针对预控顶分段充填法在深部开采存在的预控顶巷道掘进工序繁杂、顶板易受爆破震动影响等缺点,本文提出垂直孔与水平孔协同回采的机械化分段充填采矿法(协同回采分段充填法).该方法通过改变顶板支护工序的顺序,将预控顶变为后压顶,能够有效地解决顶板围岩稳定性问题.进而对协同回采分段充填法进行优化研究:一方面,通过SURPAC到ANSYS的模型转换技术,进行采场稳定性数值分析,获得最佳的结构参数;另一方面,通过分区出矿分区支护的方式,解决两帮支护不到位和出矿效率低的问题.将该方法应用于新城金矿V#矿体开采,结果显示顶板岩移量显著减小,且各项经济技术指标均得到改善,实现了高应力条件下厚大矿体的安全高效开采.
In view of the shortcomings of pre-control top section filling method in the deep mining, such as pre-control top roadway heading process complicated, roof vulnerable to blasting vibration and other shortcomings, this paper presents a mechanized sub-fill mining method of vertical hole and horizontal hole collaborative mining Which can effectively solve the stability problem of the surrounding rock of the roof by changing the order of roof supporting process and changing the pre-control roof into the post-pressure roof, and then optimize the sectional filling method of the collaborative mining: on the one hand , Through SURPAC to ANSYS model conversion technology, numerical analysis of stope stability, to obtain the best structural parameters; the other hand, by partitioning out of mine partition support way to solve the two support is not in place and the mine efficiency Low.The application of this method to the mining of V # orebody in Xincheng Gold Mine showed that the displacement of roof slate was significantly reduced and various economic and technical indicators were improved and the safety of thick orebody under high stress condition was realized Efficient mining.