以淳安~开化公路淳安段隧道群为背景,从人员、人工费和监控量测交通费等角度,在考虑掌子面多少、隧道交通条件、隧道间距离以及隧道所属合同标段等条件,研究了隧道群施工监控量测组织方案。研究表明:隧道群施工监控量测的最佳组织方案应综合考虑隧道群监控量测项目、掌子面多少、隧道交通条件、隧道间距离及隧道合同标段等因素;在隧道群施工监控量测项目投标前,要重点实地考察隧道群的交通条件、隧道间距离、隧道所属合同标段及施工单位的施工组织等情况。研究成果可为隧道群施工监控量测的投标及组织方案选择提供参考。
Based on the Chun’an-Kaihua highway tunnel section, from the point of personnel, labor cost and monitoring the traffic cost, considering the conditions such as the number of the tunnel face, the traffic conditions of the tunnel, the distance between the tunnels and the bidding section of the tunnel, , Studied the tunnel group construction monitoring measuring organization plan. The research shows that the optimal organization scheme of tunnel group construction monitoring measurement should comprehensively consider such factors as the tunnel group monitoring project, the number of facets, the tunnel traffic conditions, the distance between tunnels and the contract of the tunnel. In the tunnel group construction monitoring Before bidding for the project, it is necessary to focus on the spot investigation of the traffic conditions of the tunnel group, the distance between the tunnels, the contract sections under the tunnel and the construction organization of the construction unit. The research results can provide a reference for the bidding and organizational scheme selection of tunnel group construction monitoring measurement.