柬埔寨甘再水电站项目大坝碾压混凝土超过150万m3,由于当地工业市场十分不发达,混凝土所需的水泥、粉煤灰全部要进口,给施工成本造成巨大增加并且运输组织管理难度巨大。为了减少胶凝材料的进口量,本项目碾压混凝土配合比设计采用了高掺石粉(30%)的方案。工程左岸砂石系统的设计在满足强度、可靠度的前提下,采用近年才兴起的粗砂整形先进工艺来调整控制成品砂的细度模数,确保了成品砂的质量,同时采用了雷蒙磨工艺大规模生产石粉的工艺,在国内外均属首创。
As the local industrial market is underdeveloped, all the cement and fly ash required for concrete will be imported, resulting in a tremendous increase in construction costs and a huge difficulty in the management of transport organizations. In order to reduce the amount of cementitious materials imported, the mix design of this project uses a program of highly doped stone powder (30%). On the premise of meeting the strength and reliability, the design of the left gravel system of the project adopts the advanced technology of grit shaping in recent years to adjust and control the fineness modulus of the finished sand to ensure the quality of the finished sand. At the same time, Grinding process mass production of stone powder process, both at home and abroad are the first.