施工过程中给排水监理工程师不仅要熟悉规范、规程、标准、图集,更要详细掌握图纸内容,根据自身的水平在审图时把不合理、缺漏问题以及自己不能理解的问题进行一一列举,在设计图纸会审时把审图时发现的问题及时与设计人员沟通,探讨,强化自身对本项目的工作内容的理解与掌握。
Abstract: pre-control, pipe installation, construction organization design review, piping layout, model.
During the construction of water supply and sewerage engineer not only familiar with the norms, rules, standards, Atlas, more detailed understanding of drawings, one one are listed according to their own level in the trial, the unreasonable, missing and I didn't understand the question, in the design drawings to find trial, problems timely communication, and designers to explore, to strengthen their understanding of the contents of this project and grasp of the.
中图分类号:U415.1文献标识码:A
施工过程中严格依据标准规范及图纸进行监督检查。首先
1.孔洞、预埋问题及严格执行隐蔽工程验收制度
1.1由于在工程施工中土建与给排水专业缺乏必要的配合,设计上不够完善,大量的预留预埋洞口位置不准确,后期施工中容易造成打凿洞口等一系列质量缺欠,这样既影响给排水工程施工质量和使用功能,又降低了建筑结构的承载力。因此预留孔洞应当与土建施工同步进行,在土建装好分层模板绑扎钢筋时,按设计图纸在混凝上楼板、梁、墙上标好预留孔、洞、槽等管道及设备的位置标高尺寸,并将预制好的模盒、预埋件固定在附近的钢筋上以保证牢固。不同层同一位置的留孔应吊线保證基本垂直。许多钢套管要求预埋,也同样要调好水平或垂直并固定。尤其雨排水管道预留预埋时一定要确定好标高,防止低于室外检查井的标高同时室外部分也要保证在冻土线下。在浇筑混凝土过程中应有专人配合校对及看管模盒或管件以免移位,尤其要预留好建筑外墙内外管线连接的穿墙管套管,并仔细按图确定好是否刚性套管还是柔性套管。
在施工过程中严格执行隐蔽验收制度。高层施工中给排水管道及设备安装较复杂,施工方必须按设计和规范要求通过监理工程师隐蔽验收。因此阶段钢筋砼工程最主要,承包商往往忽视给排水预埋工作,极易造成预埋、预留不准确或遗留、漏埋。为保证给排水工程质量,监理工程师必须做好预控工作,协调好总包单位与专业施工队之间的关系,要求施工方提前形成整座楼预留、预埋统计表,落实专人负责,以备专业监理工程师在混凝土浇筑前进行核查,同时监理部形成一项制度,项目总监签署混凝土浇灌令时,必须先检查各专业监理工程师对预留预埋报验是否签署意见,同意隐蔽验收的再可以浇筑混凝土,这样确保给排水专业工程预埋预留已按图纸、规范完成。
1.2 套管安装问题
由于施工过程中套管安装不正确造成给水管道穿楼板处发生渗漏问题。给水管道穿过墙壁和楼板时,应设置金属或塑料套管。安装在楼板内的套管,其顶部宜高出装饰地面20mm,安装在卫生间及厨房内的套管,其顶部应高出装饰地面50mm,底部应与楼板底面相平。安装在墙壁内的套管其两端与饰面相平。穿过楼板的套管与管道之间缝隙应用阻燃密实材料和防水油膏填实,端面光滑。穿墙套管与管道之间缝隙宜用阻燃密实材料填实,端面应光滑。管道的接口不得设在套管内。
2、管材、管件及设备的质量控制
工程质量的控制是施工阶段质量控制的重点,材料、设备控制是工程质量的保证的关键阶段。
材料设备进场时,监理工程师必须对施工方提供的质保资料、备案证、业主方或施工单位确定的样品检验合格证清单等进行验收。
建筑给排水采暖所使用的主要材料成品半成品配件器具和设备必须具有中文的质量合格证明文件,规格、型号及性能检测报告应符合国家技术标准和设计要求,主要器具和设备必须有完整的安装使用说明书,进场时应做检查验收,同时施工单位在材料设备运输、保管和施工过程中应采取有效措施防止损坏或腐蚀。
.3 管道安装控制要点
首先认真审核施工单位提交的给排水施工施工组织设计,使用的材料和重点部位的质量控制是否符合设计图纸和规范的要求,然后检查施工单位的项目组成机构是否符合项目管理,以及各阶段组织的人力是否能保证工期的顺利进行,最后看方案内的施工机械是否能适应工程的需要。专项工程还要求施工单位提供专项施工方案,监理工程师在施工工作中应该严格按照通过审核合格的方案进行监督管理。
管道施工时,根据现场实际情况地下室、各楼层走廊及避难层等管线密集部位监理工程师要求施工单位组织各管线单位为保证设备管线布局合理,本着电气管线在水管上,与水管距离要有100mm以上,小管让大管,支管让干管,有压管让无压管的原则布置各管道、管线标高、走向,必要时考虑与装饰装修协调处理等原则对管道管线定位,符合规范和功能使用要求,要求总包单位必须将各个系统统一在一起考虑,进行综合布置,因此监理工程师应详细核对图纸,加强与业主、设计、承包商沟通,审核管线综合布置图进行预先控制,确保管线综合布置图符合图纸和规范及使用功能要求的前提下进行严格监督管理。
按照布置好的管道管线图,各单位有序进行安装。
⑴实行方案先行样板领路,施工单位要严格按施工方案施工图纸进行样板施工,经甲方、监理验收合格后方可大面积施工
⑵管道连接(丝接、焊接、法兰连接、卡套连接等)要符合规范要求,确保正常运行时不渗不漏。施工过程局部出现管线碰撞交叉、冲突时协调处理,必要时与设计及时沟通。
⑶消防喷淋头的安装方向,看是否有吊顶要求,以及距墙、距楼板底的距离要满足规范要求。
⑷消防泵、无负压给水设备等设备的基础位置、尺寸与管道之间的尺寸配合。
⑸埋地管道防锈防腐处理,在管道安装前及回填前及时做好防腐。住宅内排水立管与出户横管连接处要使用2个45度弯头或曲率半径大于4倍的管径的90度弯头,且拐弯处采取设置支墩等固定措施等。
⑹功能性检测,如水压试压、灌水试验、泵的试运转要符合相关标准要求,严格进行验收。
⑺工程进度:考核周进度计划、月进度计划,进度滞后超前进行分析,要求施工单位采取必要措施,确保进度计划合理。
⑻实事求是审核每月施工单位每月的实际完成工程量,根据实际完成的合格工程量予以确认,现场设计变更必须有甲方、设计、监理、施工单位四方单位共同签字予以确认,然后根据合同要求进行工程款支付,投资目标是确保给排水工程造价在合同款内。
⑼工程资料管理:工程资料管理要求施工单位资料齐全、完整、及时、真实,资料要与工程形象进度要同步进行,严禁事后补资料。
4.成品保护:管道安装完成后,应将有管口封闭严密,防止杂物进入,造成管道堵塞
⑴.安装完的管道应加强保护,弯管处加设支墩固定。
⑵.严禁利用管道作为脚手架的支点或安全带的拉点、吊顶的吊点。以防管道变形、接口开裂导致使用时渗漏。
⑶.油漆粉刷前应将管道用纸包裹,以免污染管道。
施工过程中给排水监理工程师不仅要熟悉规范、规程、标准、图集,更要详细掌握图纸内容,根据自身的水平在审图时把不合理、缺漏问题以及自己不能理解的问题进行一一列举,在设计图纸会审时把审图时发现的问题及时与设计人员沟通,探讨,强化自身对本项目的工作内容的理解与掌握。
Abstract: pre-control, pipe installation, construction organization design review, piping layout, model.
During the construction of water supply and sewerage engineer not only familiar with the norms, rules, standards, Atlas, more detailed understanding of drawings, one one are listed according to their own level in the trial, the unreasonable, missing and I didn't understand the question, in the design drawings to find trial, problems timely communication, and designers to explore, to strengthen their understanding of the contents of this project and grasp of the.
中图分类号:U415.1文献标识码:A
施工过程中严格依据标准规范及图纸进行监督检查。首先
1.孔洞、预埋问题及严格执行隐蔽工程验收制度
1.1由于在工程施工中土建与给排水专业缺乏必要的配合,设计上不够完善,大量的预留预埋洞口位置不准确,后期施工中容易造成打凿洞口等一系列质量缺欠,这样既影响给排水工程施工质量和使用功能,又降低了建筑结构的承载力。因此预留孔洞应当与土建施工同步进行,在土建装好分层模板绑扎钢筋时,按设计图纸在混凝上楼板、梁、墙上标好预留孔、洞、槽等管道及设备的位置标高尺寸,并将预制好的模盒、预埋件固定在附近的钢筋上以保证牢固。不同层同一位置的留孔应吊线保證基本垂直。许多钢套管要求预埋,也同样要调好水平或垂直并固定。尤其雨排水管道预留预埋时一定要确定好标高,防止低于室外检查井的标高同时室外部分也要保证在冻土线下。在浇筑混凝土过程中应有专人配合校对及看管模盒或管件以免移位,尤其要预留好建筑外墙内外管线连接的穿墙管套管,并仔细按图确定好是否刚性套管还是柔性套管。
在施工过程中严格执行隐蔽验收制度。高层施工中给排水管道及设备安装较复杂,施工方必须按设计和规范要求通过监理工程师隐蔽验收。因此阶段钢筋砼工程最主要,承包商往往忽视给排水预埋工作,极易造成预埋、预留不准确或遗留、漏埋。为保证给排水工程质量,监理工程师必须做好预控工作,协调好总包单位与专业施工队之间的关系,要求施工方提前形成整座楼预留、预埋统计表,落实专人负责,以备专业监理工程师在混凝土浇筑前进行核查,同时监理部形成一项制度,项目总监签署混凝土浇灌令时,必须先检查各专业监理工程师对预留预埋报验是否签署意见,同意隐蔽验收的再可以浇筑混凝土,这样确保给排水专业工程预埋预留已按图纸、规范完成。
1.2 套管安装问题
由于施工过程中套管安装不正确造成给水管道穿楼板处发生渗漏问题。给水管道穿过墙壁和楼板时,应设置金属或塑料套管。安装在楼板内的套管,其顶部宜高出装饰地面20mm,安装在卫生间及厨房内的套管,其顶部应高出装饰地面50mm,底部应与楼板底面相平。安装在墙壁内的套管其两端与饰面相平。穿过楼板的套管与管道之间缝隙应用阻燃密实材料和防水油膏填实,端面光滑。穿墙套管与管道之间缝隙宜用阻燃密实材料填实,端面应光滑。管道的接口不得设在套管内。
2、管材、管件及设备的质量控制
工程质量的控制是施工阶段质量控制的重点,材料、设备控制是工程质量的保证的关键阶段。
材料设备进场时,监理工程师必须对施工方提供的质保资料、备案证、业主方或施工单位确定的样品检验合格证清单等进行验收。
建筑给排水采暖所使用的主要材料成品半成品配件器具和设备必须具有中文的质量合格证明文件,规格、型号及性能检测报告应符合国家技术标准和设计要求,主要器具和设备必须有完整的安装使用说明书,进场时应做检查验收,同时施工单位在材料设备运输、保管和施工过程中应采取有效措施防止损坏或腐蚀。
.3 管道安装控制要点
首先认真审核施工单位提交的给排水施工施工组织设计,使用的材料和重点部位的质量控制是否符合设计图纸和规范的要求,然后检查施工单位的项目组成机构是否符合项目管理,以及各阶段组织的人力是否能保证工期的顺利进行,最后看方案内的施工机械是否能适应工程的需要。专项工程还要求施工单位提供专项施工方案,监理工程师在施工工作中应该严格按照通过审核合格的方案进行监督管理。
管道施工时,根据现场实际情况地下室、各楼层走廊及避难层等管线密集部位监理工程师要求施工单位组织各管线单位为保证设备管线布局合理,本着电气管线在水管上,与水管距离要有100mm以上,小管让大管,支管让干管,有压管让无压管的原则布置各管道、管线标高、走向,必要时考虑与装饰装修协调处理等原则对管道管线定位,符合规范和功能使用要求,要求总包单位必须将各个系统统一在一起考虑,进行综合布置,因此监理工程师应详细核对图纸,加强与业主、设计、承包商沟通,审核管线综合布置图进行预先控制,确保管线综合布置图符合图纸和规范及使用功能要求的前提下进行严格监督管理。
按照布置好的管道管线图,各单位有序进行安装。
⑴实行方案先行样板领路,施工单位要严格按施工方案施工图纸进行样板施工,经甲方、监理验收合格后方可大面积施工
⑵管道连接(丝接、焊接、法兰连接、卡套连接等)要符合规范要求,确保正常运行时不渗不漏。施工过程局部出现管线碰撞交叉、冲突时协调处理,必要时与设计及时沟通。
⑶消防喷淋头的安装方向,看是否有吊顶要求,以及距墙、距楼板底的距离要满足规范要求。
⑷消防泵、无负压给水设备等设备的基础位置、尺寸与管道之间的尺寸配合。
⑸埋地管道防锈防腐处理,在管道安装前及回填前及时做好防腐。住宅内排水立管与出户横管连接处要使用2个45度弯头或曲率半径大于4倍的管径的90度弯头,且拐弯处采取设置支墩等固定措施等。
⑹功能性检测,如水压试压、灌水试验、泵的试运转要符合相关标准要求,严格进行验收。
⑺工程进度:考核周进度计划、月进度计划,进度滞后超前进行分析,要求施工单位采取必要措施,确保进度计划合理。
⑻实事求是审核每月施工单位每月的实际完成工程量,根据实际完成的合格工程量予以确认,现场设计变更必须有甲方、设计、监理、施工单位四方单位共同签字予以确认,然后根据合同要求进行工程款支付,投资目标是确保给排水工程造价在合同款内。
⑼工程资料管理:工程资料管理要求施工单位资料齐全、完整、及时、真实,资料要与工程形象进度要同步进行,严禁事后补资料。
4.成品保护:管道安装完成后,应将有管口封闭严密,防止杂物进入,造成管道堵塞
⑴.安装完的管道应加强保护,弯管处加设支墩固定。
⑵.严禁利用管道作为脚手架的支点或安全带的拉点、吊顶的吊点。以防管道变形、接口开裂导致使用时渗漏。
⑶.油漆粉刷前应将管道用纸包裹,以免污染管道。