二冶一公司三大队在某配料槽施工中,对于1.2米×6米大型保温墙板,共2500多平方米的构缝工作采用了平衡活动吊架(如图3),作到了省工省料、文明施工。平衡活动吊架是指在厂房跨度方向、布置在两面大墙之前、可以上下左右任意活动、非永久性的固定工具;它是结合工程特点临时用胶轮车轮轴4付、脚手杆、钢丝绳一根或两根、双滑轮8个组装而成;其
In the construction of a batching tank, the Third Brigade of No.2 Smelting Company of the Second Metallurgical Company used a balance activity hanger (see Fig. 3) for the 1.2m × 6m large-scale heat-insulated wallboards, with a total of more than 2,500 square metres of joints. Material and civilized construction. The balance activity hanger refers to any movable, non-permanent fixing tool that can be moved up and down and left and right before the plant span direction, and is arranged on both sides of the large wall; it is a temporary rubber wheel axle 4 pay, foot pole, wire rope combined with engineering features. One or two, two pulleys assembled 8;