[摘 要]随着经济的高速发展,社会的用电需求不断提升,电力设施的建设需求也越来越大,且随着城市美观的需要,越来越多的高压电缆需要依托电力隧道施工,但电力隧道的施工存在着施工难度大、监理控制难度大、工程质量难以保证的特点。文章以A市220 kV变电站输变电配套110 kV线路工程为例,详细介绍了该工程施工过程中采用的监理控制。
[关键词]输变电配套工程;电缆;监理控制;工程质量
[中图分类号]TM711 [文献标志码]A [文章编号]2095–6487(2021)03–0–02
[Abstract]With the rapid development of the economy, the demand for electricity in the society continues to increase, and the demand for construction of power facilities is also increasing. With the need for urban beauty, more and more high-voltage cables need to rely on power tunnel construction, but The construction of power tunnels has the characteristics of great difficulty in construction, great difficulty in supervision and control, and difficulty in guaranteeing project quality. This paper takes the 110 kV line project of 220 kV B substation in City A as an example, and introduces the supervision and control adopted in the construction process of the project in detail.
[Keywords]power transmission and transformation supporting project; cable; supervision control; engineering quality
以A市220 kV輸变电配套110 kV线路工程为例,详细介绍了施工过程中采用的监理控制方法,最终项目顺利通过验收,各项技术指标均符合设计及施工技术规程规定,其中结构防水的验收合格率得到了显著的提升。
1 A市220 kV输变电配套110 kV线路工程简介
1.1 工程名称
A市220 kV变电站输变电配套110 kV线路工程(B变电站至力源终端场改线部分)。
1.2 工程建设规模
(1)110 kV配套A线线路工程(架空部分):110 kV配套A线线路工程(架空部分)新建线路长0.048 km。导线选用JL/LB1A630/45型铝包钢芯铝绞线,地线选用JLB40-100钢芯铝绞线;新建钢管杆2基,其中双回耐张钢管杆1基,四回耐张钢管杆1基。
(2)110 kV配套B线线路工程(架空部分):110 kV配套B线线路工程(架空部分)新建线路长0.076 km。导线选用JL/LB1A630/45型铝包钢芯铝绞线,地线选用JLB40-100钢芯铝绞线;新建钢管杆2基,其中三回耐张钢管杆2基。
(3)110 kV配套A线线路工程(电缆部分):从新建电缆终端场Ⅰ~新建电缆终端场Ⅱ。新建四回电缆线路长4×3.42 km。A线对应的站点线路为:熙都甲、乙、丙线三回,熙陈线一回,共四回路。
四回路线路:共3 049 m,其中,四回路电缆沟1 348 m,四回路电缆埋管689 m,四回路电缆水平定向钻拉管352 m,四回路电缆桥架42 m。
新建中间接头井共6个,其中,Ⅰ型中间接头井2个,2型中间接头井1个,3型中间接头井3个。长度共111 m。
新建两个电缆终端场,终端场Ⅰ大小为50 m×21 m(非长方形),终端场Ⅱ大小为26.5 m×21.5 m。电缆终端均为地面终端。
隧道工程:顶管隧道618 m(含隧道土建及装修工程、通风工程、给排水工程、给排水工程接驳工程、低压配电工程、弱电系统工程)。工作井2个(13.4 m×13.4 m),顶进井深度26.45 m,接收井深度27.89 m。
(4)110 kV配套B线线路工程(电缆部分):从新建电缆终端场Ⅰ~NB125接藤都联线工井位置。新建四回电缆线路长4×1.62 km。B线对应的站点线路为:熙潭甲、乙线双回,熙道线一回,熙谭线一回,共四回路。四回路线路:共1378 m,其中,四回路电缆沟636 m,四回路电缆埋管504 m,四回路电缆水平定向钻拉管196 m,四回路电缆桥架42 m。图1为A市220 kV变电站输变电配套110 kV线路工程效果图。
2 基于7S管理的高压电力电缆施工过程的监理控制要点
2.1 标识管理
对于标识管理,监理需要注意施工现场有没有划分管理区域,责任人是否明确,责任人执行力是否到位;有没有分区标示,标示牌、警示牌、操作牌、小看板是否齐全醒目,布置是否合理;材料堆放是否按区域,是否分类,是否整齐;有没有闲置材料、设备,是否有用途不明之物;现场有没有乱放的个人东西;通道是否干净,是否堆放杂物,堆放的物品有没有和通道平行或成直角堆放等。图2为A市220 kV变电站输变电配套110 kV线路工程标示管理效果图。 2.2 施工过程管理
对于施工过程管理,监理需要注意施工现场的工器具、计量仪器等是否存放有序,是否便于寻找及归位;危险品有否明确标示,灭火器是否有定期点检;走道、临边、洞口标示是否齐全,防护措施是否标准;交叉作业措施是否到位,是否规范;施工机械设备防护措施是否齐全、完整、规范;施工、生活电源线布置是否整齐有序;作业人员的周边环境是否安全,是否有凌乱物件;现场道路是否有交通标示;施工场地是否平整,是否有扬尘,是否有积水等。
2.3 施工周边管理
对于施工周边管理,监理需要注意现场消防器材是否齐全,布置是否合理;现场工人着装是否统一,是否规范;个人安全防护用品是否齐全,使用是否规范;办公区是否与施工区隔离,办公室是否整齐、整洁明亮;施工垃圾、生活垃圾清理是否及时。
2.4 7S监理细则
编制人员要结合工程实际,按技术标准和规程要求编制,审批人把好审批关,未经审批严禁实施。进行安全宣传教育;做好安全技术措施交底;开展班组活动;加强特殊工种管理、设备管理、违章事故处理程序的管理;问题处理应及时有效。督促施工单位加强对员工进行安全教育,检查相关记录,确保安全教育的有效性。对发现的问题,发限期整改单,要求限期整改,并按有关管理规定要求对不符合要求的行为进行处理。在审核施工总平面图布置时,应注意平时布置符合安全卫生、消防要求,满足环境保护的需要。督促相关单位按总体规划要求布置场地。应注意地下、地上管线,场地排水,垃圾、污泥处理,材料堆放,安全距离等。每天对各区域进行巡视检查,发现问题先口头通知该区域责任人进行整改,如整改不及时或不到位,则以书面形式通知施工单位,并要求限时整改,同时进行跟踪整改情况。每周进行定期检查,对存在的问题列出整改清单(文明施工整体视觉形象检查评价表),限时整改,并跟踪整改进度及整改结果。
根据现场7S的执行情况,每月进行一次7S管理效果回顾讨论,对存在的不足之处进行罗列,找出主要问题,分析原因及出现的主要部位,商议形成有效的改进办法,使之在现场行之有效,达到现场文明施工良性循环,并能持之以恒的效果。同时也进一步完善监理对7S管理的办法。
3 A市220 kV输变电配套110 kV线路工程监理示例
3.1 加强设备安装质量的检查措施
监理提前编制了专项的管节进场验收方案,对于不合格的管节要求厂家返厂或者重新修复。现场工人对所有检查不合格的管节钢圈进行焊接加固处理,焊接完成后,对加工处理后的管节钢圈进行重新检查,确保了管节止水胶圈的固定效果合格后方可用于隧道顶管施工。
为了避免后续生产的管节出现同类问题,小组组长组织管节的生产厂家重新召开了技术交底会,明确止水胶圈的安装要求,并且规范管节进场验收的细节工作,制作了管节进场验收标准表格,每批次管节进场前,需各方验收并签名确认。
定位钢圈加固处理后,止水胶圈的位置更加牢固,在管节拼接过程中未发现胶圈脱落现象,监理小组成员对熙悦项目的工地管节进行抽样检查,统计后发现一批次管节(15节)胶圈脱落次数仅为1次,合格率提升到了93.3%,达到了施工目标。隧道贯通后,隧道内的管节内壁接缝处无渗水现象,实现对策实施后,隧道内部整体防水效果提升。
3.2 延长洞口处尾管钢圈、焊接加装双层遇水膨胀带
最后一节管节生产前,小组成员提前与管节生产厂家进行沟通,提出尾管的钢圈加长的具体尺寸和其他要求,确保尾管在和止水环进行密封处理时,可以提供有效的焊接处理工作面。
A市220 kV变电站输变电配套110 kV线路工程工程顶管贯通后,监理小组成员安排工人对尾管和止水环接缝处的钢圈进行了密封处理,采取双层遇水膨胀带沿着整个圆形接触面焊接,焊接完成后检查止水胶条的安装效果,确保密封性。
采取密封处理后,每道接缝处都有了双层防水材料,实现了对策目标,大幅加强了接缝处密封效果,且后续检查发现剪力墙浇筑完成后,隧道洞口处无渗水现场发生,起到了加强防水的效果。图3为双层止水胶条现场安装图。
4 结语
以A市220 kV输变电配套110 kV线路工程为例,详细介绍了A市220 kV输变电配套110 kV线路工程概状,分析了基于7S管理的高压电力电缆施工过程的监理控制要点、施工过程中关于监理事项方面的管理创新做法和技术创新做法,对其他工程具有较强的借鉴性。
参考文献
[1] 于景丰.电力电纜实用新技术[M].北京:中国水利水电出版社,2014.
[2] 李光辉.电力电缆施工技术[M].北京:中国电力出版社,2008.
[3] 高志强,孙丽伟.供电企业操作岗位员工安全胜任力模型的构建[J].中国安全科学学报,2011,21(8):22-29.
[4] 周曙琦.探析电力管沟设计中的电力电缆敷设方式选用[J].通讯世界,2018(5):120-121.
[关键词]输变电配套工程;电缆;监理控制;工程质量
[中图分类号]TM711 [文献标志码]A [文章编号]2095–6487(2021)03–0–02
[Abstract]With the rapid development of the economy, the demand for electricity in the society continues to increase, and the demand for construction of power facilities is also increasing. With the need for urban beauty, more and more high-voltage cables need to rely on power tunnel construction, but The construction of power tunnels has the characteristics of great difficulty in construction, great difficulty in supervision and control, and difficulty in guaranteeing project quality. This paper takes the 110 kV line project of 220 kV B substation in City A as an example, and introduces the supervision and control adopted in the construction process of the project in detail.
[Keywords]power transmission and transformation supporting project; cable; supervision control; engineering quality
以A市220 kV輸变电配套110 kV线路工程为例,详细介绍了施工过程中采用的监理控制方法,最终项目顺利通过验收,各项技术指标均符合设计及施工技术规程规定,其中结构防水的验收合格率得到了显著的提升。
1 A市220 kV输变电配套110 kV线路工程简介
1.1 工程名称
A市220 kV变电站输变电配套110 kV线路工程(B变电站至力源终端场改线部分)。
1.2 工程建设规模
(1)110 kV配套A线线路工程(架空部分):110 kV配套A线线路工程(架空部分)新建线路长0.048 km。导线选用JL/LB1A630/45型铝包钢芯铝绞线,地线选用JLB40-100钢芯铝绞线;新建钢管杆2基,其中双回耐张钢管杆1基,四回耐张钢管杆1基。
(2)110 kV配套B线线路工程(架空部分):110 kV配套B线线路工程(架空部分)新建线路长0.076 km。导线选用JL/LB1A630/45型铝包钢芯铝绞线,地线选用JLB40-100钢芯铝绞线;新建钢管杆2基,其中三回耐张钢管杆2基。
(3)110 kV配套A线线路工程(电缆部分):从新建电缆终端场Ⅰ~新建电缆终端场Ⅱ。新建四回电缆线路长4×3.42 km。A线对应的站点线路为:熙都甲、乙、丙线三回,熙陈线一回,共四回路。
四回路线路:共3 049 m,其中,四回路电缆沟1 348 m,四回路电缆埋管689 m,四回路电缆水平定向钻拉管352 m,四回路电缆桥架42 m。
新建中间接头井共6个,其中,Ⅰ型中间接头井2个,2型中间接头井1个,3型中间接头井3个。长度共111 m。
新建两个电缆终端场,终端场Ⅰ大小为50 m×21 m(非长方形),终端场Ⅱ大小为26.5 m×21.5 m。电缆终端均为地面终端。
隧道工程:顶管隧道618 m(含隧道土建及装修工程、通风工程、给排水工程、给排水工程接驳工程、低压配电工程、弱电系统工程)。工作井2个(13.4 m×13.4 m),顶进井深度26.45 m,接收井深度27.89 m。
(4)110 kV配套B线线路工程(电缆部分):从新建电缆终端场Ⅰ~NB125接藤都联线工井位置。新建四回电缆线路长4×1.62 km。B线对应的站点线路为:熙潭甲、乙线双回,熙道线一回,熙谭线一回,共四回路。四回路线路:共1378 m,其中,四回路电缆沟636 m,四回路电缆埋管504 m,四回路电缆水平定向钻拉管196 m,四回路电缆桥架42 m。图1为A市220 kV变电站输变电配套110 kV线路工程效果图。
2 基于7S管理的高压电力电缆施工过程的监理控制要点
2.1 标识管理
对于标识管理,监理需要注意施工现场有没有划分管理区域,责任人是否明确,责任人执行力是否到位;有没有分区标示,标示牌、警示牌、操作牌、小看板是否齐全醒目,布置是否合理;材料堆放是否按区域,是否分类,是否整齐;有没有闲置材料、设备,是否有用途不明之物;现场有没有乱放的个人东西;通道是否干净,是否堆放杂物,堆放的物品有没有和通道平行或成直角堆放等。图2为A市220 kV变电站输变电配套110 kV线路工程标示管理效果图。 2.2 施工过程管理
对于施工过程管理,监理需要注意施工现场的工器具、计量仪器等是否存放有序,是否便于寻找及归位;危险品有否明确标示,灭火器是否有定期点检;走道、临边、洞口标示是否齐全,防护措施是否标准;交叉作业措施是否到位,是否规范;施工机械设备防护措施是否齐全、完整、规范;施工、生活电源线布置是否整齐有序;作业人员的周边环境是否安全,是否有凌乱物件;现场道路是否有交通标示;施工场地是否平整,是否有扬尘,是否有积水等。
2.3 施工周边管理
对于施工周边管理,监理需要注意现场消防器材是否齐全,布置是否合理;现场工人着装是否统一,是否规范;个人安全防护用品是否齐全,使用是否规范;办公区是否与施工区隔离,办公室是否整齐、整洁明亮;施工垃圾、生活垃圾清理是否及时。
2.4 7S监理细则
编制人员要结合工程实际,按技术标准和规程要求编制,审批人把好审批关,未经审批严禁实施。进行安全宣传教育;做好安全技术措施交底;开展班组活动;加强特殊工种管理、设备管理、违章事故处理程序的管理;问题处理应及时有效。督促施工单位加强对员工进行安全教育,检查相关记录,确保安全教育的有效性。对发现的问题,发限期整改单,要求限期整改,并按有关管理规定要求对不符合要求的行为进行处理。在审核施工总平面图布置时,应注意平时布置符合安全卫生、消防要求,满足环境保护的需要。督促相关单位按总体规划要求布置场地。应注意地下、地上管线,场地排水,垃圾、污泥处理,材料堆放,安全距离等。每天对各区域进行巡视检查,发现问题先口头通知该区域责任人进行整改,如整改不及时或不到位,则以书面形式通知施工单位,并要求限时整改,同时进行跟踪整改情况。每周进行定期检查,对存在的问题列出整改清单(文明施工整体视觉形象检查评价表),限时整改,并跟踪整改进度及整改结果。
根据现场7S的执行情况,每月进行一次7S管理效果回顾讨论,对存在的不足之处进行罗列,找出主要问题,分析原因及出现的主要部位,商议形成有效的改进办法,使之在现场行之有效,达到现场文明施工良性循环,并能持之以恒的效果。同时也进一步完善监理对7S管理的办法。
3 A市220 kV输变电配套110 kV线路工程监理示例
3.1 加强设备安装质量的检查措施
监理提前编制了专项的管节进场验收方案,对于不合格的管节要求厂家返厂或者重新修复。现场工人对所有检查不合格的管节钢圈进行焊接加固处理,焊接完成后,对加工处理后的管节钢圈进行重新检查,确保了管节止水胶圈的固定效果合格后方可用于隧道顶管施工。
为了避免后续生产的管节出现同类问题,小组组长组织管节的生产厂家重新召开了技术交底会,明确止水胶圈的安装要求,并且规范管节进场验收的细节工作,制作了管节进场验收标准表格,每批次管节进场前,需各方验收并签名确认。
定位钢圈加固处理后,止水胶圈的位置更加牢固,在管节拼接过程中未发现胶圈脱落现象,监理小组成员对熙悦项目的工地管节进行抽样检查,统计后发现一批次管节(15节)胶圈脱落次数仅为1次,合格率提升到了93.3%,达到了施工目标。隧道贯通后,隧道内的管节内壁接缝处无渗水现象,实现对策实施后,隧道内部整体防水效果提升。
3.2 延长洞口处尾管钢圈、焊接加装双层遇水膨胀带
最后一节管节生产前,小组成员提前与管节生产厂家进行沟通,提出尾管的钢圈加长的具体尺寸和其他要求,确保尾管在和止水环进行密封处理时,可以提供有效的焊接处理工作面。
A市220 kV变电站输变电配套110 kV线路工程工程顶管贯通后,监理小组成员安排工人对尾管和止水环接缝处的钢圈进行了密封处理,采取双层遇水膨胀带沿着整个圆形接触面焊接,焊接完成后检查止水胶条的安装效果,确保密封性。
采取密封处理后,每道接缝处都有了双层防水材料,实现了对策目标,大幅加强了接缝处密封效果,且后续检查发现剪力墙浇筑完成后,隧道洞口处无渗水现场发生,起到了加强防水的效果。图3为双层止水胶条现场安装图。
4 结语
以A市220 kV输变电配套110 kV线路工程为例,详细介绍了A市220 kV输变电配套110 kV线路工程概状,分析了基于7S管理的高压电力电缆施工过程的监理控制要点、施工过程中关于监理事项方面的管理创新做法和技术创新做法,对其他工程具有较强的借鉴性。