通过对6~#平炉在大修前编制网络计划及不断综合平衡和优化,大修过程中对关键路线不断控制和协调,取得了缩短工期、提高大修的组织管理水平及节约人力财力的良好效果。指出实施网络计划的重点应放在确定关键路线、狠抓关键路线上的关键工序进度上;要利用有效时差合理调配各类资源,保证关键工序对资源的需求,以确保整个网络计划的总进度。同时,各施工单位按网
Through the preparation of the network plan before the overhaul and continuous comprehensive balance and optimization of the 6## open hearth, the critical route has been continuously controlled and coordinated during the overhaul process, which has achieved a good effect of shortening the construction period, improving the organization and management level of the overhaul, and saving manpower and financial resources. It is pointed out that the key to the implementation of the network plan should be to determine the key routes and pay close attention to the progress of key processes on the key routes; to use reasonable time differences to rationally allocate all types of resources and to ensure the demand for resources from key processes, so as to ensure the overall progress of the entire network plan. . At the same time, each construction unit