【摘 要】本文主要从施工准备、施工方法、墙体的整体性检验等几个方面论述了城市地下隧道连续墙施工的施工工艺,并对施工过程中存在的问题和处理方式以及施工期间的安全措施作了简要的分析和陈述。
【关键词】地下墙;施工工艺;检验
Analysis of urban underground wall construction technology
Zhu Lu-ning
(Xiaoshan District, Hangzhou City Construction Development Co., Ltd Hangzhou Zhejiang 311200)
【Abstract】In this paper, from the aspects of construction preparation, construction methods, wall integrity inspection discusses the process of construction of urban underground continuous wall construction of the tunnel, and the problems in the construction process and handling as well as safety measures during construction were brief analysis and presentation.
【Key words】Underground wall;Construction technology;Inspection
1. 工程简介
(1)杭州市庆春路过江隧道江南工作井土建工程作为庆春路过江隧道项目的重要部分,位于萧山世纪城规划地块内。江南工作井(86.8m×25.2m×29.6m)东西向长86.8m,南北向宽25.2m,基坑开挖深度近30m;围护结构采用1.2m厚地下连续墙,共54幅,接头型式采用止水效果好、地墙整体刚度大、施工安全的“十”字钢板接头,主体结构采用有利于工程安全的明挖逆作法施工。
(2)地下连续墙是采用成槽机沿着隧道墙体采用泥浆护壁开挖出一条具有一定宽度与深度的沟槽,成槽后,在槽内放置钢筋笼,采用导管法在泥浆中浇筑混凝土,筑成一单元墙段(每幅宽约6m)。本工程采用工字钢刚性接头将每幅地连墙连接成一个整体。地下连续墙的施工主要分为以下几个部分:导墙施工、钢筋笼制作、泥浆制作、成槽放样、成槽、钢筋笼吊装和下钢筋笼、下砼导管浇筑砼。其施工工艺与钻孔灌注桩基本相同。
2. 施工准备
2.1 根据地层、地下水及施工环境条件,经设计计算,选择施工方法及隔水帷幕种类。落地式隔水帷幕一直深入到含水层底并进入到不透水层,把地下水全部隔住;悬挂式隔水帷幕只达到基坑开挖面的以下某深度处,主要用于隔断水量不大的上层滞水,不适于承压水地层。高压旋喷注浆法形成帷幕墙的质量好,适用粘土、淤泥质土、粉土、砂土及碎石土,适用土层广,但成本较高。深层搅拌法形成帷幕墙成本低,适用于软粘土、淤泥质土、粉土地基地层,施工深度一般在15m以内。液压抓斗成槽法形成帷幕墙主要以素混凝土墙为主,适用各种地层情况。在选择隔水帷幕方法时,应因地制宜,综合分析,选择合理的方法。
2.2 选择何种方式的隔渗帷幕墙设计方案,必须充分考虑如下主要影响因素,当然不局限于以下因素:
(1)工程地质:地表约35m下为卵砾石层及风化基岩层,成槽施工十分困难。
(2)前期设计:原钢筋砼地下墙仅插入卵砾石层上部,未贯穿。
(3)嵌岩要求:隔渗帷幕底部需深入至风化基岩不透水层,该层的渗透系数及围岩的完整性需满足隔渗帷幕的要求。
(4)可靠性:第二次深化设计必须确保隔渗设计效果。
(5)经济合理性:在安全可靠地前提下,需进行综合造价比较,以降低工程费用。
3. 施工方法
(1)定位:用起重机(或塔架)悬吊深层搅拌机到达桩位并对中。当场地起伏不平时,应调整塔架丝杆或平台基座,使搅拌轴保持垂直。对中误差不宜超过20mm,垂直度偏差不超过1%。
(2)浆液配制:严格控制水灰比,一般为0.45~0.55;水泥浆必须充分搅和均匀,拌和时间一般不少于3min。为保证水泥的和易性,可加入适量外加剂,如木质素磺酸钙(水泥重量的0.2%),三乙醇胺(水泥重量的0.05%)。
(3)预搅下沉:搅拌机冷却水循环正常后,启动搅拌机电机,放松起重机(或塔架)的钢丝绳,使搅拌机沿导向架切土搅拌下沉,将土搅松,下沉速度由电流检测表控制,工作电流不应大于额定电流。
(4)送浆:将制备好的水泥浆经筛过滤后,倒入贮浆桶。
(5)喷浆、搅拌、提升:搅拌机下降至设计深度后,开动灰浆泵,其出口压力保持0.4~0.6MPa,使水泥浆连续喷出,并严格按设计的提升速度边喷边搅拌边提升,使浆液和土体充分搅和直至设计的桩顶标高。提升速度不宜大于0.5m/min。
(6)重复搅拌:再次将搅拌机边旋转边沉入土中,直至设计要求深度,再次边旋转边提升至桩顶标高,并上升至地面,制桩完毕。
(7)清洗移位:向集料斗中注入适量清水,开启灰浆泵,清洗全部管路中的水泥浆,并将粘附在搅拌头上的土清洗干净,移位至下一个设计桩位,将相邻搅拌桩纵向相垂搭接成行,完成帷幕墙施工。
4. 墙体的整体性检验
4.1 检查方法。
(1)水泥土帷幕墙可采用开挖检查或钻孔取芯检查,钻孔取样观察完整性。
(2)液压抓斗成槽帷幕墙宜采用声波透射法检验墙身完整性,检验墙身结构质量。 (3)并符合其他相关标准的要求方法。
表1
4.2 检验点的部位。
(1)有代表性区域。
(2)帷幕中心线上,桩体搭接处。
(3)施工中出现异常情况的部位。
(4)并符合其他相关标准的要求部位。
4.3 检验点的数量。
(1)钻孔取芯法检测墙身完整性,检验点的数量根据需要定,一般不宜少于总桩数的2%,并至少要检验5个点。检验不合格者,应在不合格点附近进行补喷或采取有效补救措施,然后进行质量检验。
(2)采用声波透射法检验墙身完整性检验槽段应不少于总槽段的20%,且不少应于3个槽段。
(3)符合其他相关标准的要求数量。
4.4 检验时间。
宜在成墙结束7d~28d后进行,并符合其他相关标准的要求的检测时间。
5. 地下帷幕墙施工常见问题、原因及处理方法如表1
6. 安全、环保措施
6.1 安全操作要求。
施工期间,所有机具必须执行工程机械的基本安全技术操作规程。所有人员须遵守有关的安全施工及文明施工要求。
6.2 技术安全措施。
施工时,钻机要站在平整坚实的地面上,其平整度和地耐力要满足钻机施工的要求。钻机应放置平稳、坚实,并调整挺杆保持垂直。
在施工中应注意泥浆泵和管路的清洗,以防堵塞。
机械回转半径范围内不得站人。
施工前应逐级要进行安全技术交底工作。
6.3 环境保护措施。
水泥和其他易飞扬的细颗粒散体材料,应安排在库内存放或严密遮盖。
连续墙护壁泥浆宜采用立式循环系统,减少泥浆落地。
施工中的废浆的处理必须在开工前做好规划,废浆及时运出现场,不得随意排放,保持现场文明和环境保护。
施工机具尽量采用低噪音系列产品,最大限度地避免对周围环境造成破坏。设专人定期测定噪音值,发现超标及时采取降噪措施。
参考文献
[1] 孙东营,王晖.城市下穿式隧道地下连续墙施工工艺及质量控制[J].科技资讯2011NO.18.
[2] 杨隆限. 谈地下连续墙施工中常见问题及处理措施[J].山西建筑 2013.34(114~115).
[3] 曾凡奎.浅谈地下连续墙的施工[J].中华建筑报 2013.19(1~2).
【关键词】地下墙;施工工艺;检验
Analysis of urban underground wall construction technology
Zhu Lu-ning
(Xiaoshan District, Hangzhou City Construction Development Co., Ltd Hangzhou Zhejiang 311200)
【Abstract】In this paper, from the aspects of construction preparation, construction methods, wall integrity inspection discusses the process of construction of urban underground continuous wall construction of the tunnel, and the problems in the construction process and handling as well as safety measures during construction were brief analysis and presentation.
【Key words】Underground wall;Construction technology;Inspection
1. 工程简介
(1)杭州市庆春路过江隧道江南工作井土建工程作为庆春路过江隧道项目的重要部分,位于萧山世纪城规划地块内。江南工作井(86.8m×25.2m×29.6m)东西向长86.8m,南北向宽25.2m,基坑开挖深度近30m;围护结构采用1.2m厚地下连续墙,共54幅,接头型式采用止水效果好、地墙整体刚度大、施工安全的“十”字钢板接头,主体结构采用有利于工程安全的明挖逆作法施工。
(2)地下连续墙是采用成槽机沿着隧道墙体采用泥浆护壁开挖出一条具有一定宽度与深度的沟槽,成槽后,在槽内放置钢筋笼,采用导管法在泥浆中浇筑混凝土,筑成一单元墙段(每幅宽约6m)。本工程采用工字钢刚性接头将每幅地连墙连接成一个整体。地下连续墙的施工主要分为以下几个部分:导墙施工、钢筋笼制作、泥浆制作、成槽放样、成槽、钢筋笼吊装和下钢筋笼、下砼导管浇筑砼。其施工工艺与钻孔灌注桩基本相同。
2. 施工准备
2.1 根据地层、地下水及施工环境条件,经设计计算,选择施工方法及隔水帷幕种类。落地式隔水帷幕一直深入到含水层底并进入到不透水层,把地下水全部隔住;悬挂式隔水帷幕只达到基坑开挖面的以下某深度处,主要用于隔断水量不大的上层滞水,不适于承压水地层。高压旋喷注浆法形成帷幕墙的质量好,适用粘土、淤泥质土、粉土、砂土及碎石土,适用土层广,但成本较高。深层搅拌法形成帷幕墙成本低,适用于软粘土、淤泥质土、粉土地基地层,施工深度一般在15m以内。液压抓斗成槽法形成帷幕墙主要以素混凝土墙为主,适用各种地层情况。在选择隔水帷幕方法时,应因地制宜,综合分析,选择合理的方法。
2.2 选择何种方式的隔渗帷幕墙设计方案,必须充分考虑如下主要影响因素,当然不局限于以下因素:
(1)工程地质:地表约35m下为卵砾石层及风化基岩层,成槽施工十分困难。
(2)前期设计:原钢筋砼地下墙仅插入卵砾石层上部,未贯穿。
(3)嵌岩要求:隔渗帷幕底部需深入至风化基岩不透水层,该层的渗透系数及围岩的完整性需满足隔渗帷幕的要求。
(4)可靠性:第二次深化设计必须确保隔渗设计效果。
(5)经济合理性:在安全可靠地前提下,需进行综合造价比较,以降低工程费用。
3. 施工方法
(1)定位:用起重机(或塔架)悬吊深层搅拌机到达桩位并对中。当场地起伏不平时,应调整塔架丝杆或平台基座,使搅拌轴保持垂直。对中误差不宜超过20mm,垂直度偏差不超过1%。
(2)浆液配制:严格控制水灰比,一般为0.45~0.55;水泥浆必须充分搅和均匀,拌和时间一般不少于3min。为保证水泥的和易性,可加入适量外加剂,如木质素磺酸钙(水泥重量的0.2%),三乙醇胺(水泥重量的0.05%)。
(3)预搅下沉:搅拌机冷却水循环正常后,启动搅拌机电机,放松起重机(或塔架)的钢丝绳,使搅拌机沿导向架切土搅拌下沉,将土搅松,下沉速度由电流检测表控制,工作电流不应大于额定电流。
(4)送浆:将制备好的水泥浆经筛过滤后,倒入贮浆桶。
(5)喷浆、搅拌、提升:搅拌机下降至设计深度后,开动灰浆泵,其出口压力保持0.4~0.6MPa,使水泥浆连续喷出,并严格按设计的提升速度边喷边搅拌边提升,使浆液和土体充分搅和直至设计的桩顶标高。提升速度不宜大于0.5m/min。
(6)重复搅拌:再次将搅拌机边旋转边沉入土中,直至设计要求深度,再次边旋转边提升至桩顶标高,并上升至地面,制桩完毕。
(7)清洗移位:向集料斗中注入适量清水,开启灰浆泵,清洗全部管路中的水泥浆,并将粘附在搅拌头上的土清洗干净,移位至下一个设计桩位,将相邻搅拌桩纵向相垂搭接成行,完成帷幕墙施工。
4. 墙体的整体性检验
4.1 检查方法。
(1)水泥土帷幕墙可采用开挖检查或钻孔取芯检查,钻孔取样观察完整性。
(2)液压抓斗成槽帷幕墙宜采用声波透射法检验墙身完整性,检验墙身结构质量。 (3)并符合其他相关标准的要求方法。
表1
4.2 检验点的部位。
(1)有代表性区域。
(2)帷幕中心线上,桩体搭接处。
(3)施工中出现异常情况的部位。
(4)并符合其他相关标准的要求部位。
4.3 检验点的数量。
(1)钻孔取芯法检测墙身完整性,检验点的数量根据需要定,一般不宜少于总桩数的2%,并至少要检验5个点。检验不合格者,应在不合格点附近进行补喷或采取有效补救措施,然后进行质量检验。
(2)采用声波透射法检验墙身完整性检验槽段应不少于总槽段的20%,且不少应于3个槽段。
(3)符合其他相关标准的要求数量。
4.4 检验时间。
宜在成墙结束7d~28d后进行,并符合其他相关标准的要求的检测时间。
5. 地下帷幕墙施工常见问题、原因及处理方法如表1
6. 安全、环保措施
6.1 安全操作要求。
施工期间,所有机具必须执行工程机械的基本安全技术操作规程。所有人员须遵守有关的安全施工及文明施工要求。
6.2 技术安全措施。
施工时,钻机要站在平整坚实的地面上,其平整度和地耐力要满足钻机施工的要求。钻机应放置平稳、坚实,并调整挺杆保持垂直。
在施工中应注意泥浆泵和管路的清洗,以防堵塞。
机械回转半径范围内不得站人。
施工前应逐级要进行安全技术交底工作。
6.3 环境保护措施。
水泥和其他易飞扬的细颗粒散体材料,应安排在库内存放或严密遮盖。
连续墙护壁泥浆宜采用立式循环系统,减少泥浆落地。
施工中的废浆的处理必须在开工前做好规划,废浆及时运出现场,不得随意排放,保持现场文明和环境保护。
施工机具尽量采用低噪音系列产品,最大限度地避免对周围环境造成破坏。设专人定期测定噪音值,发现超标及时采取降噪措施。
参考文献
[1] 孙东营,王晖.城市下穿式隧道地下连续墙施工工艺及质量控制[J].科技资讯2011NO.18.
[2] 杨隆限. 谈地下连续墙施工中常见问题及处理措施[J].山西建筑 2013.34(114~115).
[3] 曾凡奎.浅谈地下连续墙的施工[J].中华建筑报 2013.19(1~2).