中卫—甘塘位于包兰线南段的腾格里大沙漠地段,长73公里,线路弯曲,坡道陡峻,限坡12.5‰,是全线的控制区段。六十年代末,贺兰山煤炭基地大量开发,北煤南运增长较快,为了适应这一需要,先是采取了花钱少、见效快、短期可以发挥投资效益的信号技术改造措施,包括两端大站及六个中间站的电气集中、区间自动闭塞和调度集中装置。1971年开工,1973年完工。以上包括电源装置合计投资420余万元。后因在长大坡道上,蒸汽机车上坡起动和下坡制动困难,而无法办理列车追踪运行,加之一些元部件性能不良,达不到完好可靠程度,因此自动闭塞和调度集中被放弃使用。 1978年根据包兰线运量继续增加的趋势,铁道部下令,按应急工程批准在该段的长流水、红卫及一碗泉三站修建双线插入段。初步设计文件由兰州铁路局审定,报部核备。1979
Zhongwei - Gan Tang is located in the southern section of the Bao Lan line Tengger desert, 73 km long, the line bending, steep slopes, limiting slope 12.5 ‰, is the control of the entire section. In the late 1960s, a large number of Helan Mountain coal base development, the rapid growth of North coal south transport, in order to meet this need, take the first to spend less, quick, short-term investment returns can play a signal transformation measures, including large Station and six intermediate stations of the electrical concentration, automatic blocking and scheduling centralized device. Started in 1971, completed in 1973. The above devices include a total investment of more than 420 million yuan. After the climb on the ramp, the steam locomotive uphill and downhill braking difficulties, and can not handle train tracking operation, coupled with some poor performance of the components, can not reach the intact and reliable, so automatic blocking and scheduling focused abandoned . In 1978, according to the trend that the volume of Bao-Lan line continued to increase, the Ministry of Railways ordered that the two-lane insert should be constructed in Changshuishui, Hongwei and Yilanquan III of this section according to the emergency engineering approval. The preliminary design documents are validated by Lanzhou Railway Bureau and reported to the Ministry for verification. 1979