南京德基广场二期工程是目前国内规模最大的逆作法工程之一,地下5层、地上62层。该工程裙楼采用逆作法施工,利用地下连续墙围护、结构梁板作为水平支撑,工程地下室结构与基坑土方开挖交叉流水进行;土方开挖以明挖、盖挖结合实施,是工程总体部署的关键工序。结合工程实际与设计要求,介绍土方开挖采用“分层、分区、对称、流水”的施工方法,基坑土方开挖与地下室结构施工同步顺利完成。
Nanjing Teji Plaza Phase II project is currently one of the largest reverse engineering projects in China, with 5 floors underground and 62 floors above ground. The project podium construction by the reverse method, the use of underground continuous wall enclosure, the structure of the beam as a horizontal support, engineering basement structure and excavation earthwork cross-flow of water; earth excavation to dig dig, cover digging implementation of the project The key process of overall deployment. Combined with engineering practice and design requirements, this paper introduces the earthwork excavation using “stratification, zoning, symmetry, water ” construction method, excavation of foundation pit and basement structure construction simultaneously completed smoothly.