我厂是1956年开始筹建的一个现代化大型水泥厂。工业建设工程于1958年4月开始施工。主要工程量有土方九十万立方米,石方十七万立方米,混凝土四万三千立方米,机械设备安装九千五百吨,电动机及控制设备安装将近一千台,电缆敷设三十五公里。按照初步设计规定,正式投入生产的时间为1960年6月。在党和上级的正确领导、民主德国专家的无私帮助、设计施工部门和全厂职工的努力下,特别是经过伟大的整风运动和贯彻党的鼓足干劲、力争上游、多快好省地建设社会主义的总路
Our factory is a modern large-scale cement plant that was set up in 1956. Industrial construction began in April 1958. The main works include 900,000 cubic meters of earthwork, 170,000 cubic meters of stone, 43,000 cubic meters of concrete, 9,500 tons of machinery and equipment, nearly 1,000 motors and control equipment, and 30 cables. Five kilometers. According to the preliminary design regulations, the official production time was June 1960. With the correct leadership of the Party and superiors, the selfless help of democratic German experts, the design and construction department, and the efforts of the entire factory staff, especially after the great rectification movement and the implementation of the Party’s dedication, strive for the upper reaches, and build the society more quickly and efficiently. Total Road