论文部分内容阅读
摘 要:针对新疆焦煤集团2130煤矿24221综采工作面煤层倾角大、地质条件复杂,在回采过程中遇多次大面积冒顶、片帮事故。结合实际情况,通过现场处理,解决了大倾角综采工作面冒顶、片帮事故,总结了大倾角综采工作面过复杂地质构造带的方法。
关键词:大倾角;地质构造;综采
Inclined fully mechanized mining face passing the geological technical summary
LI Zeng-feng
(Xinjiang Coking Coal (Group) Co., Ltd. 2130 Coal Mine)
Abstract: Xinjiang Coking Coal Group 2130 Coal Mine 24221 mechanized mining face seam inclination and complex geological conditions in the mining process in the case of a number of large area of ??roof collapse, spalling accident. The actual situation, and through on-site processing, to solve a big dip fully mechanized coal face roof fall, spalling accident, summed up the inclined fully mechanized mining face is too complex geological structure with the method.
Key words: inclination angle; geological structure; mechanized mining
1前言
新疆焦煤集团2130煤矿24221工作面自回采的一年中,回风巷推进195m,运输巷推进210m,平均推进200m,工作面伪斜度为19°,该工作面地质构造复杂,煤层倾角大,工作面倾角最大时期为48°,平均倾角43°,顶板起伏变化大,两巷道超前支护难以支护,工作面支架时常因顶板起伏不能有效接顶和支架压死,24221工作面自开采以来已遇两次较大断层,2009年11月遇第一次断层,断距达3m,工作面冒顶,造成工作面支架倒架,工作面溜槽大幅度弯曲,耗时2个月将工作面调整正常;2010年2月,遇第二次断层,因吸取上次处理断层经验,提前采取措施进行背顶,调整工作面耗时一个月,其后,多次遇石梁结构、顶板下沉、顶板抬高等情况,为工作面整体推进带来较大影响,现将处理措施总结如下。
2顶板特征
2.1顶板岩层组合
直接顶为0.28米的砂砾岩硅质胶结坚硬。老顶为8.4米厚粗砂岩和8.5米厚中砂岩组成,老顶厚度16.9米,粗砂岩灰白色,坚硬,以石英为主,裂隙较发育,中砂岩灰白色以石英为主,层理不明显。直接底为0.35米厚黑色炭质泥岩块状薄层状。老底为2.11米厚粉砂岩,致密块状下部粗砂岩层理清晰,节理发育易碎。顶底板标高起伏变化较大,岩体凸出较为频繁。
2.2工作面推进及两巷顶板状况
工作面自2009年5月底开采以来,两巷平均推进30m时,采空区顶板未垮落,采取补孔强制放顶措施后,再次向前推进5m,于2009年9月顶板初次垮落,垮落块度较为合适。
3存在的问题
24221工作面于2009年11月在推进过程中初遇断层结构,当回风顺槽推进64m,运输顺槽推进81m,工作面伪斜度为14°后初遇断层。断层产状为逆断层,位置位于工作面62#~73#支架处,延工作面走向长无法预计,延煤层倾向长约为17m,随工作面推进,于12月10日观测,断层结构发生变化,当日运输顺槽推进68m,回风顺槽推进92m。工作面伪斜度为18°,运输顺槽推进超前回风顺槽26.5m。断层延煤层倾向由74#支架延伸至23#支架处,倾向长约80m。此断层断距最大处(42#支架左右)达2.8m,最小处(73#支架左右)约为60cm,其他处平均断距为80cm。断层伪斜度为21°。工作面33#支架附近顶板出现裂隙水,涌水量较大,此段附近煤帮因受裂隙水冲刷,跨帮现象十分严重,煤壁上帮与下帮水平距达2.5m左右。23#~33#支架顶部出现大面积冒顶现象。12月8日,工作面支架发生倒架,倒架支架为30#~33#四架支架,其上下段支架挤架、咬架情况严重。34#~39#支架处刮板机溜槽呈弧形向支架方向弯曲,弯曲量最大处约为30cm,整个工作面无法推进。
4处理措施
4.1对支架处理
对工作面倒架支架采取单体住配合液压缸进行扶架,在扶架过程中,为保证有足够的空间对倒架支架扶架,需调整支架架间间隙。从上方68#支架处向下调整支架间隙,调至34#支架处,由下方16#支架处向上调整支架间隙,调至30#支架处。
4.2对煤壁处理
对断层不能进行机采地段,使用炮采,对43#~33#支架处煤帮进行扩帮处理,帮上打锚杆和锚索配合锚网进行护帮,顶板打锚索配合经纬网对顶板进行支护,以防止跨帮、冒顶现象加剧。
4.3对顶板处理
23#~33#支架处冒顶区域采取做假顶的办法对顶板进行支护。在冒落处架设木垛,木垛高度与支架顶梁上平面一致,在木垛与支架构成平面上设置人员作业平台。人员在平台上对该处顶板使用锚索配合经纬网进行支护,锚索长度10m,深入顶板长度为5m,裸露锚索贴顶板位置使用十字梁配合锁具进行紧固。将裸露锚索尾部穿过5m~6m的工字钢一端和中间,另一端固定在支架顶梁上部。在其上铺设木垛,对冒顶顶板进行支护,使其形成假顶,保证支架能够在接顶、带压情况下进行拉、移架操作。
4.4对采高的控制
在过地质构造过程时,地质变化原因使得采高沿顶底板开采时变化起伏较大,难以控制。为保证刮板机溜槽平直,采煤机能够正常通行,这要求工作面55#支架以上段采高不得大于2.8m,55#支架以下段采高不得大于2.4m,55#支架附近支架平稳过渡。支架向前推进时,遇顶、底板下沉的情况时,应保证刮板机溜槽和支架的平直,沿原顶板平面向前推进。采煤机割煤时,沿原顶板位置割煤,底板下沉时,将底煤留住,严禁割底煤。底煤因倾角较大难以保留时,使用防倒缸配合链条或钢丝绳对刮板机溜槽进行提升作业,刮板机溜槽被提起后,在每一节刮板机溜槽的下面垫规格为500×200×200mm的枕木,要求垫完后的溜槽平直。溜槽垫平直后,将其支架的抬底缸伸出,使支架底座抬起与溜槽保持相同的高度,在底座下垫相同规格的枕木。由于工作面倾角较大,枕木垫完后,在推、移架时,枕木容易下滑,为防止其下滑,在枕木下侧底板打钢钎。在规定的采高内,遇见半岩壁的煤帮时,对夹矸层和岩石松软的伪顶地段使用采煤机截割,对坚硬顶板处采用每2m进行一次打眼放炮的方式进行处理,保证采高控制在规定的范围内。在拉、移架操作过程中,保证梁端距为50cm以内,刮板机溜槽到前立柱的距离控制在60cm范围内。
4.5对飞矸的防护
过此段地质构造时,片帮、空顶造成大量的飞矸,人员进入工作面作业存在重大的安全隐患,因此必须加强对飞矸的管理工作。要求人员进入机道作业时,严格的执行敲帮问顶工作,在作业地点上方架设全断面挡矸墙,并设专人做看护工作。每班安排人员对支架处的防飞矸网进行检修,更换损坏的防飞矸网,保证工作面的防飞矸网为两层。
5后期推进计划
因24221工作面为推进困难阶段,因此计划2个月内推进30m,在后期推进的30m范围内观测两巷道地质情况来看:从回风巷顶板情况推断,工作面中部至回风巷在推进近30m段内会遇3处石梁(岩体凸出),此三处石梁从回风揭露处判断其走向长都在80cm左右,错差在50~80cm左右,倾向沿工作面倾向略大于工作面伪斜度(工作面伪斜19°),过此地质构造时,因运输巷底板抬高,工作面再调整采高,使用采煤机提刀,因此不采用卧底方案,初期方案采用降采高,当降采高不能满足推进需求时,采用爆破挑顶方案。预计每个石梁需耗费4个班次调整、推进,共计12个班次。该工作会对工作面推进量带来较大的影响。从运输巷顶板及底板观察,转载机处于爬坡状态,坡度较大,底板标高落差为5m,运输巷距工作面30m段顶板起伏较大,距工作面3m处有一石梁,此石梁走向长1.5m,延伸至工作面10#支架处,对工作面提刀带来很大影响,此段石梁必须采用爆破挑顶的办法进行处理,预计耗费5个生产班次。距工作面6m处,顶板冒高,实测落差在70~80cm,长度为20m,此段有7组棚架,棚架间距为1.2~1.3m,共计9m,此20m段上帮高度较高,平高度为4.5m,最大高度为5m,下帮高度为2.5m左右。支护较困难,需锚索配合工字钢对此段顶板进行特殊支护,推进至棚架段时,需对棚架进行拆除,观测棚架段发现,棚架段煤帮已跨落,跨落高度为2.3m左右,跨落深度预计在4m左右,推进至此时,可能导致支架不接顶现象,需在推进过程中在棚架段及其前后共20m范围内做假顶辅助支架进行推进作业。
参考文献:
(1)杨相海,井巷工程,中国矿业大学出版社,2008:143-144
(2)伍卫国,急倾斜综采工作面过逆断层技术实践,教育科学博览,2011(5)。
作者简介:
李增峰(1980-),男,汉族,新疆塔城人,在读工硕,助理工程师,2005年毕业于新疆大学采矿工程专业,现任新疆焦煤(集团)有限责任公司2130煤矿副总工程师。
关键词:大倾角;地质构造;综采
Inclined fully mechanized mining face passing the geological technical summary
LI Zeng-feng
(Xinjiang Coking Coal (Group) Co., Ltd. 2130 Coal Mine)
Abstract: Xinjiang Coking Coal Group 2130 Coal Mine 24221 mechanized mining face seam inclination and complex geological conditions in the mining process in the case of a number of large area of ??roof collapse, spalling accident. The actual situation, and through on-site processing, to solve a big dip fully mechanized coal face roof fall, spalling accident, summed up the inclined fully mechanized mining face is too complex geological structure with the method.
Key words: inclination angle; geological structure; mechanized mining
1前言
新疆焦煤集团2130煤矿24221工作面自回采的一年中,回风巷推进195m,运输巷推进210m,平均推进200m,工作面伪斜度为19°,该工作面地质构造复杂,煤层倾角大,工作面倾角最大时期为48°,平均倾角43°,顶板起伏变化大,两巷道超前支护难以支护,工作面支架时常因顶板起伏不能有效接顶和支架压死,24221工作面自开采以来已遇两次较大断层,2009年11月遇第一次断层,断距达3m,工作面冒顶,造成工作面支架倒架,工作面溜槽大幅度弯曲,耗时2个月将工作面调整正常;2010年2月,遇第二次断层,因吸取上次处理断层经验,提前采取措施进行背顶,调整工作面耗时一个月,其后,多次遇石梁结构、顶板下沉、顶板抬高等情况,为工作面整体推进带来较大影响,现将处理措施总结如下。
2顶板特征
2.1顶板岩层组合
直接顶为0.28米的砂砾岩硅质胶结坚硬。老顶为8.4米厚粗砂岩和8.5米厚中砂岩组成,老顶厚度16.9米,粗砂岩灰白色,坚硬,以石英为主,裂隙较发育,中砂岩灰白色以石英为主,层理不明显。直接底为0.35米厚黑色炭质泥岩块状薄层状。老底为2.11米厚粉砂岩,致密块状下部粗砂岩层理清晰,节理发育易碎。顶底板标高起伏变化较大,岩体凸出较为频繁。
2.2工作面推进及两巷顶板状况
工作面自2009年5月底开采以来,两巷平均推进30m时,采空区顶板未垮落,采取补孔强制放顶措施后,再次向前推进5m,于2009年9月顶板初次垮落,垮落块度较为合适。
3存在的问题
24221工作面于2009年11月在推进过程中初遇断层结构,当回风顺槽推进64m,运输顺槽推进81m,工作面伪斜度为14°后初遇断层。断层产状为逆断层,位置位于工作面62#~73#支架处,延工作面走向长无法预计,延煤层倾向长约为17m,随工作面推进,于12月10日观测,断层结构发生变化,当日运输顺槽推进68m,回风顺槽推进92m。工作面伪斜度为18°,运输顺槽推进超前回风顺槽26.5m。断层延煤层倾向由74#支架延伸至23#支架处,倾向长约80m。此断层断距最大处(42#支架左右)达2.8m,最小处(73#支架左右)约为60cm,其他处平均断距为80cm。断层伪斜度为21°。工作面33#支架附近顶板出现裂隙水,涌水量较大,此段附近煤帮因受裂隙水冲刷,跨帮现象十分严重,煤壁上帮与下帮水平距达2.5m左右。23#~33#支架顶部出现大面积冒顶现象。12月8日,工作面支架发生倒架,倒架支架为30#~33#四架支架,其上下段支架挤架、咬架情况严重。34#~39#支架处刮板机溜槽呈弧形向支架方向弯曲,弯曲量最大处约为30cm,整个工作面无法推进。
4处理措施
4.1对支架处理
对工作面倒架支架采取单体住配合液压缸进行扶架,在扶架过程中,为保证有足够的空间对倒架支架扶架,需调整支架架间间隙。从上方68#支架处向下调整支架间隙,调至34#支架处,由下方16#支架处向上调整支架间隙,调至30#支架处。
4.2对煤壁处理
对断层不能进行机采地段,使用炮采,对43#~33#支架处煤帮进行扩帮处理,帮上打锚杆和锚索配合锚网进行护帮,顶板打锚索配合经纬网对顶板进行支护,以防止跨帮、冒顶现象加剧。
4.3对顶板处理
23#~33#支架处冒顶区域采取做假顶的办法对顶板进行支护。在冒落处架设木垛,木垛高度与支架顶梁上平面一致,在木垛与支架构成平面上设置人员作业平台。人员在平台上对该处顶板使用锚索配合经纬网进行支护,锚索长度10m,深入顶板长度为5m,裸露锚索贴顶板位置使用十字梁配合锁具进行紧固。将裸露锚索尾部穿过5m~6m的工字钢一端和中间,另一端固定在支架顶梁上部。在其上铺设木垛,对冒顶顶板进行支护,使其形成假顶,保证支架能够在接顶、带压情况下进行拉、移架操作。
4.4对采高的控制
在过地质构造过程时,地质变化原因使得采高沿顶底板开采时变化起伏较大,难以控制。为保证刮板机溜槽平直,采煤机能够正常通行,这要求工作面55#支架以上段采高不得大于2.8m,55#支架以下段采高不得大于2.4m,55#支架附近支架平稳过渡。支架向前推进时,遇顶、底板下沉的情况时,应保证刮板机溜槽和支架的平直,沿原顶板平面向前推进。采煤机割煤时,沿原顶板位置割煤,底板下沉时,将底煤留住,严禁割底煤。底煤因倾角较大难以保留时,使用防倒缸配合链条或钢丝绳对刮板机溜槽进行提升作业,刮板机溜槽被提起后,在每一节刮板机溜槽的下面垫规格为500×200×200mm的枕木,要求垫完后的溜槽平直。溜槽垫平直后,将其支架的抬底缸伸出,使支架底座抬起与溜槽保持相同的高度,在底座下垫相同规格的枕木。由于工作面倾角较大,枕木垫完后,在推、移架时,枕木容易下滑,为防止其下滑,在枕木下侧底板打钢钎。在规定的采高内,遇见半岩壁的煤帮时,对夹矸层和岩石松软的伪顶地段使用采煤机截割,对坚硬顶板处采用每2m进行一次打眼放炮的方式进行处理,保证采高控制在规定的范围内。在拉、移架操作过程中,保证梁端距为50cm以内,刮板机溜槽到前立柱的距离控制在60cm范围内。
4.5对飞矸的防护
过此段地质构造时,片帮、空顶造成大量的飞矸,人员进入工作面作业存在重大的安全隐患,因此必须加强对飞矸的管理工作。要求人员进入机道作业时,严格的执行敲帮问顶工作,在作业地点上方架设全断面挡矸墙,并设专人做看护工作。每班安排人员对支架处的防飞矸网进行检修,更换损坏的防飞矸网,保证工作面的防飞矸网为两层。
5后期推进计划
因24221工作面为推进困难阶段,因此计划2个月内推进30m,在后期推进的30m范围内观测两巷道地质情况来看:从回风巷顶板情况推断,工作面中部至回风巷在推进近30m段内会遇3处石梁(岩体凸出),此三处石梁从回风揭露处判断其走向长都在80cm左右,错差在50~80cm左右,倾向沿工作面倾向略大于工作面伪斜度(工作面伪斜19°),过此地质构造时,因运输巷底板抬高,工作面再调整采高,使用采煤机提刀,因此不采用卧底方案,初期方案采用降采高,当降采高不能满足推进需求时,采用爆破挑顶方案。预计每个石梁需耗费4个班次调整、推进,共计12个班次。该工作会对工作面推进量带来较大的影响。从运输巷顶板及底板观察,转载机处于爬坡状态,坡度较大,底板标高落差为5m,运输巷距工作面30m段顶板起伏较大,距工作面3m处有一石梁,此石梁走向长1.5m,延伸至工作面10#支架处,对工作面提刀带来很大影响,此段石梁必须采用爆破挑顶的办法进行处理,预计耗费5个生产班次。距工作面6m处,顶板冒高,实测落差在70~80cm,长度为20m,此段有7组棚架,棚架间距为1.2~1.3m,共计9m,此20m段上帮高度较高,平高度为4.5m,最大高度为5m,下帮高度为2.5m左右。支护较困难,需锚索配合工字钢对此段顶板进行特殊支护,推进至棚架段时,需对棚架进行拆除,观测棚架段发现,棚架段煤帮已跨落,跨落高度为2.3m左右,跨落深度预计在4m左右,推进至此时,可能导致支架不接顶现象,需在推进过程中在棚架段及其前后共20m范围内做假顶辅助支架进行推进作业。
参考文献:
(1)杨相海,井巷工程,中国矿业大学出版社,2008:143-144
(2)伍卫国,急倾斜综采工作面过逆断层技术实践,教育科学博览,2011(5)。
作者简介:
李增峰(1980-),男,汉族,新疆塔城人,在读工硕,助理工程师,2005年毕业于新疆大学采矿工程专业,现任新疆焦煤(集团)有限责任公司2130煤矿副总工程师。