国家体委羽排球馆为第十一届亚运会工程项目之一,地处北京体育馆路,建筑面积10338.58m~2,南北长91m,东西宽38.6m,两层。底层16.5m,为排球训练馆。第二层13.1m,为羽毛球训练馆。中部9~10轴设有夹层,为更衣室。办公室、库房、机房等建筑物全高40m。本工程1987年5月开工,1988年11月交付使用。经北京市建委等部门验收,被评为
The National Sports Plume Volleyball Hall is one of the projects of the 11th Asian Games. It is located on the Beijing Stadium Road, with a building area of 10338.58m~2, a length of 91m from north to south, 38.6m from east to west, and two floors. The bottom 16.5m is a volleyball training hall. The second layer is 13.1m, which is a badminton training hall. The center 9~10 axis has a mezzanine and is a dressing room. The total height of buildings such as offices, warehouses, and computer rooms is 40m. This project started in May 1987 and was delivered for use in November 1988. Accepted by the Beijing Construction Commission and other departments, was rated