在1974年,南非的英美联合公司的金铀分部在一项机械化计划中,决定调查平巷掘进机在掘进独头巷道方面的应用,以提高生产效率和增加掘进速度。在南非金矿要完成的第一条机械掘进巷道是长为1150米、直径为3.4米的主要运输道,它是由西德维尔特公司制造的掘进机掘出来的。该巷道是在Free State Geduld公司2号井筒的53水平(深1627米) 掘进的,它通过了从坚韧的磨蚀岩层到软的破碎性的石英岩的各种地层,在该巷的开拓过程中,遇到了大量的问题,控制该工程的南非的英美联合公司金铀分部的技术发展部(T、D、S)在掘进机的操作和机器结构方面获得了大量的经验,许多问题只有在深部坚硬岩石的掘进中才有的,针对这些问题,提出了许多改进措施。工程组确信:在全断面巷道掘进方面取得了充分进展,已作出证明在AAC Group金矿所作的巷道掘进试验是正确的。
In 1974, South Africa’s Anglo-American joint venture’s uranium-uranium division decided in a mechanized plan to investigate the application of a roadheading machine in heading a single-headed tunnel to increase production efficiency and increase tunneling speed. The first mechanical roadway to be completed at the South African gold mine was a 1,150-meter-long main road with a diameter of 3.4 meters excavated by a boring machine manufactured by West Devon Corporation. The tunnel was drilled at 53 level (1627 meters deep) at Free State Geduld’s No. 2 wellbore and passed through various formations ranging from a tough, abrasive rock formation to soft, crushed quartzite. During the development of the lane (T, D, S), the Anglo-American unit of the Anglo-American consortium in South Africa that controlled the project, gained a great deal of experience in the operation and construction of the roadheader and many of the problems were only found in Deep hard rock excavation only, for these problems, put forward many improvements. The engineering team is convinced that sufficient progress has been made in heading full-face tunneling and that the test of tunneling test done at AAC Group Gold Mine is correct.