株树桥水库属我国第一批混凝土面板堆石坝工程。大坝自 1992年 7月起发现有漏水 ,以后呈逐年增加趋势 ,1999年 7月达到 2 5 0 0L/s ,为同类工程所罕见。为此 ,对株树桥水库大坝渗漏原因做了初步分析 ,认为大坝与两岸岩体相对变形导致止水破坏是大坝面板破坏的基本原因 ,并由此对混凝土面板堆石坝的设计、施工等方面提出了一些值得探讨的问题
Zhushuqiao Reservoir is China’s first batch of concrete faced rockfill dam project. The dam has been found to have leaked water since July 1992, showing an increasing trend year after year. It reached 2550 L / s in July 1999, which is rare for similar projects. Therefore, a preliminary analysis is made of the causes of seepage in the dam of Zhushuqiao Reservoir. It is considered that the relative deformation of the dam and the two sides of the rock mass results in the failure of water stoppage, which is the basic reason for the dam panel failure. Therefore, the concrete face rockfill dam Design, construction and other aspects put forward some issues worth exploring