8月27日,在国家能源局、上海市发改委、科委等有关部门以及上海东海风力发电有限公司的大力支持和帮助下,华锐风电自主研发的5MW海上风电机组在上海东海大桥海上风电场项目二期一次性顺利通过240小时预验收考核。该台5MW样机于8月17日进入240小时考核,考核期间5MW样机机组可利用率达到100%,240小时考核期间机组无故障运行。东海大桥海上风电场工程位于上海市东海大桥东侧海域,是中国第一个国
On August 27, with the strong support and assistance from NEA, Shanghai Municipal Development and Reform Commission, Science and Technology Commission and other relevant departments and Shanghai Donghai Wind Power Co., Ltd., the 5 MW offshore wind turbine independently developed by Sinovel in Shanghai East Sea Bridge offshore wind farm Project two one-time pass 240 hours pre-acceptance test. The 5MW prototype entered the 240-hour assessment on August 17, the 100MW utilization rate of the 5MW prototype during the assessment period, and the unit’s no-fault operation during the 240-hour assessment period. Donghai Bridge offshore wind farm project is located in the east of Shanghai Donghai Bridge waters, is China’s first country