截至10月底,我市主城排水工程累计完成投资 29.17亿元。昨日,记者从市国资委获悉,今年我市主城排水工程已完成总投资的79.07%,其中一期工程完成24.49亿元,二期工程完成4.68亿元; 主城供水旧管网改造工程已完工38条,在建24 条,累计完成投资8 837万元。市国资委有关人士表示,唐家沱二期污水、污泥土建工程已完成总工程量的90%,对无法到货的关键设备已启动应急方案,确保年底通水。鸡冠石
As of the end of October, the city’s main city drainage project has completed a total investment of 2.917 billion yuan. Yesterday, the reporter learned from the Municipal SASAC that this year the city’s main city drainage project has completed 79.07% of the total investment, of which a total of 2.449 billion yuan was completed in Phase I project and 468 million yuan was completed in Phase II project. Completed 38, under construction 24, a total investment of 83700000 yuan. Municipal SASAC official said that the second phase of Tangjiatuo sewage, sludge and civil engineering has completed 90% of the total amount of the project, the key equipment can not be reached the emergency plan to ensure that the end of the water. Chicken crown stone