积混凝土结构表面产生裂缝、麻面、蜂窝等。裂缝的形成通常与浇筑过程中的温度控制、振捣操作以及后期的养护措施有关。而蜂窝和麻面之类的问题则与模板搭建、振捣的充分性高度相关。
1.2.2管道积水或位置偏差
市政自来水厂管道在施工中一般要根据预先设计的线路完成地质勘察、地下结构勘察以及线路复核,但是在实际敷设管道的过程中有可能因为某些突发的因素而造成原有的施工路线不能满足实际需求,例如,地下水上涌、与其他工程项目产生冲突等。另外,施工图纸上的各项设计要求必须经过工程测绘来完成施工放样,再由施工班组将管道敷设在对应的位置上,测量放样精度不足或者施工走样等情况也是造成管道在水平面上产生偏差的常见原因。管道出现积水的问题与管道在立面上的坡度设计具有密切地联系,因为规避地下建筑物而导致其立面坡度设计不合理是常见的原因。
1.2.3 管道密封性不符合要求
市政自来水厂的管网系统呈现出覆盖范围大、长度大、接口多、受地质条件影响大的特点,管道基础部分主要起到承载管道的作用,在基础夯实不到位、降水、管道荷载等多种因素共同作用下导致其出现不均匀的沉降,并且还有可能受到膨胀土地质以及软土地基等不良因素的干扰,而管道失去有效的承载之后就会在某些局部产生较大的应力,进而形成泄漏。施工所用的管道在装卸、运输、吊装以及组对的过程中有可能因为操作不当而产生变形或者破损之类的问题,这也是造成其密封性不足的潜在因素。管道之间的连接点以及闭水段的端头封堵处也是常见的泄漏点之一,主要原因在于密封处理不到位[1]。
1.2.4 检查井施工质量差
检查井作为一种辅助性的检修设施,在整个工程项目的作用容易被忽视,基础夯实不到位、回填施工不规范容易导致检查井在后续的使用中出现比较明显的变形和下沉,很多检查井的井盖采用了容易破裂的水泥盖板,并且其主体部分的规范性较差,垂直度、整齐度以及整体外观都给人产生不良的感受。造成井体变形和观感差的主要原因是施工人员砌筑井体时没有控制好垂直度、井口大小、井体高度以及井体的中心位置。
2 施工组织管理措施
2.1 加强工程勘察以及测绘放样
第一,在前期的工程勘察阶段要对施工线路上已经存在的地下建筑物、地下电缆、地下光缆、市政管线形成全面地掌握,并且和相关政府部门提前沟通其他工程项目施工的信息,在各方的配合之下设计出合理的工艺流程线路,做好立面坡度的控制。防止因为前期勘察不到位而造成后期出现较大的改动,这样也会影响整体的布局。第二,施工单位的测绘和放样效果具有不可忽视的作用,因而在自来水厂建设作业中必须采用先进的工程测绘设备来提高放样的精度,并且此类放样的范围较大,应使用放样桩做好相关线路的标记[3]。 2.2 重视施工材料的质量控制
第一,钢筋混凝土材料的质量控制。自来水厂中的絮凝池、沉淀池、砂滤池等结构主要使用钢筋混凝土材料来建造。施工前要检查水泥、粗细集料、钢筋等主要原材料的质量是否满足工程要求。水泥可采用抽样检查的方法来确认其体积稳定性、凝结时间、坍落度、和易性等关键的性能指标。钢筋材料也要通过抽样检查的方法来确认其抗拉轻度、直径、重量、冷弯强度等。粗集料必须将含泥量控制在不超过1%,否则配置成的混凝土材料在强度、凝结效果、裂缝控制方面都会出现一定的问题。
第二,管材质量控制。管道进场之后要先去检查其表面是否存在下凹、管口是否存在变形或者缺损等情况,在确认外观质量合格的情况下再去检查质量合格证、生产许可证、管道规格、材质、壁厚、接口以及附件的质量。
2.3 管线施工要点
第一, 提升管道接口密封性的措施。在接口连接之前先将管道内部的异物、工机具以及接口处的管壁清理干净,如果接口填料采用水泥,为了确保其配比不受影响,还应将管口处润湿。还有些管道接口填料使用带有一定油性的材料,此时要确保填料密封部位达到足够的干燥程度,然后在其表面涂刷一層冷底子油[4]。
第二, 管道支墩施工。市政自来水厂管道中的三通、弯管以及变径处是整个管道系统中质量大、应力大的部位,因而一般需在这些部位设置专门的支墩,以达到加固支撑的效果。施工过程中需评估支墩设置部位的土质结构和承载力是否满足设计要求,如果原状土层的强度不足,则应采用分层夯实的方法来全面提高其强度等级。
第三, 井室砌筑。这一部分施工活动涉及混凝土工程、砌体结构施工、钢筋绑扎、基坑夯实、排水等多道工序,虽然整体的工程量不算大,但技术上的要求相对较高。有些施工人员在原材料检查、混凝土配置、钢筋绑扎、井体高程控制、井室几何尺寸控制中没有严格落实设计要求和工程规范。因此,施工单位在井室砌筑施工中必须加强测量精度控制以及各类工程材料的控制。
2.4 钢筋混凝土结构施工要点
城市自来水厂的混凝土施工主要集中在厂区道路、办公楼、水处理工艺中的各种净化池,如絮凝池、沉淀池、臭氧接触池、滤池等,其难点在于各种池体的浇筑。自来水厂的池体体积较大,池壁的浇筑质量不易控制。施工单位可采用承载力强、密封性佳的钢模板作为池体混凝土浇筑的模板材料,并且在浇筑混凝土的过程中要通过在适当的位置设置伸缩缝来预防混凝土结构变形开裂,封模之前将预制好的钢筋设置并固定在预先设计好的位置上,采用泵送混凝土浇筑的方案分层浇筑池壁,每层的厚度控制在30cm之内,并且在每一层浇筑完成之后立即采用振捣棒将新浇筑的混凝土振捣密实,振捣棒要穿过上层混凝土,并插入下层混凝土中,防止上下层的界面部位融合不到位。另外,自来水厂的各种池体在施工过程中还必须加强底部和池壁的防水抗渗性能。在防水施工中重点做好面层处理以及防腐防水涂料的涂刷,表1展示了水池防水施工的主要流程。
3 结束语
混凝土结构表面产生裂缝、麻面、蜂窝、立面坡度不合理、泄漏、积水、管道位置发生偏移、以及密封效果不佳等是城市自来水厂施工的常见质量缺陷。这些问题通常与工程勘察和放样、基础夯实效果、回填土施工、管道连接、管道密封等关键工序的施工质量具有直接的关系,施工单位应该强化关键工序的施工控制。
参考文献:
[1]邢雯雯.城市自来水厂项目建设中常见问题与管理措施[J].地产, 2019(21):104-105.
[2]崔逸诚.水厂建设施工中常见问题及组织管理探讨[J].产城(上半月),2020, 000(001):P.1-1.
[3]郑国东.室外自来水管道施工组织与管理分析[J].居业,2017, 04(No.111):98+100.
[4]孙玲.室外自来水管道施工实践与组织管理策略分析[J].科学与财富,2018, 000(031):151.
(作者单位:南通水务集团有限公司)
关键词:城市自来水厂;项目建设;常见问题;组织管理
Abstract: During the construction of urban water plants, quality defects such as cracks on the surface of the concrete structure, pockmarked surfaces, honeycombs, water accumulation in the pipeline, deviation of the pipeline position, and insufficient pipeline sealing are prone to occur. Usually the appearance of these situations reflects that the construction unit has not strictly implemented various technical measures in the construction of some key procedures. This article analyzes the quality defects that easily occur in the construction of water plants from the technical level, and proposes countermeasures.
Keywords: urban waterworks; project construction; common problems; organization and management
引言
城市自來水厂在建设中要安装大量的大型设备、阀门、管道、法兰以及等其他类型的附属装置,但是有可能因为技术措施落实不到位而产生基础的不均匀沉降、回填土沉降、管道泄漏、管线位置偏移等质量问题。施工单位应该充分掌握造成此类问题的原因,并在其基础上制定应对措施。
1自来水厂建造工艺及常见问题
1.1 建造工艺
自来水厂在建设过程中可分为水源地选择、取水泵房施工、净水厂施工以及配套管线系统施工几个主要环节。取水泵房主要是借助大功率的水泵从水源地向净水泵房供水。净水厂的絮凝池要借助回转式隔板或者折板式隔板来实现水中胶体和悬浮颗粒物的清除,然后将经过絮凝的水体输送到砂率池中,借助石英砂进一步过滤水中的悬浮颗粒物。紧接着再利用提升泵房将经过过滤的水体转移至臭氧池和活性炭池,以实现杀菌的目的。活性炭池自上而下设置了一定厚度的活性炭、石英砂、承托层。经过以上的净化作用之后水体进入清水池,分流给不同的用户。
1.2 常见问题
1.2.1 混凝土工程质量差
自来水厂在建设过程中要大量使用钢筋混凝土材料来完成厂区内各种设备基础、道路以及建筑物的施工,并且这些结构物的体积都比较大。此类施工中容易出现的质量问题包括大体积混凝土结构表面产生裂缝、麻面、蜂窝等。裂缝的形成通常与浇筑过程中的温度控制、振捣操作以及后期的养护措施有关。而蜂窝和麻面之类的问题则与模板搭建、振捣的充分性高度相关。
1.2.2管道积水或位置偏差
市政自来水厂管道在施工中一般要根据预先设计的线路完成地质勘察、地下结构勘察以及线路复核,但是在实际敷设管道的过程中有可能因为某些突发的因素而造成原有的施工路线不能满足实际需求,例如,地下水上涌、与其他工程项目产生冲突等。另外,施工图纸上的各项设计要求必须经过工程测绘来完成施工放样,再由施工班组将管道敷设在对应的位置上,测量放样精度不足或者施工走样等情况也是造成管道在水平面上产生偏差的常见原因。管道出现积水的问题与管道在立面上的坡度设计具有密切地联系,因为规避地下建筑物而导致其立面坡度设计不合理是常见的原因。
1.2.3 管道密封性不符合要求
市政自来水厂的管网系统呈现出覆盖范围大、长度大、接口多、受地质条件影响大的特点,管道基础部分主要起到承载管道的作用,在基础夯实不到位、降水、管道荷载等多种因素共同作用下导致其出现不均匀的沉降,并且还有可能受到膨胀土地质以及软土地基等不良因素的干扰,而管道失去有效的承载之后就会在某些局部产生较大的应力,进而形成泄漏。施工所用的管道在装卸、运输、吊装以及组对的过程中有可能因为操作不当而产生变形或者破损之类的问题,这也是造成其密封性不足的潜在因素。管道之间的连接点以及闭水段的端头封堵处也是常见的泄漏点之一,主要原因在于密封处理不到位[1]。
1.2.4 检查井施工质量差
检查井作为一种辅助性的检修设施,在整个工程项目的作用容易被忽视,基础夯实不到位、回填施工不规范容易导致检查井在后续的使用中出现比较明显的变形和下沉,很多检查井的井盖采用了容易破裂的水泥盖板,并且其主体部分的规范性较差,垂直度、整齐度以及整体外观都给人产生不良的感受。造成井体变形和观感差的主要原因是施工人员砌筑井体时没有控制好垂直度、井口大小、井体高度以及井体的中心位置。
2 施工组织管理措施
2.1 加强工程勘察以及测绘放样
第一,在前期的工程勘察阶段要对施工线路上已经存在的地下建筑物、地下电缆、地下光缆、市政管线形成全面地掌握,并且和相关政府部门提前沟通其他工程项目施工的信息,在各方的配合之下设计出合理的工艺流程线路,做好立面坡度的控制。防止因为前期勘察不到位而造成后期出现较大的改动,这样也会影响整体的布局。第二,施工单位的测绘和放样效果具有不可忽视的作用,因而在自来水厂建设作业中必须采用先进的工程测绘设备来提高放样的精度,并且此类放样的范围较大,应使用放样桩做好相关线路的标记[3]。 2.2 重视施工材料的质量控制
第一,钢筋混凝土材料的质量控制。自来水厂中的絮凝池、沉淀池、砂滤池等结构主要使用钢筋混凝土材料来建造。施工前要检查水泥、粗细集料、钢筋等主要原材料的质量是否满足工程要求。水泥可采用抽样检查的方法来确认其体积稳定性、凝结时间、坍落度、和易性等关键的性能指标。钢筋材料也要通过抽样检查的方法来确认其抗拉轻度、直径、重量、冷弯强度等。粗集料必须将含泥量控制在不超过1%,否则配置成的混凝土材料在强度、凝结效果、裂缝控制方面都会出现一定的问题。
第二,管材质量控制。管道进场之后要先去检查其表面是否存在下凹、管口是否存在变形或者缺损等情况,在确认外观质量合格的情况下再去检查质量合格证、生产许可证、管道规格、材质、壁厚、接口以及附件的质量。
2.3 管线施工要点
第一, 提升管道接口密封性的措施。在接口连接之前先将管道内部的异物、工机具以及接口处的管壁清理干净,如果接口填料采用水泥,为了确保其配比不受影响,还应将管口处润湿。还有些管道接口填料使用带有一定油性的材料,此时要确保填料密封部位达到足够的干燥程度,然后在其表面涂刷一層冷底子油[4]。
第二, 管道支墩施工。市政自来水厂管道中的三通、弯管以及变径处是整个管道系统中质量大、应力大的部位,因而一般需在这些部位设置专门的支墩,以达到加固支撑的效果。施工过程中需评估支墩设置部位的土质结构和承载力是否满足设计要求,如果原状土层的强度不足,则应采用分层夯实的方法来全面提高其强度等级。
第三, 井室砌筑。这一部分施工活动涉及混凝土工程、砌体结构施工、钢筋绑扎、基坑夯实、排水等多道工序,虽然整体的工程量不算大,但技术上的要求相对较高。有些施工人员在原材料检查、混凝土配置、钢筋绑扎、井体高程控制、井室几何尺寸控制中没有严格落实设计要求和工程规范。因此,施工单位在井室砌筑施工中必须加强测量精度控制以及各类工程材料的控制。
2.4 钢筋混凝土结构施工要点
城市自来水厂的混凝土施工主要集中在厂区道路、办公楼、水处理工艺中的各种净化池,如絮凝池、沉淀池、臭氧接触池、滤池等,其难点在于各种池体的浇筑。自来水厂的池体体积较大,池壁的浇筑质量不易控制。施工单位可采用承载力强、密封性佳的钢模板作为池体混凝土浇筑的模板材料,并且在浇筑混凝土的过程中要通过在适当的位置设置伸缩缝来预防混凝土结构变形开裂,封模之前将预制好的钢筋设置并固定在预先设计好的位置上,采用泵送混凝土浇筑的方案分层浇筑池壁,每层的厚度控制在30cm之内,并且在每一层浇筑完成之后立即采用振捣棒将新浇筑的混凝土振捣密实,振捣棒要穿过上层混凝土,并插入下层混凝土中,防止上下层的界面部位融合不到位。另外,自来水厂的各种池体在施工过程中还必须加强底部和池壁的防水抗渗性能。在防水施工中重点做好面层处理以及防腐防水涂料的涂刷,表1展示了水池防水施工的主要流程。
3 结束语
混凝土结构表面产生裂缝、麻面、蜂窝、立面坡度不合理、泄漏、积水、管道位置发生偏移、以及密封效果不佳等是城市自来水厂施工的常见质量缺陷。这些问题通常与工程勘察和放样、基础夯实效果、回填土施工、管道连接、管道密封等关键工序的施工质量具有直接的关系,施工单位应该强化关键工序的施工控制。
参考文献:
[1]邢雯雯.城市自来水厂项目建设中常见问题与管理措施[J].地产, 2019(21):104-105.
[2]崔逸诚.水厂建设施工中常见问题及组织管理探讨[J].产城(上半月),2020, 000(001):P.1-1.
[3]郑国东.室外自来水管道施工组织与管理分析[J].居业,2017, 04(No.111):98+100.
[4]孙玲.室外自来水管道施工实践与组织管理策略分析[J].科学与财富,2018, 000(031):151.
(作者单位:南通水务集团有限公司)