一、瓦斯抽放的变化情况1969年道内煤矿的瓦斯抽放量达到最高水平(17个煤矿共抽放瓦斯40400万米~3,按纯甲烷计算)。随着煤矿的减少,到1974年瓦斯抽放量有逐年下降的倾向(12个煤矿共抽放瓦斯26500万米~3)。1975年由于夕张新煤矿的正式投产、瓦斯抽放量又有所增加(11个煤矿共抽放瓦斯31400万米)。但是,由于幌内煤矿发生事故(1975年11月发生事故,1977年10月恢复生产),以及夕张新第二煤矿停产(1977年8月全面停产),所以瓦斯抽放量1976年减少到30600万米~3。而1977年则减少到26500米~3。1978年由于幌内煤矿全面恢复生产,瓦斯抽放量又增加到28300万米~3。
First, the gas drainage changes In 1969, the coal mine in the gas drainage volume reached the highest level (17 coal mines in a total drainage gas 404000000 ~ 3, calculated as pure methane). With the reduction of coal mines, the amount of gas drainage tends to decrease year by year (a total of 126.5 million m 3 was drained from 12 coal mines). In 1975, due to the official production of the Yixiazha Coal Mine, the quantity of gas drainage increased again (11 coal mines drained 314 million meters of methane in total). However, the gas drainage volume was reduced to 30,600 in 1976 due to an accident at the Rock Cave (an accident in November 1975 and the resumption of production in October 1977) and the halt of the Yixin Second Mine (completed in August 1977) Million meters ~ 3. While in 1977 it was reduced to 26500m ~ 3. In 1978, due to the full resumption of production at Sawai Mine, gas drainage volume increased to 283 million m3.