文章结合工程实例,分析了左右端分别与溢流坝和右岸土堤相接,中部布置有右岸灌溉取水口特殊地形,考虑了面板钢筋及侧模采用简易坡面运输台车运至施工工作面,钢筋加工根据具体施工情况,考虑在钢筋加工厂进行加工,以加快施工进度。面板填缝材料及防渗盖板施工,根据现场实际情况,与面板混凝土施工穿插进行。
Based on the engineering examples, the left and right ends of the dam are connected with the overflow dam and the right bank of the earth bank, respectively, and the special terrain of the right bank irrigation and water intake is arranged in the middle. Considering that the panel steel bar and the side mold are transported to the working face with a simple slope transport trolley According to the specific construction conditions, steel processing plant to consider processing, in order to speed up the construction progress. Panel caulking materials and impermeable cover construction, according to the actual situation on the scene, and panel concrete construction interspersed.