摘要:近年来,对工程造价进行控制已经被人们所广泛接受了,但是造价问题是常抓常有,项目管理是常抓常新。“概算超估算,预算超概算,结算超预算”的三超现象在政府投资项目中还普遍存在,结算扯皮现象也屡见不鲜。
工程项目的全过程包括投资决策阶段、设计阶段、项目实施阶段、项目营运阶段,每个阶段又包含了若干个环节和步骤,加强每一个环节的管理对工程造价的控制都有着重要的意义,而做好这些环节的监督审计工作就成为政府投资项目审计的重点,笔者就从以下几个方面谈个人观点:
关键字:工程项目;造价控制;跟踪审计
Abstract: in recent years, to control the cost of the project have been widely accepted, but cost the problem is often catch is common, the project management is often catch often new. "The budget estimate, the budget exceeds the probable settlement budget," SanChao phenomenon in government investment project exists generally, settlement dispute over trifles phenomenon is also common occurance.
The whole process of the project including investment decision stage, the design phase, project implementation phase, project operation stages, and contains several links and steps, strengthen the management of each link to the project cost control is of great significance, and doing these links in the supervision and audit work will become the auditing of government investment projects, the author from the following several aspects to discuss personal point of view:
Key word: engineering projects; Cost control; Track audit
中图分类号:TU723.3 文献标识码:A文章编号:
一、关注工程项目的决策控制阶段的审计
1、编制项目建议书。建设单位根据企业资本支出计划提出工程项目建设计划,并指定项目管理部门或委托具有相应资质的单位编制项目建议书,项目建议书经项目管理部门审核后,提交决策部门审批。
2、编制可行性研究报告。根据已通过审批的项目建议书,建设单位自行或委托具有相应资质的设计单位编制可行性研究报告,报告内容主要包括市场可行性分析、技术可行性分析和财务可行性分析。为了防止工程项目投资失控,在可行性研究阶段必须深入调研,对可行性方案的审批应慎重,要进行多方面的论证,并建立决策责任制。。
3、项目决策。將项目建议书和可行性研究报告提交最高管理层,由管理层开专题会议进行决策,在进行充分论证后,得出科学的决策。在设计阶段必须委托资信良好的单位设计并签定详细合同,规定若应设计问题导致工程变更而增加的费用由设计单位担负,在工程的过程管理中,设计阶段具有重要的意义,设计对工程造价的影响很大,不能因设计的不妥所造成整个项目效益低下。
二、强化项目实施阶段的全方位审计
1、建立健全招投标机制。严格按照招投标的控制流程进行招投标管理,该流程主要包括招标、评标、定标和合同管理四个环节。招标是根据招标项目的特点和需要编制招标文件,明确招标项目的技术要求、对投标人资格审查的标准、投标报价要求等内容要经过财务部门认可;评标,组建专门的评标委员会评标,评标是依据是招标文件中确定的原则和方法,评标方法由评标委员会在开标前确定,评标方法一经确定,在评标时不得改变;定标,评标委员会按照招标文件确定的标准和方法,对侯选投标文件进行公开评审和比较,并择优选择中标人;合同管理,建设单位分别与监理单位、施工单位及材料设备供应商订立书面合同,会计人员参与合同的签订,审核合同的金额、支付条件、结算方式、支付时间等。书面合同留存财务部门一份作为支付合同价款的依据。
2、优化施工方案,减少无益消耗,对工程中涉及到人力、材料、机械和工期的,要科学配置,保证施工协调、有序和高效。
3、加强施工现场管理,杜绝因工程质量和材料问题造成的返工浪费情况发生。
三、杜绝违法分包转包现象。鉴于分包转包现象对于工程项目的危害之大,在招投标时认真审查投标单位的资格,在订立合同时明确规定并注明违约责任,在施工过程中对工程项目的施工单位进行监督,防止施工单位私自转包发包。
四、完善监督人员的责权利关系,强化监督机制。针对大多数工程缺乏有效的监督机制问题,制定和完善了监督人员的责权利关系。监督人员在施工现场部分代表了建设单位的权利,施工单位必须听从监督人员的意见和建议,通过多种渠道俩解决工程监督不力的问题。
五、严格控制工程投资,防止投资失控。在施工之前,根据工程项目预算,列出施工进度及费用预算计划表。在实际支付工程款时,严格按照施工进度及费用预算计划表付款,对于超出部分不予承担,有效防止投资失控。
六、加强对工程结算的监督,严格控制项目投资。
一是完善工程付款程序,把握好付款的关口。
以前在对工程款的拨付问题上,业主容易出现对工程造价情况不能准确把握,造成工程款的拨付凭感觉,容易产生超比例支付甚至是超付总造价的现象。现在形成的一套比较可行的办法是在工程施工过程中,对工程进度款的支付流程是由施工单位提交申请支付工程款单,监理单位根据工程进度状况初步核算工程量,从而进步估算工程造价,再由监理单位将附有工程量完成情况的清单及付款申请单移交于工程造价咨询机构,由造价咨询机构再对此进行核查,以确定工程款的拨付。这种根据工程进度状况进行工程款拨付的行为,应该说是比较科学的反映工程的现状和有效进行工程造价控制的重要环节,层层把关,层层审核,程序比较严谨,责任比较清晰,对工程造价起到有力控制,但由于在工程建设的过程中,各项工作非常繁杂,经常出现一些对工程造价的失控点和盲点,项目的实际发生与否,以及发生的量的大小,不能客观反映出来,因此在这方面要进一步加强对工程造价的动态,建立台账,使之与工程的进度直接衔接起来,让工程造价与工程进度图一样直观。
二是加强对监理、造价咨询机构等中介机构的监督管理。
工程监理、造价咨询等单位在工程建设的全过程中起到了至关重要的作用,工程监理对工程质量、工期进度等方面的监督管理充分发挥出其主观能动,造价咨询机构对项目工程造价控制发挥了闸门的作用,所有与本工程项目有关的资金流向都应通过造价咨询机构予以确认,杜绝了资金拨付的随意性和盲目性。由上可见,中介机构在工程建设的管理过程中发挥了主要的管理作用,它们作用发挥好坏,直接关系到工程建设的质量和投资效益,通过对中介机构实施有效监管,是实现工程有效控制的关键,加强对中介机构的业务指导和随机性的抽查,检查有无违规操作的行为,以及中介机构之间的相互监督,切实保证中介机构发挥其各自职能作用。
三是加强对图纸以外发生的工程量签证的管理工作。
在目前的工程造价中,工程量签证已成为其组成中分量较重的一块,图纸以内的工程量,属于静态的部分,比较容易控制,但工程量签证部分在事过境迁以后,很难予以核实其是否发生的真实性,过程控制尤显重要,加强监理单位和工程造价咨询单位共同对工程进展过程中发生的工程量和工程进度款进行有效控制,现场签证由业主、监理单位、工程造价咨询单位及施工单位四家签字认可,拧干签证中的水分,提高了现场签证的真实度,实现工程造价的有效控制。
总而言之,我们做好政府投资项目的跟踪是审计工作需要长期、持续的时间,需要不断树立新理念,以人为本,开拓视野,真正发挥出全过程管理的巨大作用,去实现工跟踪审计的最大效力,让政府投资项目发挥最大的效能。
作者简介:崔志男,1979年12月出生,性别:男,民族:汉,山东省济南市,工作单位:济南市审计局,中级审计师,学士学位,研究方向:建筑经济与管理。
工程项目的全过程包括投资决策阶段、设计阶段、项目实施阶段、项目营运阶段,每个阶段又包含了若干个环节和步骤,加强每一个环节的管理对工程造价的控制都有着重要的意义,而做好这些环节的监督审计工作就成为政府投资项目审计的重点,笔者就从以下几个方面谈个人观点:
关键字:工程项目;造价控制;跟踪审计
Abstract: in recent years, to control the cost of the project have been widely accepted, but cost the problem is often catch is common, the project management is often catch often new. "The budget estimate, the budget exceeds the probable settlement budget," SanChao phenomenon in government investment project exists generally, settlement dispute over trifles phenomenon is also common occurance.
The whole process of the project including investment decision stage, the design phase, project implementation phase, project operation stages, and contains several links and steps, strengthen the management of each link to the project cost control is of great significance, and doing these links in the supervision and audit work will become the auditing of government investment projects, the author from the following several aspects to discuss personal point of view:
Key word: engineering projects; Cost control; Track audit
中图分类号:TU723.3 文献标识码:A文章编号:
一、关注工程项目的决策控制阶段的审计
1、编制项目建议书。建设单位根据企业资本支出计划提出工程项目建设计划,并指定项目管理部门或委托具有相应资质的单位编制项目建议书,项目建议书经项目管理部门审核后,提交决策部门审批。
2、编制可行性研究报告。根据已通过审批的项目建议书,建设单位自行或委托具有相应资质的设计单位编制可行性研究报告,报告内容主要包括市场可行性分析、技术可行性分析和财务可行性分析。为了防止工程项目投资失控,在可行性研究阶段必须深入调研,对可行性方案的审批应慎重,要进行多方面的论证,并建立决策责任制。。
3、项目决策。將项目建议书和可行性研究报告提交最高管理层,由管理层开专题会议进行决策,在进行充分论证后,得出科学的决策。在设计阶段必须委托资信良好的单位设计并签定详细合同,规定若应设计问题导致工程变更而增加的费用由设计单位担负,在工程的过程管理中,设计阶段具有重要的意义,设计对工程造价的影响很大,不能因设计的不妥所造成整个项目效益低下。
二、强化项目实施阶段的全方位审计
1、建立健全招投标机制。严格按照招投标的控制流程进行招投标管理,该流程主要包括招标、评标、定标和合同管理四个环节。招标是根据招标项目的特点和需要编制招标文件,明确招标项目的技术要求、对投标人资格审查的标准、投标报价要求等内容要经过财务部门认可;评标,组建专门的评标委员会评标,评标是依据是招标文件中确定的原则和方法,评标方法由评标委员会在开标前确定,评标方法一经确定,在评标时不得改变;定标,评标委员会按照招标文件确定的标准和方法,对侯选投标文件进行公开评审和比较,并择优选择中标人;合同管理,建设单位分别与监理单位、施工单位及材料设备供应商订立书面合同,会计人员参与合同的签订,审核合同的金额、支付条件、结算方式、支付时间等。书面合同留存财务部门一份作为支付合同价款的依据。
2、优化施工方案,减少无益消耗,对工程中涉及到人力、材料、机械和工期的,要科学配置,保证施工协调、有序和高效。
3、加强施工现场管理,杜绝因工程质量和材料问题造成的返工浪费情况发生。
三、杜绝违法分包转包现象。鉴于分包转包现象对于工程项目的危害之大,在招投标时认真审查投标单位的资格,在订立合同时明确规定并注明违约责任,在施工过程中对工程项目的施工单位进行监督,防止施工单位私自转包发包。
四、完善监督人员的责权利关系,强化监督机制。针对大多数工程缺乏有效的监督机制问题,制定和完善了监督人员的责权利关系。监督人员在施工现场部分代表了建设单位的权利,施工单位必须听从监督人员的意见和建议,通过多种渠道俩解决工程监督不力的问题。
五、严格控制工程投资,防止投资失控。在施工之前,根据工程项目预算,列出施工进度及费用预算计划表。在实际支付工程款时,严格按照施工进度及费用预算计划表付款,对于超出部分不予承担,有效防止投资失控。
六、加强对工程结算的监督,严格控制项目投资。
一是完善工程付款程序,把握好付款的关口。
以前在对工程款的拨付问题上,业主容易出现对工程造价情况不能准确把握,造成工程款的拨付凭感觉,容易产生超比例支付甚至是超付总造价的现象。现在形成的一套比较可行的办法是在工程施工过程中,对工程进度款的支付流程是由施工单位提交申请支付工程款单,监理单位根据工程进度状况初步核算工程量,从而进步估算工程造价,再由监理单位将附有工程量完成情况的清单及付款申请单移交于工程造价咨询机构,由造价咨询机构再对此进行核查,以确定工程款的拨付。这种根据工程进度状况进行工程款拨付的行为,应该说是比较科学的反映工程的现状和有效进行工程造价控制的重要环节,层层把关,层层审核,程序比较严谨,责任比较清晰,对工程造价起到有力控制,但由于在工程建设的过程中,各项工作非常繁杂,经常出现一些对工程造价的失控点和盲点,项目的实际发生与否,以及发生的量的大小,不能客观反映出来,因此在这方面要进一步加强对工程造价的动态,建立台账,使之与工程的进度直接衔接起来,让工程造价与工程进度图一样直观。
二是加强对监理、造价咨询机构等中介机构的监督管理。
工程监理、造价咨询等单位在工程建设的全过程中起到了至关重要的作用,工程监理对工程质量、工期进度等方面的监督管理充分发挥出其主观能动,造价咨询机构对项目工程造价控制发挥了闸门的作用,所有与本工程项目有关的资金流向都应通过造价咨询机构予以确认,杜绝了资金拨付的随意性和盲目性。由上可见,中介机构在工程建设的管理过程中发挥了主要的管理作用,它们作用发挥好坏,直接关系到工程建设的质量和投资效益,通过对中介机构实施有效监管,是实现工程有效控制的关键,加强对中介机构的业务指导和随机性的抽查,检查有无违规操作的行为,以及中介机构之间的相互监督,切实保证中介机构发挥其各自职能作用。
三是加强对图纸以外发生的工程量签证的管理工作。
在目前的工程造价中,工程量签证已成为其组成中分量较重的一块,图纸以内的工程量,属于静态的部分,比较容易控制,但工程量签证部分在事过境迁以后,很难予以核实其是否发生的真实性,过程控制尤显重要,加强监理单位和工程造价咨询单位共同对工程进展过程中发生的工程量和工程进度款进行有效控制,现场签证由业主、监理单位、工程造价咨询单位及施工单位四家签字认可,拧干签证中的水分,提高了现场签证的真实度,实现工程造价的有效控制。
总而言之,我们做好政府投资项目的跟踪是审计工作需要长期、持续的时间,需要不断树立新理念,以人为本,开拓视野,真正发挥出全过程管理的巨大作用,去实现工跟踪审计的最大效力,让政府投资项目发挥最大的效能。
作者简介:崔志男,1979年12月出生,性别:男,民族:汉,山东省济南市,工作单位:济南市审计局,中级审计师,学士学位,研究方向:建筑经济与管理。