2015年元旦前夕,从54路改扩建工程指挥部工程前沿传来捷报:55路有轨电车站前街至西客站最后760米工程正式竣工,电车人在新的一年里向700万春城市民献上了幸福的民生大礼!自2013年4月20日54路改扩建项目开工以来,电车公司共投入人员1200人次,出动高空作业车235台次,协助通讯公司排迁光缆5321米,处置轨道内突发溢水23起,清理积水1800立方米,撒防滑沙750立方米,共设置警示标志
On the eve of New Year’s Day in 2015, the 54-Road Reconstruction and Extension Project headquarters came with the latest news: the last 760-meter project of the 55-seater tramway station from Qianqian to West Railway Station was officially completed. Since April 20, 2013 Road 54 expansion project started, the tram company invested a total of 1,200 people, sent 235 aerial work vehicles to help communications companies to relocate 5321 meters of optical cable, the disposal of the track Suddenly overflowing 23, clearing 1,800 cubic meters of water, scatter anti-sliding sand 750 cubic meters, a total set of warning signs